Sub topic 10
Forecasting the Cost at Completion
Prerequisites and the forecasting model
This chapter assumes that you understand basic arithmetic, percentages, project scope, work packages, and the difference between planned and actual spending.
A project budget is the approved cost baseline. A forecast is your current prediction of what the project will cost when the remaining work is complete. The forecast can change during the project. The baseline should change only through approved change control.
For each work package, use this basic formula:
Forecast at completion = actual cost so far + estimate to complete
The estimate to complete (ETC) is the expected cost of all remaining work. The forecast at completion (FAC), also called the estimate at completion (EAC), combines money already spent with the ETC.
To compare the forecast with the approved budget, calculate:
Cost variance = budget - forecast
A negative variance means that the forecast is higher than the budget. A positive variance means that the forecast is lower than the budget.
Build the forecast from work packages
Forecasting at the work-package level makes the result easier to explain. For each package, record its approved budget, actual cost, and ETC.
| Work package | Budget | Actual cost | ETC | Forecast | Variance |
|---|---|---|---|---|---|
| Design | 3,200 | 3,600 | 0 | 3,600 | -400 |
| Development | 10,800 | 5,000 | 6,200 | 11,200 | -400 |
| Testing | 3,500 | 0 | 3,500 | 3,500 | 0 |
| Total | 17,500 | 8,600 | 9,700 | 18,300 | -800 |
Design has already exceeded its budget by 400. Development has spent less than half its budget, but its remaining work is expected to cost 6,200. Its final forecast is therefore 11,200, which is also 400 over budget.
The total forecast is 18,300 against a budget of 17,500. The project currently shows an expected overrun of 800.
Calculate a work-package forecast
The following script applies the formula to each package:
budget = {
"Design": 3200.0,
"Development": 10800.0,
"Testing": 3500.0,
}
actual = {
"Design": 3600.0,
"Development": 5000.0,
"Testing": 0.0,
}
estimate_to_complete = {
"Design": 0.0,
"Development": 6200.0,
"Testing": 3500.0,
}
total_budget = 0.0
total_forecast = 0.0
for name in budget:
forecast = actual[name] + estimate_to_complete[name]
variance = budget[name] - forecast
total_budget += budget[name]
total_forecast += forecast
print(
f"{name}: forecast {forecast:.2f}, "
f"variance {variance:.2f}"
)
print(f"Total forecast: {total_forecast:.2f}")
print(f"Total variance: {total_budget - total_forecast:.2f}")The most important input is the ETC. Do not calculate it by simply subtracting actual cost from the budget unless the remaining work is unchanged and expected to use the original cost assumptions. Ask the person responsible for the work to review the remaining tasks, rates, quantities, and risks.
Choose an appropriate forecasting method
Use bottom-up forecasting when the team can review the remaining work in detail. This is usually the most useful method for a small or changing project.
Use a performance-based method when reliable cost performance data exists. One simple version is:
Forecast = actual cost + (remaining budget × performance factor)
For example, if the remaining budget is 10,000 and the team is spending 20% more than planned, use a performance factor of 1.20. The remaining forecast becomes 12,000.
Performance-based formulas are useful for repeated work, but they can mislead when a one-time problem has already been corrected. Always explain the assumption behind the formula.
Review variance and take action
A variance deserves investigation, not an automatic budget change. Ask:
- Is the difference caused by timing, such as an invoice arriving early?
- Is work taking more hours than planned?
- Have rates, quantities, or supplier prices changed?
- Is the remaining scope still accurate?
- Does an approved change explain the difference?
- Is the contingency reserve available for a recognized risk?
Separate approved scope changes from performance problems. An approved feature may increase the budget and forecast through change control. An inefficient process may require corrective action without changing the baseline.
Report the budget, actual cost, ETC, forecast, variance, major assumptions, and requested decisions. This gives stakeholders enough information to act without hiding the original baseline.
Exercise
A work package has a budget of 5,000, actual cost of 2,400, and an estimate to complete of 2,900. What are its forecast and variance?
Show answer
The forecast is 5,300 because 2,400 + 2,900 = 5,300. The variance is -300 because 5,000 - 5,300 = -300, so the package is forecast to exceed its budget by 300.