Sub topic 12
Deciding What to Eliminate, Reduce, Simplify, or Keep
This chapter assumes you can already classify a step as value-added (VA), non-value-added (NVA), or business-necessary non-value-added (BNVA). It also assumes you can total time by class and compute process cycle efficiency (PCE, which is value-added time divided by lead time). Here you turn that classified map into decisions.
From classification to action
A classified map says what each step is. It does not say what to do about it. Each step gets one of four actions.
| Action | Applies to | Meaning |
|---|---|---|
| Eliminate | NVA steps | Remove the step and the need for it. |
| Reduce | NVA and BNVA steps | Keep the step but cut its time, frequency, or volume. |
| Simplify | BNVA steps, sometimes NVA | Keep the purpose but use fewer handoffs, fields, approvals, or tools. |
| Keep | VA steps and BNVA steps with a firm requirement | Leave the step as it is. |
Classification limits the choices. A pure NVA step has no customer or rule behind it, so elimination is the default. A BNVA step exists because of a regulation, contract, or risk control, so you cannot delete it without dealing with that requirement. A VA step is normally kept, although you can still make it faster.
A decision flow
The flow below asks the questions in order. The order matters because each question rules out the more drastic actions.
Prioritizing: where the time is
Do not work through the map from top to bottom. Rank steps by how much lead time they could give back, then adjust for effort and risk.
Use three filters:
- Time at stake. In most processes a few waiting steps hold most of the lead time. Waiting is NVA time, and it usually dwarfs every handled step.
- Effort and cost. A step that costs little to change and saves a lot comes first. A step that needs a system rebuild for a few minutes of savings comes later.
- Risk. Anything that touches a regulation, a safety control, or a contract needs sign-off before you change it. Risk does not forbid change. It sets how much evidence you need first.
Take the seven-step order process from the earlier chapters. Lead time is 200 minutes, VA time is 40 minutes, and PCE is 20.0%. The queue before credit approval holds 120 of those 200 minutes, so it is where you start.
Choosing the action for each kind of step
Pure NVA steps: eliminate the cause, not the symptom
Rework (15 minutes in the example) is NVA because the first pass was not right. Deleting the rework step does not remove the defect. The defect would ship, or the work would reappear somewhere else. Eliminating rework means fixing the cause upstream, for example a poor assembly instruction or a missing check at the source. Until the cause is gone, treat the step as reduced, not eliminated.
Waiting works the same way. A queue is not a task someone performs. It is the visible result of batching, approvals that arrive late, or uneven workload. To eliminate it you change the flow: approve small orders automatically, release work in smaller batches, or add capacity at the bottleneck.
BNVA steps: first test the requirement
A BNVA step earns its place only through a requirement you can name. Trace it to a source: a regulation, a contract clause, or a documented risk. If you cannot find the source, you have probably found an NVA step that someone relabeled as necessary, a habit left over from an old incident or from a system that no longer exists.
If the requirement is real, aim at the way the step is done, not at the step itself:
- Simplify by removing duplicate data entry, merging two approvals into one, or pre-filling fields.
- Reduce by applying the control to a risk-based sample or to orders above a threshold, when the rule allows it.
- Automate the control while keeping its evidence, such as a system credit check with a logged result.
In the example, the credit check takes 10 minutes. The rule is probably "check credit before shipping," not "have a person check credit by hand." Automating the check keeps the control and shortens the time.
The regulatory inspection (10 minutes) is different. If the regulation requires it and gives no sampling option, the correct action is to keep it. Keeping a step is a valid result of the analysis, not a failure to improve.
VA steps: keep, and improve separately
VA steps are kept. Shortening a VA step is a different kind of work, such as better tooling or a better method, and it raises throughput, not PCE directly. Do not shorten a VA step by lowering quality, because the step is VA only while it is done right the first time.
Projecting the result
Before committing to changes, estimate their effect. The script below records an action and a target time for each step, then compares lead time and PCE before and after, and ranks steps by minutes saved.
steps = [
# (name, minutes now, class, action, minutes after)
("Enter order", 5, "BNVA", "simplify", 2),
("Wait in credit approval queue", 120, "NVA", "reduce", 30),
("Credit check", 10, "BNVA", "simplify", 2),
("Assemble product", 30, "VA", "keep", 30),
("Rework defects", 15, "NVA", "eliminate", 0),
("Regulatory inspection", 10, "BNVA", "keep", 10),
("Pack and label", 10, "VA", "keep", 10),
]
before = sum(s[1] for s in steps)
after = sum(s[4] for s in steps)
va_before = sum(s[1] for s in steps if s[2] == "VA")
va_after = sum(s[4] for s in steps if s[2] == "VA")
print(f"Lead time: {before} -> {after} min")
print(f"PCE: {va_before / before:.1%} -> {va_after / after:.1%}")
print("Ranked by minutes saved:")
for name, now, cls, action, new in sorted(steps, key=lambda s: s[1] - s[4], reverse=True):
if now - new > 0:
print(f" {name}: {action}, saves {now - new} min")The output shows lead time falling from 200 to 84 minutes and PCE rising from 20.0% to 47.6%. The ranking lists the queue first at 90 minutes, then rework at 15, the credit check at 8, and order entry at 3. VA time stays at 40 minutes. The whole gain in PCE comes from shrinking the denominator.
Edge cases and judgment calls
- A step is NVA to the customer but critical to another team. Trace it. It may feed a later step that is truly required, in which case it is BNVA. If nothing downstream consumes its output, treat it as NVA.
- Eliminating a step moves the problem. Removing an inspection without improving the process upstream sends defects to the customer. Check the cost of failure before and after.
- Reduction by sampling needs rule support. Some requirements allow risk-based sampling, and others require every unit. Confirm which applies before you change the frequency.
- One change can alter several steps. An automatic credit approval for small orders shortens the queue and the check together. Estimate the combined effect, not the sum of separate guesses.
- Estimates are not measurements. The target times in the script are hypotheses. After the change, measure lead time again and recompute PCE.
Recording the decision
On the process map, add the action beside each step's class and time, for example "BNVA, 10 min, simplify." Add the owner and the evidence for any BNVA step you keep, such as the regulation clause or contract number. A later reader can then see why a step survived and can recheck the requirement when the rules change.
Exercise
A 20-minute manager sign-off sits before every purchase order. Nobody can point to a policy that requires it. A reviewer says it exists "because of an audit finding three years ago." What class and action do you assign, and what do you do first?
Show answer
Treat it as unproven BNVA, which is probably NVA. First trace the audit finding to a current, written control. If a real requirement exists, keep the control but simplify or reduce it, for example by approving only orders above a spending threshold. If the finding was closed or the control has been replaced, eliminate the step.
Exercise
A process has a lead time of 150 minutes and a VA time of 30 minutes. A change removes 60 minutes of waiting and leaves VA time unchanged. What are the PCE before and after?
Show answer
Before, PCE is 30 / 150 = 20.0%. After, lead time is 90 minutes, so PCE is 30 / 90 = 33.3%.
Exercise
Why is "delete the rework step" usually the wrong way to eliminate rework?
Show answer
Rework exists because of defects produced earlier. Deleting the step leaves the defects in place, so they reach the customer or reappear elsewhere. The cause has to be fixed upstream. Until then the step is reduced, not eliminated.