Adding a Contingency Reserve
This chapter assumes that you can break scope into work packages and estimate labor and non-labor costs. It also assumes that you know basic percentages. The earlier cost total is the expected cost of planned work. A contingency reserve covers uncertainty in that plan.
What contingency is for
A contingency reserve is money set aside for identified uncertainty. It covers events that might happen while the approved scope remains the same.
Examples include:
- A development task taking longer than expected.
- A vendor charging more than its initial quote.
- Extra testing caused by a known technical risk.
- A small amount of rework after user acceptance testing.
Contingency is sometimes called a reserve for known unknowns. You know that uncertainty exists, but you cannot predict the exact event or cost.
Contingency is different from a budget estimate and a forecast:
- An estimate predicts what planned work may cost before approval.
- A budget is the approved cost target, including the approved contingency.
- A forecast predicts the final cost using current information and actual spending.
Contingency does not pay for new features or an expanded scope. A scope change requires change control and may need additional funding.
Choose a calculation basis
Start with the direct cost total. Direct costs are costs that you can assign to the project, such as project labor, software licenses, and project hosting.
A simple method applies a percentage:
contingency = cost basis × contingency rate
approved budget = cost basis + contingencyThe cost basis must be documented. For example, you might apply 10% to all direct costs, or apply different rates to different work packages. Do not silently change the basis between estimates.
A percentage works well when the project is small or when detailed risk data is unavailable. A risk-based reserve is better when you have a useful risk register. For each risk, estimate the probability and the cost impact:
expected monetary value = probability × cost impactFor example, a 30% chance of a $2,000 testing problem has an expected value of $600. Add the expected values of relevant risks, then review the result for risks that are related or difficult to quantify.
Apply contingency to a worked budget
Suppose a project has these planned costs:
| Cost group | Amount |
|---|---|
| Labor | $17,500 |
| Software licenses | $1,200 |
| Hosting | $600 |
| Direct cost basis | $19,300 |
With a 10% contingency rate:
contingency = $19,300 × 0.10 = $1,930
approved budget = $19,300 + $1,930 = $21,230The reserve is part of the approved budget, but it should remain visible as a separate line. If you hide it inside work-package estimates, you may spend it without knowing that you are using the reserve.
This Python example calculates the same result:
tasks = [
{"name": "Design", "hours": 40, "rate": 80.0},
{"name": "Development", "hours": 120, "rate": 90.0},
{"name": "Testing", "hours": 50, "rate": 70.0},
]
non_labor = {"Software licenses": 1200.0, "Hosting": 600.0}
contingency_rate = 0.10
labor = sum(task["hours"] * task["rate"] for task in tasks)
direct = labor + sum(non_labor.values())
contingency = direct * contingency_rate
budget = direct + contingency
print(f"Labor: {labor:.2f}")
print(f"Direct costs: {direct:.2f}")
print(f"Contingency: {contingency:.2f}")
print(f"Budget: {budget:.2f}")The output is $17,500.00 for labor, $19,300.00 for direct costs, $1,930.00 for contingency, and $21,230.00 for the budget.
Common errors and controls
A reserve becomes useful only when its rules are clear.
- Do not add contingency to unapproved scope.
- Do not calculate a percentage on a total that already contains contingency.
- Do not treat contingency as free money.
- Do not remove unused reserve from the baseline without recording the decision.
- Do not use the reserve to hide an inaccurate estimate.
Set an owner and an approval rule. For example, a project manager may approve reserve use below $500, while larger uses require sponsor approval. Record the date, reason, amount, and remaining balance whenever the reserve is used.
How reserve use affects the budget
When an approved risk occurs, move the required amount from the reserve into the affected work package or cost category. Keep the original baseline visible. This preserves the difference between the original plan and the current approved plan.
Exercise
A project has a direct cost basis of $24,000 and a contingency rate of 12%. What are the contingency reserve and approved budget? What should happen if the sponsor asks for a new feature?
Show answer
The contingency is $2,880, calculated as $24,000 × 0.12. The approved budget is $26,880. The new feature should go through change control rather than being paid from contingency, because it expands scope.