Sub topic 6
Assembling the Budget Total
Assume you already have a scope breakdown, work-package estimates, and a schedule. You also know the difference between an estimate, a budget, and a forecast:
- An estimate predicts what the work may cost before approval.
- A budget is the approved cost plan used to control the project.
- A forecast is the current prediction of the final cost, based on actual results and remaining work.
This chapter turns cost estimates into one approved budget total.
Start with direct costs
Calculate the cost of each work package separately. Labor cost is usually:
\[ \text{Labor cost} = \text{Hours} \times \text{Hourly rate} \]
Non-labor costs include items such as software licenses, equipment, travel, materials, contractors, and hosting. Add these costs to the labor costs to get the direct cost total.
| Work package or item | Cost type | Amount |
|---|---|---|
| Design labor | Direct labor | $3,200 |
| Development labor | Direct labor | $10,800 |
| Testing labor | Direct labor | $3,500 |
| Software licenses | Direct non-labor | $1,200 |
| Hosting | Direct non-labor | $600 |
In this example, labor costs total $17,500. Non-labor costs total $1,800. The direct cost total is therefore $19,300.
Add indirect costs deliberately
Indirect costs support the project but cannot be assigned easily to one work package. Examples include project-management overhead, shared office space, accounting support, or general information-technology services.
Do not add indirect costs twice. An organization may already include overhead in an hourly labor rate. If the rate includes overhead, adding a separate overhead percentage would inflate the budget.
Keep a record of the rule you use:
- List each indirect cost or allocation method.
- State whether it is already included in labor rates.
- Add only the amount that is not already covered.
- Document the assumptions for approval and later review.
The resulting total before contingency is often called the cost baseline before reserve or the cost estimate, depending on the organization's terminology.
Calculate the budget total
A simple budget structure is:
\[ \text{Budget} = \text{Direct costs} + \text{Indirect costs} + \text{Contingency reserve} \]
The following example has no additional indirect costs. It applies a 10% contingency to the direct cost total.
tasks = [
{"name": "Design", "hours": 40, "rate": 80.0},
{"name": "Development", "hours": 120, "rate": 90.0},
{"name": "Testing", "hours": 50, "rate": 70.0},
]
non_labor = {"Software licenses": 1200.0, "Hosting": 600.0}
contingency_rate = 0.10
labor = sum(t["hours"] * t["rate"] for t in tasks)
direct = labor + sum(non_labor.values())
contingency = direct * contingency_rate
budget = direct + contingency
print(f"Labor: {labor:.2f}")
print(f"Direct costs: {direct:.2f}")
print(f"Contingency: {contingency:.2f}")
print(f"Budget: {budget:.2f}")The output is:
- Labor: $17,500.00
- Direct costs: $19,300.00
- Contingency: $1,930.00
- Budget: $21,230.00
The contingency is not an unexplained extra amount. It is a reserve for identified uncertainty, such as rework, uncertain requirements, or price changes. Its rate and basis should be visible to the approver.
Check the total before approval
Use a simple flow to verify that every cost has a place and that contingency is applied only once.
Before approval, reconcile the total with the scope and schedule. Confirm that every work package has an owner, a cost basis, and a unit such as hours, days, licenses, or items. Check that tax, currency, procurement fees, and indirect costs follow the organization's rules.
Once approved, record the total as the project budget baseline. Later spending is compared with this baseline. If scope changes, do not silently edit the original total. Submit the change for review and record the approved adjustment separately.
Exercise
Direct costs are $19,300, approved indirect costs are $700, and contingency is 10% of the subtotal. What is the budget total?
Show answer
The subtotal is $20,000. Contingency is $2,000, so the budget total is $22,000.