Sub topic 7
Spreading the Budget Over Time
Assume you already have approved scope, work packages, cost estimates, and an expected schedule. This chapter shows how to turn a total budget into a time-phased baseline: a plan that states how much the project expects to spend during each period.
A total budget answers, “How much may the project cost?” A time-phased budget also answers, “When will the project need the money?” This view supports cash planning, progress tracking, and early detection of spending problems.
From work packages to periods
Start with the cost of each work package. Then assign each cost to the period in which the work or purchase is expected to happen. Use a consistent period, such as a week or month.
For example, suppose the project has these approved costs:
| Cost category | Total |
|---|---|
| Design | 3,200 |
| Development | 10,800 |
| Testing | 3,500 |
| Software licenses and hosting | 1,800 |
| Contingency reserve | 1,930 |
| **Approved budget** | **21,230** |
The schedule determines when these costs appear. Development may span January through March. Testing may begin in February. A software license may be purchased at the start of the project.
The time-phased plan could look like this:
| Period | Design | Development | Testing | Non-labor | Contingency | Period total |
|---|---|---|---|---|---|---|
| January | 3,200 | 2,000 | 0 | 1,200 | 0 | 6,400 |
| February | 0 | 6,000 | 1,000 | 600 | 0 | 7,600 |
| March | 0 | 2,800 | 2,500 | 0 | 1,930 | 7,230 |
| **Total** | **3,200** | **10,800** | **3,500** | **1,800** | **1,930** | **21,230** |
The column totals must equal the approved budget. If they do not, a cost has been omitted, duplicated, or assigned to the wrong period.
Baseline and cash-flow view
The approved time-phased plan becomes the cost baseline. A baseline is the approved reference used for comparison during execution. Once work starts, record actual costs against the same periods and categories.
The period total shows planned cash use. The cumulative plan shows how much of the budget should have been spent by a given date:
| Period | Planned spend | Cumulative planned spend |
|---|---|---|
| January | 6,400 | 6,400 |
| February | 7,600 | 14,000 |
| March | 7,230 | 21,230 |
A cash-flow view is useful for arranging funding and checking whether invoices or payments are likely to create a short-term cash need. However, the accounting date may differ from the date when work was performed. Decide whether your baseline tracks incurred cost, invoice date, or payment date, and use that rule consistently.
Building a simple time-phased plan
A spreadsheet is often enough. Use one row per work package and one column per period. Add a row for each non-labor item and a separate reserve row. Check that every row total matches its approved cost.
The same calculation can be performed with a small script:
plan = {
"January": {"Design": 3200, "Development": 2000, "Testing": 0,
"Non-labor": 1200, "Contingency": 0},
"February": {"Design": 0, "Development": 6000, "Testing": 1000,
"Non-labor": 600, "Contingency": 0},
"March": {"Design": 0, "Development": 2800, "Testing": 2500,
"Non-labor": 0, "Contingency": 1930},
}
cumulative = 0
for month, costs in plan.items():
period_total = sum(costs.values())
cumulative += period_total
print(f"{month}: planned {period_total:.2f}, "
f"cumulative {cumulative:.2f}")The output should show planned totals of 6,400, 7,600, and 7,230. If the schedule changes, update future allocations through change control rather than silently rewriting completed periods.
Common errors
- Spreading every cost evenly, even when the work or purchase is front-loaded.
- Treating the total budget as a cash requirement for the first period.
- Moving baseline amounts after spending occurs, which hides the original variance.
- Forgetting taxes, subscriptions, procurement lead times, or one-time setup costs.
- Spending contingency without recording the related risk or approved change.
Review the time-phased plan with the people responsible for delivery and finance. They can identify payment timing, resource availability, and contractual costs that a simple task estimate may miss.
Exercise
The planned monthly costs are 6,400 in January, 7,600 in February, and 7,230 in March. What is the planned cumulative spend at the end of February?
Show answer
14,000, calculated as 6,400 + 7,600.