Sub topic 9
Classifying Steps on a Process Map
A process map shows the sequence of steps. A classified map also shows which steps the customer values, which ones the business must keep, and where time is lost. This chapter covers how to record the classification and the time data on the map, and what to do with the awkward cases.
This chapter assumes you can read a simple flowchart and that you know the three-question test (would the customer pay, does the step change form, fit, or function, is it right the first time). It also assumes you know that a business-necessary non-value-added (BNVA) step must trace to a rule, contract, or risk control. Process cycle efficiency (PCE) has its own chapter, so here we only gather the data it needs.
What an annotated map adds
An ordinary map answers "what happens, and in what order?" An annotated map also answers three further questions for every step:
- Which class is it: VA (value-added), BNVA, or NVA (non-value-added)?
- How long does the work take, and how long does the work wait before it starts?
- Why was it classified that way?
The third question is the one teams skip, and it is the one that makes the map defensible. A label with no reason is an opinion. A label with a reason, such as "required by the credit policy, section 4", can be checked and challenged later.
What to record for each step
Add a small data block to every step, or keep the same fields in a table next to the map.
| Field | Meaning | Example |
|---|---|---|
| Step name | Verb plus object, one action | Check customer credit |
| Class | VA, BNVA, or NVA | BNVA |
| Process time | Minutes of hands-on work for one unit | 10 |
| Wait time before | Minutes the unit sits before this step starts | 120 |
| Basis | For BNVA, the rule or risk. For NVA, the waste type | Credit policy 4.2 |
| Owner | Role that performs the step | Credit analyst |
Process time and wait time are kept separate because they usually belong to different classes. The 10 minutes of credit checking is BNVA. The 120 minutes before it is pure waiting, which is NVA. If you merge the two into one 130-minute box, you hide the biggest finding on the map.
A procedure for classifying a map
- Fix the unit and the customer. Choose what flows through the map (one order, one claim, one patient) and who the customer is. Classification changes if you change the customer.
- Walk the real process. Follow an actual unit from start to finish, or interview the people who do the work. Do not classify the procedure manual. Manuals leave out rework loops and queues.
- Make waiting visible. Every place where work sits in an inbox, a queue, or a pile becomes its own step marked as waiting.
- Apply the three-question test to each step. Ask the questions in order. A step that passes all three is VA.
- Test the failures for necessity. For each step that failed, ask whether a regulation, contract, or risk control requires it. If so, it is BNVA, and you write down which one. If not, it is NVA, and you write down the waste type.
- Add the times. Record process time and wait time from observation or timestamps, not from memory.
- Review with the people who do the work. They will find steps you missed and will tell you which "required" steps are only habits.
Worked example
An order-to-shipment process has seven steps. The diagram shows the classes. The bracketed numbers are minutes.
Two judgment calls in this map are worth explaining.
- Enter order is BNVA, not VA. The customer asked for a product, not for a database record. The record is required for traceability and invoicing, so it stays, but it adds nothing the customer would pay for.
- Rework is NVA even though people work hard on it. The effort is real, but the customer pays for the product once. The defect was created by an earlier step, so the rework does not pass the "right the first time" question.
Automating the bookkeeping
Once a map has more than a dozen steps, a table in code is easier to keep consistent than a drawing. The script below stores the annotated steps, rejects entries that break the annotation rules, and totals minutes by class.
VALID = {"VA", "BNVA", "NVA"}
steps = [
{"name": "Enter order", "minutes": 5, "cls": "BNVA", "basis": "Invoice and traceability record"},
{"name": "Wait in credit queue", "minutes": 120, "cls": "NVA", "basis": "Waiting"},
{"name": "Credit check", "minutes": 10, "cls": "BNVA", "basis": "Credit policy 4.2"},
{"name": "Assemble product", "minutes": 30, "cls": "VA", "basis": ""},
{"name": "Rework defects", "minutes": 15, "cls": "NVA", "basis": "Defects"},
{"name": "Regulatory inspection", "minutes": 10, "cls": "BNVA", "basis": "Safety regulation"},
{"name": "Pack and label", "minutes": 10, "cls": "VA", "basis": ""},
]
def check(rows):
"""Return a list of annotation problems; an empty list means the map is consistent."""
problems = []
for row in rows:
if row["cls"] not in VALID:
problems.append(f"{row['name']}: unknown class {row['cls']!r}")
elif row["cls"] in ("BNVA", "NVA") and not row.get("basis"):
problems.append(f"{row['name']}: {row['cls']} needs a named rule, risk, or waste type")
return problems
def summarize(rows):
totals = {cls: 0 for cls in ("VA", "BNVA", "NVA")}
for row in rows:
totals[row["cls"]] += row["minutes"]
return totals
print(check([{"name": "Approve", "minutes": 3, "cls": "BNVA", "basis": ""}]))
print(check(steps))
totals = summarize(steps)
lead_time = sum(totals.values())
for cls, minutes in totals.items():
print(f"{cls}: {minutes} min ({minutes / lead_time:.1%})")
print(f"Total: {lead_time} min")Running it prints:
['Approve: BNVA needs a named rule, risk, or waste type']
[]
VA: 40 min (20.0%)
BNVA: 25 min (12.5%)
NVA: 135 min (67.5%)
Total: 200 minThe first check call shows the rule at work. A BNVA step without a basis is rejected, which stops the common habit of labelling something "necessary" because nobody wants to remove it. The totals feed directly into the PCE calculation in the next chapter.
Where classification gets difficult
Decision points
A decision diamond ("Is the order over the credit limit?") takes almost no time, but it is not VA. The customer does not pay for a decision. Classify a decision by the reason it exists. A credit-limit check is BNVA if policy requires it. A routing decision that only exists because the process is split across departments is usually NVA.
Rework loops
Draw rework as an arrow from the failing step back to an earlier one, and give the loop a rate. If 25% of units go through a 15-minute rework step, the expected rework time per unit is about 3.75 minutes, not 15. Record the rework step at full duration and note the rate, so the map is not misleading when you add up averages.
Steps with mixed content
A single box sometimes contains two kinds of work. "Prepare and send quote" may include 10 minutes of building a quote (VA, if the customer wants a quote) and 20 minutes of chasing missing information (NVA). Split the box into two steps. A mixed label gives you a wrong class and hides the waste.
Parallel branches
When two branches run at the same time, only the longer branch adds to lead time. Classify every step on both branches, but when you total time, count lead time along the critical path. The VA time on the shorter branch is still real work, but it does not extend the elapsed time.
Batches and handoffs
Work waiting for a batch to fill, or waiting for another team to pick it up, is NVA waiting. Record the handoff as a wait step between the two owners. Handoffs are where most of the wait time on a typical map accumulates, and they are easy to miss because nobody "does" them.
Different customers, different maps
An internal inspection can be VA for an internal customer (the next team needs a verified part) but BNVA or NVA for the final customer. State which customer you used on the map title, for example "Order to shipment, external customer view". Without it, two teams can classify the same step differently and both be right.
Keeping the evidence
For each BNVA step, store a reference to the source requirement, such as a regulation clause, a contract term, or a named risk in the risk register. Also store the date you last checked that the requirement still applies. Requirements change, and a step whose basis has been repealed has become NVA without anyone redrawing the map. The next chapters return to this when they cover challenging BNVA steps.
For NVA steps, record the waste type (waiting, defects, over-processing, and so on) so that the improvement list can be grouped by cause.
Checking the finished map
Before you share the map, check these points:
- Every step has exactly one class.
- Every BNVA step names its rule or risk, and every NVA step names its waste type.
- Waiting between steps appears as its own steps, not as part of a neighbouring box.
- Times come from observation or timestamps, and the unit (minutes, hours, days) is the same throughout.
- The map states its customer and the unit that flows through it.
- Rework loops show a rate.
Exercise
A seamstress process for one jacket has these steps, in order: Cut fabric (20 min, VA), Wait for sewing table (90 min), Sew jacket (40 min, VA), Seam inspection required by the customer's supply contract (8 min), Re-sew failed seams (12 min). Classify the waiting, the inspection and the re-sewing. Then give the lead time and the percentage of lead time that is NVA.
Show answer
The wait for the sewing table is NVA (waiting). The seam inspection is BNVA, because the contract requires it. The re-sewing is NVA (rework, a defect). Lead time is 20 + 90 + 40 + 8 + 12 = 170 minutes. NVA time is 90 + 12 = 102 minutes, which is 102 / 170 = 60% of lead time.
Exercise
A box on a map reads "Review and correct application" and takes 30 minutes. About 10 minutes is a mandatory identity check required by law. The other 20 minutes is fixing errors that applicants made on the form. What should you do with this box, and why?
Show answer
Split it into two steps. The 10-minute identity check is BNVA, and its basis is the legal requirement. The 20 minutes of correcting errors is NVA (defects and rework). Leaving the box as one step would give it a single wrong label and hide the rework, which is the part that can be reduced by fixing the form or the instructions.