Sub topic 1
What a Project Budget Is For
A project budget is an approved financial plan for completing a defined project. It connects the work the team promises to deliver with the money, timing, and cost limits needed to deliver it. A budget gives the team a reference point for decisions during the project.
Prerequisites
Assume that you understand basic arithmetic and percentages, can read a simple spreadsheet, and know that a project has a scope and a schedule. Scope is the work and results included in the project. A schedule shows when that work should happen.
Estimate, budget, and forecast
These three terms describe different views of project cost:
| Term | Meaning | When it changes |
|---|---|---|
| Estimate | A prediction of what the project may cost | Whenever better information becomes available |
| Budget | The approved cost plan used for control | Through approved change control |
| Forecast | The latest prediction of the final cost | Whenever actual results or remaining work change |
An estimate helps decision-makers decide whether to approve a project. After approval, a selected estimate becomes the budget. The budget is then spread across the schedule to create a time-based baseline. A baseline is the approved plan against which actual performance is compared.
A forecast is different from the baseline. Suppose a project has an approved budget of $20,000, but unexpected rework makes the team believe the final cost will be $22,000. The $20,000 remains the approved baseline unless a change is authorized. The $22,000 is the current forecast. Keeping both values visible shows the difference between the original commitment and the expected result.
Why the budget matters
A useful budget supports four decisions:
- Approval: Sponsors can compare the expected value of the project with its cost.
- Planning: The team can assign money to work packages, which are small groups of related tasks that can be estimated and managed together.
- Control: The project manager can compare planned costs with actual costs and investigate important differences.
- Communication: Stakeholders can see what the project costs, what remains, and whether a decision is needed.
A budget also makes assumptions visible. For example, a budget may assume that a specialist works for 40 hours, that a software license costs $1,200, or that testing occurs in the final month. If an assumption changes, the team can assess its effect instead of treating the new cost as a surprise.
The budget as a management baseline
The budget should be traceable to the scope. A stakeholder should be able to ask, “What are we paying for?” and find the answer in the work breakdown and its cost entries.
A simple structure might look like this:
| Work package | Planned cost | Planned period |
|---|---|---|
| Design | $3,200 | January |
| Development | $10,800 | January–February |
| Testing | $3,500 | March |
The entries in this table form part of the cost baseline. Later chapters will show how to estimate each amount, classify costs, and spread them across time. At this stage, the key point is that a total without a connection to specific work is difficult to defend or control.
What a budget does not do
A budget does not replace a schedule, a scope statement, or a risk register. It does not explain every task or guarantee that funding is available as cash on a particular day. It also does not justify adding work without reviewing the effect on cost and time.
When requested work falls outside the approved scope, treat it as a proposed change. Estimate its cost and schedule effect, obtain the required approval, and update the approved baseline only after that approval. Keep the original baseline for comparison so that the project history remains understandable.
Exercise
A project has an approved budget of $15,000. New information suggests it will finish at $16,500, but no change has been approved. Which number is the baseline, and which is the forecast?
Show answer
The $15,000 amount is still the approved baseline. The $16,500 amount is the current forecast.