Sub topic 4
Non-value-added steps
This chapter assumes you can read a simple flowchart and know what a process step is. It also assumes you know that a customer can be internal or external. It covers non-value-added steps: what they are, where they hide, and why they are usually most of a process. It does not cover the formal classification test, the eight wastes, or process cycle efficiency in detail. Later chapters treat those.
What a non-value-added step is
A non-value-added (NVA) step is a step that consumes time, money, or effort but does not add anything the customer is willing to pay for. The customer is the person or group who receives the output of the process. For an internal process, that may be the next department.
The definition has three parts:
- It is judged from the customer's side, not the organization's side. A step can matter a great deal to your team and still be NVA.
- It is about the step, not the person doing it. A hard-working employee can spend a full day on NVA steps.
- It does not mean "useless" or "avoidable today". It means the customer would not choose to pay for it if given the choice.
Lean and Six Sigma practitioners often shorten value-added to VA and non-value-added to NVA. The related term BNVA, business-necessary non-value-added, marks NVA steps that a rule, contract, or risk control requires. This chapter treats NVA as the broader family. The next chapters separate the pure waste from the necessary steps.
Why NVA matters: most of the clock is NVA
In many transactional processes, such as approvals, claims, onboarding, and order handling, the work is actually being performed for only a small part of the elapsed time. The rest is the work sitting still, being checked, being fixed, or being moved. A common rule of thumb is that value-added time is under 10% of total lead time in office processes. Treat that figure as typical, not guaranteed. You must measure your own process.
This changes how you improve a process. Speeding up a value-added step, such as asking people to type faster, gives a small gain. Removing a two-day queue gives a large one. Effort aimed at the value-added work often produces less than effort aimed at the NVA steps around it.
Where NVA steps hide
NVA steps rarely carry a label. They show up in a few recognizable forms.
| Form | What it looks like | Example |
|---|---|---|
| Waiting | Work sits in a queue or inbox | A request waits two days for a manager |
| Rework | A step is repeated because the first pass was wrong | Correcting a form after a reviewer rejects it |
| Handoffs | Work passes between people or teams, and context is lost | A ticket moves from support to billing to support |
| Extra approvals | Sign-offs that add delay but rarely change the outcome | Three managers approve a small purchase |
| Searching | People look for information, files, or the right person | Hunting for the latest version of a contract |
| Duplicate entry | The same data is typed into more than one system | Copying an order from email into two tools |
| Over-processing | More work than the customer needs | Producing a 20-page report when a summary was requested |
| Movement and transport | Items or information are moved without changing | Carrying paper files between floors |
A useful habit: when you see a step, ask what would happen to the customer's output if the step disappeared. If the answer is "nothing the customer would notice", the step is a candidate for NVA.
Notice the loop between inspection and rework. Each trip around the loop adds time and cost without adding anything the customer wanted. A process with a 20% failure rate sends one in five orders around this loop at least once. This is sometimes called the hidden factory, because the organization is paying for a second production line that no one planned.
Two kinds of NVA
Not every NVA step can simply be deleted. Split NVA steps into two groups:
- Pure waste. No law, contract, or real risk control requires the step. Examples are most queues, rework, and duplicate entry. You aim to eliminate these.
- Business-necessary NVA (BNVA). The customer would not pay for the step, but you must still do it, for example a legal compliance check or a tax filing. You aim to reduce, simplify, or protect these, but you cannot just remove them.
Deciding which group a step belongs to is a judgment that needs evidence. "We have always done it" is not evidence. Tracing the step to a specific rule or a specific risk is. The chapter on business-necessary steps covers that trace.
Measuring NVA time
Once steps are labelled, you can total the time in each class. The snippet below tags each step as VA or NVA with a cause, then reports how much of the lead time is NVA and which causes dominate.
from collections import defaultdict
# (step name, minutes, class, NVA cause or None)
steps = [
("Submit claim form", 10, "VA", None),
("Wait for adjuster", 480, "NVA", "waiting"),
("Re-enter data in second system", 20, "NVA", "duplicate entry"),
("Assess damage", 45, "VA", None),
("Fix errors found by reviewer", 30, "NVA", "rework"),
("Pay claim", 5, "VA", None),
]
lead_time = sum(minutes for _, minutes, _, _ in steps)
nva_by_cause = defaultdict(int)
for _, minutes, cls, cause in steps:
if cls == "NVA":
nva_by_cause[cause] += minutes
nva_total = sum(nva_by_cause.values())
print(f"NVA minutes: {nva_total} of {lead_time} ({nva_total / lead_time:.1%})")
for cause, minutes in sorted(nva_by_cause.items(), key=lambda kv: -kv[1]):
print(f"{cause}: {minutes}")Running it prints:
NVA minutes: 530 of 590 (89.8%)
waiting: 480
rework: 30
duplicate entry: 20Almost all of the NVA time is one cause, waiting. Fixing rework and duplicate entry would be worthwhile, but the queue for the adjuster is where the clock is lost. Sorting NVA time by cause, as the code does, is a simple way to decide where to start.
Edge cases and judgment calls
Several situations make NVA classification harder than it first looks.
- Inspection. An inspection does not change the product, so by itself it is NVA. Whether it is pure waste or business-necessary depends on whether a rule or a real risk requires it. Do not label all inspection as waste. Do not label all inspection as necessary either.
- Steps that feel valuable. Meetings, status reports, and reviews often feel productive. Ask what the customer receives because of them. If the answer is nothing, they are NVA, even when they are useful for coordination inside the team.
- Internal customers. If a step's only beneficiary is the next team in the process, that team becomes the customer for the purpose of judging value. The step is value-added to them only if it prepares the work in a way they need. Pushing the output further down the chain, the real customer still decides the final value.
- Different customers, different answers. A step that a regulator requires but a retail buyer ignores is NVA to the buyer and required by the regulator. Be explicit about which customer's view you are using. For process analysis, the end customer's view is the usual default.
- Time spent by the customer. Waiting that the customer experiences counts the same as waiting inside your building. If the customer waits three days for a reply, those three days are NVA from their view, even if your staff were busy elsewhere.
Common errors
- Counting activity as value. A step that keeps people busy is not value-added unless the customer would pay for its result.
- Deleting steps before tracing them. Removing a step that was actually required by a rule creates compliance risk. Always check the rule or risk before eliminating.
- Mapping the process as it should work. Use observation of the real process, including queues and loops. A map that omits rework will understate NVA time.
- Ignoring waiting time. Teams often map only the work, so the largest block of NVA time never appears on the map.
- Stopping at classification. Labels are only useful if they lead to an action: eliminate, reduce, simplify, or keep. A later chapter covers that decision.
Summary
An NVA step costs resources and adds nothing the customer would pay for. NVA steps usually account for most of the lead time, especially in office processes, and they hide as waiting, rework, handoffs, extra approvals, searching, duplicate entry, over-processing, and movement. Some NVA steps are pure waste. Others are required by a rule or risk and must be handled differently. Separating NVA time by cause shows where to focus first.
Exercise
A purchase request waits 3 days in a manager's inbox, takes 10 minutes of actual review, and is then entered a second time into the finance system (15 minutes). The requester's only goal is to receive the approved item. Which of these steps are NVA candidates, and which cause is the largest by time?
Show answer
The 3-day wait and the 15-minute second data entry are NVA candidates. The 10-minute review may be NVA too if it only repeats a check that has no effect on the outcome, but you would need to trace it to a rule or risk before deciding. The largest cause by time is waiting, at 3 days, which is far larger than the 15 minutes of duplicate entry.
Exercise
A colleague says, "Inspection adds no value, so remove every inspection step from our map." Give one reason why this conclusion is too strong.
Show answer
Inspection does not change the product, so it is NVA, but some inspections are business-necessary. A regulation, contract, or genuine safety or quality risk may require them. Removing them without tracing each one to a rule or risk could create legal or quality problems. The right move is to classify each inspection separately, remove the ones that have no requirement behind them, and keep or simplify the rest.