Sub topic 7
Recognizing the eight wastes inside NVA steps
Prerequisites and where this chapter fits
This chapter assumes you can already do the following:
- Read a simple process map.
- Explain what value means from the customer's point of view.
- Apply the three-question test, which asks whether the customer would pay for the step, whether it changes form, fit, or function, and whether it is done right the first time.
A step that fails the test and is not required by a rule or risk control is non-value-added (NVA). Knowing that a step is NVA tells you to act on it. It does not tell you how. The eight wastes are a vocabulary for naming what kind of NVA a step is, and the kind decides which fix to try.
Why name the waste
Calling a step "waste" is too vague to act on. Two NVA steps can need opposite fixes. A 120-minute wait in a queue is solved by changing how work flows. A 15-minute rework loop is solved by finding the cause of the defect. If you only label both "NVA", you will not know where to look.
The eight wastes come from the Toyota Production System, which originally named seven. Lean practitioners added an eighth, unused talent. A common mnemonic is DOWNTIME, built from the first letter of each waste.
| Letter | Waste | What it means |
|---|---|---|
| D | Defects | Work that is wrong and must be fixed or scrapped |
| O | Overproduction | Making more, or sooner, than the next step or customer needs |
| W | Waiting | Work or people idle while something else finishes |
| N | Non-utilized talent | Skills and ideas of people that the process does not use |
| T | Transportation | Moving work or materials between places |
| I | Inventory | Work in progress or stock that sits unprocessed |
| M | Motion | Unneeded movement of people |
| E | Extra processing | Doing more work than the customer requires |
The eight wastes in detail
Defects
A defect is any output that does not meet requirements. The cost is the rework or scrap, plus the inspection and handling that surround it. In a classified step list, defects appear as rework loops such as "Rework defects" and as the second or third pass through a step.
This waste links directly to the third question of the test. A step that is done right the first time can be value-added. The same step done a second time to correct an error is NVA.
Overproduction
Overproduction means producing more than is needed, or producing it earlier than needed. It is often called the worst waste because it causes the others. Extra output must be stored (inventory), moved (transportation), and checked (extra processing).
Office examples include:
- Printing a report nobody reads.
- Preparing a full proposal before the customer has said they want one.
- Processing a batch of 200 invoices when only 20 are due.
Waiting
Waiting is idle time for work or for people. Work waits for an approval, a signature, a system, or a batch to fill. People wait for work to arrive from upstream.
Waiting is usually the largest source of lead time. Later in this chapter, the example process spends 120 of its 200 minutes in one queue. For most office and service processes, the work is actually being touched for a small fraction of the time it is in the system.
Non-utilized talent
Non-utilized talent is the waste of not using what people know. It happens when skilled staff do routine checking, when employees are not asked for improvement ideas, or when decisions are pushed up to managers who know less than the person doing the work.
It is the only one of the eight wastes that does not show up as a step on the map. You find it by asking who does each step and whether that person's skills are needed for it.
Transportation
Transportation is moving work, materials, or information from one place to another when the move does not change the product. In a factory this means carrying parts between buildings. In an office it means forwarding a file through several mailboxes, or moving a request between systems by hand.
Inventory
Inventory is work waiting between steps: a pile of unprocessed forms, an email inbox, a backlog of tickets, or finished goods in a warehouse. Inventory and waiting are two views of the same situation. The work in the pile is inventory. The time it spends there is waiting.
Little's Law links them: average lead time equals work in progress divided by throughput. If the number of items in progress doubles and the completion rate stays the same, lead time doubles.
Motion
Motion is unnecessary movement by people: walking to a printer, searching for a file, switching between several screens, or re-entering data into a second application. Motion is movement within one person's work area. Transportation is movement of the work itself.
Extra processing
Extra processing is doing more than the customer requires. Examples include polishing a document beyond its purpose, collecting information that nobody uses, getting three approvals where one would be enough, and entering the same data in two systems.
Mapping the wastes to a step list
The following diagram shows how the NVA classification leads to the waste type and then to the likely fix.
Notice that the eight wastes only apply after the BNVA check. A step that a regulation requires is not waste in the sense used here, even if it looks like extra processing. Whether that requirement is itself necessary is a separate question, covered in the chapter on challenging business-necessary steps.
Worked example: tagging waste on a step list
The order-to-ship process from earlier chapters has seven steps. Here we tag each NVA step with its waste type and total the time by waste. Only steps classified NVA receive a waste tag.
from collections import defaultdict
steps = [
# (name, minutes, class, waste type or None)
("Enter order", 5, "BNVA", None),
("Wait in credit approval queue", 120, "NVA", "Waiting"),
("Credit check", 10, "BNVA", None),
("Assemble product", 30, "VA", None),
("Rework defects", 15, "NVA", "Defects"),
("Regulatory inspection", 10, "BNVA", None),
("Pack and label", 10, "VA", None),
]
waste_minutes = defaultdict(int)
for name, minutes, cls, waste in steps:
if cls == "NVA":
if waste is None:
raise ValueError(f"NVA step needs a waste type: {name}")
waste_minutes[waste] += minutes
elif waste is not None:
raise ValueError(f"Only NVA steps get a waste type: {name}")
nva_total = sum(waste_minutes.values())
for waste, minutes in sorted(waste_minutes.items(), key=lambda kv: -kv[1]):
print(f"{waste}: {minutes} min ({minutes / nva_total:.0%} of NVA time)")
print(f"Total NVA: {nva_total} min")Running this prints:
Waiting: 120 min (89% of NVA time)
Defects: 15 min (11% of NVA time)
Total NVA: 135 minThe checks inside the loop enforce the rule from the previous section. A BNVA or VA step with a waste tag, or an NVA step without one, is a classification error and the script stops.
The result tells you where to look first. Waiting accounts for 89% of the NVA time, so a change to the credit approval flow will do more than any fix to the rework loop. The rework still matters, because defects also cost customer trust and can hide further problems. But the numbers show where the largest gain is.
Finding waste that is not on the map
Some waste is not visible as a separate step. These are common places to look.
- Inside a VA step. A step can be value-added overall but contain wasted motion. An assembler who walks to a shelf for each part is adding value only while assembling.
- Between steps. Queues, handoffs, and inboxes are rarely drawn as boxes. Add them to the map as their own steps, as the "Wait in credit approval queue" step is above.
- In the people. Non-utilized talent needs interviews or observation. Ask the people doing the work what they would change.
- In repeated passes. If the same item appears twice on the map, the second pass is usually defects or extra processing.
Gotchas and judgment calls
Waste types overlap, and the same step can fit more than one label. A pile of unprocessed forms is inventory and waiting. Re-entering data is motion and extra processing. Do not spend effort on perfect labeling. Choose the label that points to the most useful fix and record the choice so the team agrees.
A step that is waste in one process can be essential in another. A second inspection of a product that has already passed a statistically reliable check is likely extra processing. The same inspection on a medical device may be a required risk control, which makes it BNVA.
Do not blame people for waste. Most waste is built into the process design, such as batching rules, approval limits, and system layouts. The fix is to change the process, not to ask people to work faster.
Exercise
A claims team receives 300 claim forms each Monday and processes them as one batch. A form that arrives on Tuesday waits until the next Monday. Which waste types are present, and which is the more useful label for deciding on a fix?
Show answer
Waiting and inventory are both present, since forms sit unprocessed and the time spent sitting is waiting. Overproduction by batching also contributes, because work is released in a large batch rather than as needed. The most useful label is waiting caused by batching, because it points to the fix: process claims in smaller batches or continuously, so that a Tuesday form is handled on Tuesday.
Exercise
An operator walks 40 meters to a supply cabinet three times per shift to fetch the same fasteners. Is this transportation or motion? Name one change.
Show answer
It is motion, because a person is moving rather than the product being moved. One change is to keep a small supply of the fasteners at the workstation and refill it once per shift.
Exercise
A process step is flagged by a team member as "extra processing" because a supervisor re-checks every signed form. A regulation requires a second signature on forms above a set value. How should you classify the step, and what should you do before removing it?
Show answer
Classify it as BNVA, not as waste, because a rule requires it, at least for forms above the threshold. Before removing anything, confirm exactly which forms the regulation covers. If the supervisor also re-checks forms below the threshold, that part is extra processing and can be challenged.