Measuring Variance Against the Baseline
Assume you know basic arithmetic, percentages, spreadsheets, and the difference between project scope and schedule. This chapter uses a cost baseline: the approved, time-phased budget used for comparison. A baseline is not a prediction of what will happen. It is the plan against which you measure performance.
What variance means
Cost variance is the difference between planned cost and actual cost for a defined period or work package. Use one convention consistently:
\[ \text{Cost variance} = \text{Baseline cost} - \text{Actual cost} \]
Under this convention:
- A positive result is favorable because spending is below plan.
- A negative result is unfavorable because spending is above plan.
- Zero means actual spending matches the baseline.
For example, if the baseline for design is $3,200 and the actual cost is $3,600:
\[ 3{,}200 - 3{,}600 = -400 \]
The project has an unfavorable variance of $400. The variance does not explain the cause. It only identifies a difference that needs investigation.
You can also express the difference as a percentage:
\[ \text{Variance percentage} = \frac{\text{Baseline} - \text{Actual}}{\text{Baseline}} \times 100 \]
The design variance is:
\[ \frac{3{,}200 - 3{,}600}{3{,}200} \times 100 = -12.5\% \]
Compare like with like
Compare costs for the same work and the same time period. If the baseline says that $5,000 should have been spent by the end of March, compare it with actual costs recorded through the end of March. Do not compare the full project budget with costs incurred so far.
A useful tracking table includes the work package, baseline, actual cost, variance, and explanation.
| Work package | Baseline to date | Actual to date | Variance | Status |
|---|---|---|---|---|
| Design | $3,200 | $3,600 | -$400 | Unfavorable |
| Development | $5,400 | $5,000 | $400 | Favorable |
| Testing | $0 | $0 | $0 | On plan |
A favorable variance can still require attention. Development may be under budget because work has not started, an invoice is late, or required work was missed. Always compare financial data with progress data.
budget = {"Design": 3200.0, "Development": 10800.0, "Testing": 3500.0}
actual = {"Design": 3600.0, "Development": 5000.0, "Testing": 0.0}
for name in budget:
variance = budget[name] - actual[name]
percentage = variance / budget[name] * 100
status = "favorable" if variance >= 0 else "unfavorable"
print(f"{name}: {variance:.2f} ({percentage:.1f}%), {status}")Investigate the cause
Start with the largest or most urgent variances. Common causes include:
- More hours were needed than estimated.
- An hourly rate or supplier price increased.
- A cost was assigned to the wrong work package.
- An invoice was recorded in a different period.
- Scope changed without an approved baseline change.
- Work is ahead or behind schedule.
Separate timing variance from permanent variance. A timing variance may disappear when a delayed invoice arrives. A permanent variance means the expected total cost has changed.
Move from variance to forecast
Variance is backward-looking. Forecasting uses the variance and current knowledge to estimate the final cost. For each work package:
\[ \text{Forecast at completion} = \text{Actual cost so far} + \text{Estimate to complete} \]
Suppose development has actual costs of $5,000 and needs another $6,200. Its forecast is $11,200. Against a $10,800 baseline, the expected variance is:
\[ 10{,}800 - 11{,}200 = -400 \]
This tells stakeholders that the package is expected to finish $400 over its approved budget, even though it is currently $400 below the amount planned for the full package.
Report the amount, percentage, cause, impact on completion, and proposed action. A short report might state: “Design is $400 over baseline, or 12.5% unfavorable, because review required 5 additional hours. The work is complete, so the forecast remains $3,600. The variance is covered by the approved contingency.”
Exercise
A work package has a baseline of $8,000, actual costs of $6,500, and an estimate to complete of $2,200. What is its current variance and forecast variance?
Show answer
Current variance is $1,500 favorable because $8,000 - $6,500 = $1,500. The forecast is $8,700, so the forecast variance is -$700 unfavorable because $8,000 - $8,700 = -$700.