When Payment Is Due: Net Terms, Advances, and Milestones
Prerequisites and the payment clock
This chapter assumes you understand offer, acceptance, consideration, and the roles of buyer, seller, supplier, and customer. It also assumes you can read a basic commercial contract.
A payment clause answers four separate questions:
- What amount must the customer pay?
- When may the supplier issue an invoice?
- When does the payment period begin?
- What happens if payment is late or disputed?
“Net 30” usually means payment is due 30 days after the event named in the clause. That event is often the invoice date, but it may be the date the customer receives a correct invoice, accepts the deliverable, or reaches a milestone. A clause that says only “net 30” leaves the starting point unclear.
Common payment structures
| Structure | Payment trigger | Typical use |
|---|---|---|
| Net terms | Invoice receipt or another stated event | Routine goods or completed services |
| Advance payment | Contract signing, order, or scheduled start | Custom work or items requiring upfront costs |
| Milestone payment | Completion and approval of a defined stage | Projects delivered in phases |
The contract should state whether taxes, shipping, expenses, and disputed amounts are included in the stated price. It should also identify the currency and payment method. If the parties use different currencies, state who bears conversion costs and exchange-rate risk.
Net terms
A precise net-terms clause identifies both the invoice trigger and the due date:
Payment. Customer shall pay each undisputed invoice in US dollars within thirty (30) days after the date Customer receives the invoice. Supplier may invoice only after Customer accepts the Deliverable under Section 5. Amounts not paid when due accrue interest at the lesser of one percent (1%) per month and the maximum rate permitted by law.This clause links invoicing to acceptance. That link protects the customer from paying before the supplier has delivered an acceptable result, but it can create delay if acceptance criteria are vague. The contract should therefore define acceptance separately and objectively.
“Undisputed” also needs care. A customer should not be able to avoid all payment by making an unsupported objection. A stronger clause can require written notice identifying the disputed amount and reason, while requiring timely payment of the undisputed balance.
Advances and milestones
An advance is paid before the supplier completes the relevant performance. The clause should state whether the advance is refundable, credited against later invoices, or retained if the customer cancels. It should also identify what work the advance funds.
Milestones divide a project into payment stages. Each milestone should have:
- A measurable completion event.
- A required submission or evidence of completion.
- A review period.
- A due date for the related invoice.
- A rule for partial completion or a good-faith dispute.
For example, “payment upon completion of design” is weaker than “payment within 15 days after delivery and written approval of the design package listed in Exhibit A.” Approval should not be left entirely to personal satisfaction unless that discretion is intended.
Review exercise
Check every payment clause for a clear trigger, currency, invoice requirements, due date, treatment of disputed amounts, and late-payment consequence. Then ask whether the trigger depends on another clause, such as delivery or acceptance.
Exercise
An agreement says, “Customer shall pay within 30 days of invoice.” What key issue remains unresolved?
Show answer
The clause does not say when the invoice may be issued or when the 30-day period begins, such as on sending, receipt, delivery, or acceptance.