Sub topic 8
Lead time, cycle time, and value-added time
This chapter assumes you can read a simple process map and that you know the three step classes: value-added (VA), non-value-added (NVA), and business-necessary non-value-added (BNVA). It defines the three time measures that turn those classes into numbers. The next chapters use these numbers to annotate maps and compute process cycle efficiency.
Why time is the common unit
A process map tells you what happens. A time measure tells you how long the customer waits and where that waiting comes from. Time works well as a common unit for three reasons:
- Every step has a duration, so steps of very different kinds can be added together.
- Customers feel time directly. A late delivery is a failure they notice.
- Waiting is usually the largest hidden cost, and it rarely appears as a box on a map.
Three measures do most of the work: lead time, cycle time, and value-added time. People mix them up often, so each gets a precise definition here.
Lead time
Lead time is the elapsed time from the moment a request enters the process to the moment the customer receives the result. It includes working time, waiting time, and any time the work spends in a queue or on hold.
Two points matter when you measure it:
- The clock starts and stops at agreed boundaries. For an order process, you might start when the customer submits the order and stop when the package is delivered. Write those two events down before you measure anything.
- It is elapsed (calendar or clock) time, not effort. If an order sits overnight, the night counts, unless you have agreed to measure only in working hours. Whichever you choose, use it for every step.
Lead time is what the customer experiences. A process with 40 minutes of work can still have a lead time of three days.
Cycle time
Cycle time is the time one step takes to produce one unit of output, measured from when work on it begins to when it is finished. The word is used in two ways, and you should check which one a colleague means:
- Step cycle time: how long one step takes for one item. "Credit check takes 10 minutes."
- Process cycle time: the elapsed time from the start to the end of the whole process for one item. Some teams use this as another name for lead time.
In this tutorial, "cycle time" means step cycle time, and the whole-process measure is called lead time. That keeps the two terms from overlapping.
Cycle time covers only the time someone or something is actually working on the item. Time in a queue before the step starts is not part of it. That wait belongs to lead time, but not to any step's cycle time.
Value-added time
Value-added time is the part of the lead time spent on steps classified as VA. It is the sum of the cycle times of the VA steps, and nothing else. Time spent on NVA and BNVA steps does not count, and neither does waiting.
This is why classification has to come first. You cannot compute value-added time until each step has passed the three-question test from the earlier chapter.
A step can be partly value-added. Assembling a product may include 25 minutes of real assembly and 5 minutes of searching for a tool. Where the split is clear, record the 25 minutes as VA and the 5 as NVA. Where it is not, split the step into two on the map.
How the three measures relate
For one item, lead time is the sum of everything that happens to it, and it can be split by class:
lead time = VA time + BNVA time + NVA time
NVA time includes two kinds of time:
- Activity time, such as rework, which someone performs.
- Idle time, such as queues and waiting for approval, when nobody works on the item.
The split shows where improvement effort should go. In most processes, idle time is far larger than any activity time, so reducing queues often beats speeding up individual tasks.
A worked example
Here is the order process from the earlier chapter, with the time for each step and its class.
| Step | Minutes | Class |
|---|---|---|
| Enter order | 5 | BNVA |
| Wait in credit approval queue | 120 | NVA |
| Credit check | 10 | BNVA |
| Assemble product | 30 | VA |
| Rework defects | 15 | NVA |
| Regulatory inspection | 10 | BNVA |
| Pack and label | 10 | VA |
Adding the minutes by class gives:
- VA time: 30 + 10 = 40 minutes
- BNVA time: 5 + 10 + 10 = 25 minutes
- NVA time: 120 + 15 = 135 minutes
- Lead time: 40 + 25 + 135 = 200 minutes
The credit approval queue alone is 60% of the lead time, and no one is working on the order while it waits. The code below computes these totals and also separates idle time from activity time.
from collections import defaultdict
# (step name, minutes, class, is_idle)
steps = [
("Enter order", 5, "BNVA", False),
("Wait in credit approval queue", 120, "NVA", True),
("Credit check", 10, "BNVA", False),
("Assemble product", 30, "VA", False),
("Rework defects", 15, "NVA", False),
("Regulatory inspection", 10, "BNVA", False),
("Pack and label", 10, "VA", False),
]
by_class = defaultdict(int)
idle = 0
for name, minutes, cls, is_idle in steps:
by_class[cls] += minutes
if is_idle:
idle += minutes
lead_time = sum(by_class.values())
print("Lead time:", lead_time, "min")
for cls in ("VA", "BNVA", "NVA"):
share = by_class[cls] / lead_time
print(f"{cls}: {by_class[cls]} min ({share:.0%})")
print(f"Idle (queue) time: {idle} min ({idle / lead_time:.0%})")Running it prints a lead time of 200 minutes, with VA at 40 minutes (20%), BNVA at 25 minutes (12%, rounded from 12.5%), and NVA at 135 minutes (68%, rounded from 67.5%). Idle time is 120 minutes (60%).
Measuring time in practice
You can get the numbers in three ways, and they differ in quality.
- Direct observation (a time study). You stand at the process with a clock and record start and end times for each step. This is the most reliable method and the most costly.
- System timestamps. Workflow tools, ticketing systems, and order systems record when an item changed status. These are cheap and cover many items, but they show state changes, not whether someone was actually working.
- Estimates from the people doing the work. These are fast and useful for a first draft, but people tend to remember the work and forget the waiting.
Whichever method you use, follow these habits:
- Measure many items, not one. Times vary, so record a sample and use the average and the range.
- Record the wait before each step separately from the step itself.
- Use one unit (minutes, hours, or days) for the whole map, and one clock (clock time or working time).
Edge cases and common errors
Mixing clock time and working time
An item that waits from Friday 5 pm to Monday 9 am has waited 64 clock hours but 0 working hours. If you measure lead time in clock hours and cycle time in working hours, the ratios are wrong. Pick one basis for everything.
Treating cycle time as lead time
A team may report that "the process takes 10 minutes" when they mean the step cycle time. The customer waited two days. Always ask whether the figure includes queues.
Counting batch time as work
If a step processes 50 items together in a 100-minute run, the cycle time per item is not 100 minutes. Each item still waits for the whole batch, so its lead time includes the full 100 minutes plus any time it waited for the batch to fill. Record both the per-item processing time and the batch wait.
Parallel steps
When two steps run at the same time, lead time grows only by the longer one. Adding both durations overstates lead time. On a map with parallel paths, follow the longest path (the critical path) for lead time. You can still sum the VA time across all paths, but then the classes will no longer add up to lead time. State which you are reporting.
Averages hiding variation
A step averaging 10 minutes might take 3 minutes on most items and 60 on a few. The few cause late deliveries. Report the range or a high percentile alongside the average.
Connecting the measures to what comes next
You now have the inputs for the next chapters. Classification gives each step a class. Time data gives each step a duration. Together, they let you annotate the map and compute the ratio of value-added time to lead time, called process cycle efficiency.
Exercises
Exercise
A claim takes 2 hours to review (VA), then waits 30 hours in an approval inbox, then takes 1 hour to approve (BNVA). What are the lead time, the VA time, and the share of lead time that is idle?
Show answer
Lead time is 2 + 30 + 1 = 33 hours. VA time is 2 hours. The idle time is the 30-hour wait, which is 30 / 33, about 91% of lead time.
Exercise
A machine runs 20 parts as one batch in 40 minutes. A team says the cycle time per part is 2 minutes. Why is that misleading for lead time, and what should you record?
Show answer
Each part waits for the whole 40-minute batch, so each part's lead time includes all 40 minutes plus any time spent waiting for the batch to fill. Record the 2-minute per-part processing time and, separately, the batch wait and batch run time, so the queue stays visible.
Exercise
Two review steps run in parallel. One takes 20 minutes and the other takes 35 minutes. By how much do they extend lead time?
Show answer
They extend lead time by 35 minutes, the longer of the two. The 20-minute review runs at the same time and adds nothing to the elapsed time, though it still counts as work done.