Handling Changes Without Losing the Baseline
Assume you understand work packages, a time-phased budget, actual costs, and variance. This chapter focuses on change control: the process for deciding whether a change belongs in the approved project budget.
Why the baseline must stay stable
A budget baseline is the approved version of the plan. It records how much each work package should cost and when the project expects to spend that money. The baseline gives you a fixed comparison point.
A change request is a proposed adjustment to scope, schedule, cost, or quality. If you overwrite the baseline whenever a change is approved, later reports cannot show whether the original plan was accurate. They can show only the latest plan.
Keep these values separate:
- Original baseline: the approved budget before later changes.
- Current approved budget: the original baseline plus approved changes.
- Actual cost: money already spent.
- Forecast: the expected final cost based on actual cost and remaining work.
- Unapproved request: a possible cost that is not yet part of the approved budget.
An approved change may increase or decrease the current approved budget. An unapproved request must not change either the baseline or the official forecast.
Use a small change-control record
Every request should have an identifier, description, cost effect, schedule effect, decision, and approval date. Record the affected work packages instead of changing the whole project total without an explanation.
| Field | Example |
|---|---|
| Change ID | CR-004 |
| Description | Add export to CSV |
| Affected package | Development |
| Cost effect | +$1,500 |
| Schedule effect | +3 working days |
| Decision | Approved |
| Approver | Project sponsor |
| Effective date | 2026-04-15 |
The approval rule depends on the organization. A project manager may approve small changes, while a sponsor or change board may need to approve larger ones. State the rule before the project needs it.
Follow the change-control workflow
Use this sequence for each request:
- Describe the requested change and its reason.
- Estimate its effect on scope, labor, non-labor costs, contingency, and schedule.
- Check whether the change is already covered by the approved scope or contingency.
- Identify risks, dependencies, and affected work packages.
- Obtain the required approval.
- Update the current approved budget and schedule only after approval.
- Keep the original baseline unchanged.
- Record the change in the next budget report.
Contingency needs careful treatment. If a known risk occurs and the contingency reserve covers it, move the approved amount from the reserve to the affected work package. Record the transfer. Do not silently increase the total budget.
If the request adds new scope, contingency is usually not the right source. The sponsor should approve additional funding, remove other scope, or accept a lower forecast margin.
baseline = {
"Design": 3200.00,
"Development": 10800.00,
"Testing": 3500.00,
}
approved_changes = [
{"id": "CR-004", "package": "Development", "amount": 1500.00},
]
current_budget = baseline.copy()
for change in approved_changes:
current_budget[change["package"]] += change["amount"]
print("Original baseline:", sum(baseline.values()))
print("Current approved budget:", sum(current_budget.values()))
print("Baseline remains:", baseline)The copied dictionary represents a revised approved budget. The baseline dictionary remains unchanged, so a report can show both the original commitment and the effect of CR-004.
Show changes in variance reports
Variance should be interpreted against the correct comparison point. Before approval, compare spending with the original baseline and show the pending request separately. After approval, compare spending with the current approved budget while retaining a column for the original baseline.
A useful report includes:
- Original baseline
- Approved change total
- Current approved budget
- Actual cost
- Estimate to complete
- Forecast at completion
- Variance against the current approved budget
- Pending change requests
This prevents a team from hiding an overrun by approving a change after the cost has already occurred. The report should show when the approval happened and which costs belong to the changed scope.
Exercise
Exercise
A project has a current approved budget of $20,000. A team spends $2,000 on work that belongs to a proposed $1,500 change before approval. What should the budget report show?
Show answer
It should record the $2,000 actual cost against the existing baseline, show the $1,500 request as pending, and flag the resulting variance. Approval later may change the current budget, but it must not erase the original variance or the approval date.