Sub topic 10
Measuring process cycle efficiency
This chapter assumes you can classify a step as value-added (VA), non-value-added (NVA), or business-necessary non-value-added (BNVA) with the three-question test. It also assumes you have a process map with a time recorded for each step. Here you will turn those classifications into one number, process cycle efficiency, and learn to read it.
What process cycle efficiency measures
Process cycle efficiency (PCE) is the share of a process's total elapsed time that is spent on value-added work:
PCE = value-added time ÷ lead time
- Lead time is the elapsed time from when a work item enters the process until it is delivered. It includes waiting.
- Value-added time is the time spent in steps that pass the three-question test.
Both values must be in the same unit and describe the same work item. If your VA time is in minutes of touch time, lead time must be in elapsed minutes, not working minutes.
A PCE of 20% means that for every five minutes an item is in the process, one minute transforms it in a way the customer pays for. The other four minutes are waiting, rework, checking, or approval.
PCE is not a measure of how hard people work. A team can be fully busy and still have a PCE of 3%, because most of the lead time is the item sitting in queues, where nobody is working on it.
Getting the inputs right
Lead time
Lead time covers every minute between the start and end events you define. Waiting counts. In the example below, the 120-minute wait in the credit approval queue is the largest single block of lead time, even though nobody does anything during it.
Define the start and end events before you collect any data. "Order received" to "order shipped" gives a different lead time than "order received" to "customer has the product". Pick the boundary that matches what the customer experiences, and use it in every before-and-after comparison.
Value-added time
Add up only the time of steps classified VA. BNVA time is not value-added, however necessary it is. This is the most common source of disagreement when teams compute PCE. Counting the regulatory inspection as value-added makes the number look better but hides the question of whether the inspection could be done more cheaply.
Lead time from flow data
When you cannot time each item, you can estimate average lead time from queue data using Little's Law:
lead time = work in process ÷ throughput
If 50 orders are in the process at any time and 0.25 orders are completed per minute, the average lead time is 50 ÷ 0.25 = 200 minutes. This shows why reducing work in process (WIP) shortens lead time without anyone working faster. It also gives you a cross-check. If the sum of your step times is far from WIP ÷ throughput, you have missed a wait or a rework loop.
A worked calculation
Here is the order process from the classification examples, with each step's time and class.
| Step | Minutes | Class |
|---|---|---|
| Enter order | 5 | BNVA |
| Wait in credit approval queue | 120 | NVA |
| Credit check | 10 | BNVA |
| Assemble product | 30 | VA |
| Rework defects | 15 | NVA |
| Regulatory inspection | 10 | BNVA |
| Pack and label | 10 | VA |
The totals by class are VA 40 minutes, BNVA 25 minutes, and NVA 135 minutes. Lead time is 200 minutes, so PCE is 40 ÷ 200 = 20.0%.
The chart shows where the improvement opportunity is. The NVA slice is more than two-thirds of the lead time, and one step, the queue, is most of it.
Calculating PCE in code
The function below sums minutes by class, computes lead time, and returns PCE. It then compares three scenarios. In the improved scenario the queue is cut from 120 to 30 minutes and rework is removed. In the third scenario assembly is made faster, from 30 to 20 minutes.
from collections import defaultdict
def summarize(steps):
totals = defaultdict(int)
for _, minutes, cls in steps:
totals[cls] += minutes
lead_time = sum(totals.values())
pce = totals["VA"] / lead_time if lead_time else 0.0
return dict(totals), lead_time, pce
baseline = [
("Enter order", 5, "BNVA"),
("Wait in credit approval queue", 120, "NVA"),
("Credit check", 10, "BNVA"),
("Assemble product", 30, "VA"),
("Rework defects", 15, "NVA"),
("Regulatory inspection", 10, "BNVA"),
("Pack and label", 10, "VA"),
]
improved = [
("Enter order", 5, "BNVA"),
("Wait in credit approval queue", 30, "NVA"),
("Credit check", 10, "BNVA"),
("Assemble product", 30, "VA"),
("Regulatory inspection", 10, "BNVA"),
("Pack and label", 10, "VA"),
]
faster_assembly = [
(name, 20 if name == "Assemble product" else minutes, cls)
for name, minutes, cls in baseline
]
scenarios = [
("Baseline", baseline),
("Shorter queue, no rework", improved),
("Faster assembly only", faster_assembly),
]
for label, steps in scenarios:
totals, lead_time, pce = summarize(steps)
print(f"{label}: lead time {lead_time} min, "
f"VA {totals.get('VA', 0)} min, PCE {pce:.1%}")Running it prints:
Baseline: lead time 200 min, VA 40 min, PCE 20.0%
Shorter queue, no rework: lead time 95 min, VA 40 min, PCE 42.1%
Faster assembly only: lead time 190 min, VA 30 min, PCE 15.8%The third line is a deliberate surprise. Making a value-added step faster lowers the numerator and the denominator by the same amount, so PCE falls. The customer still gets the product 10 minutes sooner, which is a real gain. PCE rewards removing non-value-added time, not speeding up value-added work.
Reading the number
Teams often ask what a good PCE is. The answer depends heavily on the kind of work.
- Manufacturing and other physical flow processes often have long waits between operations, so a PCE in the low single digits is common before improvement.
- Transactional processes such as approvals, claims, and loan applications are usually the lowest, often under 5%, because work spends most of its time waiting in someone's queue.
- Commonly quoted Lean Six Sigma rules of thumb put "world-class" PCE at 25% or higher for transactional work and higher for manufacturing. Treat these as rough directions, not targets. Your own baseline and trend matter more.
A low PCE is not a failure of the people. It usually points to batching, handoffs, approvals, or long queues, which are system design problems.
Edge cases and measurement traps
Averages hide variation
The average lead time can look acceptable while some items take ten times longer. Report the median and a high percentile such as the 90th, along with the average. If the customer experiences the slow tail, an average of PCE across all items misleads.
Parallel steps
If two steps run at the same time, lead time includes only the longer one, because that path determines when the item finishes. Do not add the times of parallel steps to the lead time. If one parallel branch is VA and the other is NVA, decide which branch is on the critical path before you assign time.
Rework loops
A rework step that happens on only some items must be weighted. If 30% of orders need 50 minutes of rework, the expected rework time per order is 0.3 × 50 = 15 minutes, which matches the 15 minutes in the example. Use this weighted figure when you calculate average lead time. When you calculate PCE for a single order that needed rework, use its actual time.
Rework also costs VA time
When a VA step is done wrong the first time, the redone work does not count as value-added, because the step failed the "right the first time" question. Counting the first attempt as VA and the redo as NVA is a reasonable approach if the first attempt's output is scrapped, but state your rule and use it consistently.
Elapsed time versus working time
Calendar waiting over a weekend counts in elapsed lead time. Many teams measure in working hours instead. Either choice is valid, but mixing them in one calculation will produce wrong results.
Small samples
Timing one order on a quiet day gives a misleading baseline. Collect enough items across different days and volumes to cover normal variation. Timing from system timestamps is more reliable than asking people to estimate.
Using PCE to choose what to improve
PCE tells you how much of the lead time is available to improve, and the class breakdown tells you where to look.
- Rank NVA time by step. The largest block, usually a queue, offers the biggest reduction in lead time.
- Check BNVA steps next. They cannot simply be deleted, but their time may be reduced, automated, or combined with another step.
- Improve VA steps last when your goal is PCE, though you may still improve them for cost or quality.
The next chapters in this tutorial cover how to challenge BNVA steps and how to decide what to eliminate, reduce, simplify, or keep.
Exercise
A claims process has a lead time of 240 minutes. Its steps are: 20 minutes of data entry (BNVA), 150 minutes waiting in a review queue (NVA), 40 minutes of assessment (VA), 10 minutes of required compliance sign-off (BNVA), and 20 minutes of correcting data entry errors (NVA). What is the PCE? What is it if the queue is cut to 30 minutes?
Show answer
VA time is 40 minutes and lead time is 20 + 150 + 40 + 10 + 20 = 240 minutes, so PCE = 40 ÷ 240 = 16.7%. With the queue at 30 minutes, lead time is 120 minutes and PCE = 40 ÷ 120 = 33.3%.
Exercise
A team speeds up a value-added step from 30 to 20 minutes in a process with a 200-minute lead time. They report that the process is better, but PCE dropped. Explain why, and say whether the team's improvement was real.
Show answer
VA time fell from 30 to 20 and lead time fell from 200 to 190... but the starting VA time was 40 in the example; in this process the drop in VA time is 10 minutes. Both numerator and denominator fall by 10 minutes, so the ratio falls. The improvement was real because items now reach the customer 10 minutes sooner. PCE is not a measure of speed. It shows how much of the time is VA, so it falls when only VA time is shortened.
Exercise
A process has 80 items in progress and completes 0.5 items per minute on average. Using Little's Law, what is the average lead time? If the team halves WIP to 40 items without changing throughput, what happens to lead time and, assuming VA time stays at 32 minutes, to PCE?
Show answer
Lead time = 80 ÷ 0.5 = 160 minutes, so PCE = 32 ÷ 160 = 20.0%. With WIP at 40, lead time = 40 ÷ 0.5 = 80 minutes and PCE = 32 ÷ 80 = 40.0%. Halving WIP halves lead time and doubles PCE, because the VA time is unchanged.