Sub topic 11
Testing Periods and Deemed Acceptance
This chapter assumes you understand basic contract formation and the roles of buyer, seller, supplier, and customer. It focuses on commercial contracts where a customer must test goods or a deliverable before accepting it.
What acceptance controls
An acceptance clause defines when the customer must treat the supplier's performance as satisfactory. Acceptance can affect:
- Whether the supplier may invoice.
- Whether payment becomes due.
- Whether the customer may reject the performance.
- Whether the supplier must correct defects.
- When warranties or support periods begin.
Acceptance criteria should be objective. A standard such as “Customer is satisfied” gives the customer broad discretion and makes disputes harder to resolve. A stronger standard identifies the specifications, tests, measurements, documents, or performance levels that determine compliance.
Acceptance is different from delivery. Delivery may occur when the customer receives the goods. Acceptance may occur later, after testing confirms that the goods meet the contract.
Testing periods
A testing period is a defined time after delivery during which the customer can inspect or test the deliverable. A useful clause answers four questions:
- When does the period begin?
- How long does it last?
- What tests or criteria apply?
- What notice must the customer give if the deliverable fails?
The start event must be clear. “After delivery” may be uncertain if delivery occurs in stages. The contract might instead say that the period begins when the supplier delivers the complete deliverable and the required documentation.
The notice requirement should require a written description of the failure. A general statement such as “the product does not work” may not identify what the supplier must correct.
Acceptance. Customer has ten (10) business days after delivery to test the Deliverable against the Specifications. If Customer gives written notice within that period describing how the Deliverable fails the Specifications, Supplier shall correct the failure and redeliver within ten (10) business days. If Customer gives no notice within the testing period, the Deliverable is deemed accepted.Deemed acceptance
Deemed acceptance means the contract treats the deliverable as accepted when a specified event occurs, often the customer's failure to reject it within the testing period. This rule gives both parties a clear endpoint. It prevents a customer from keeping the deliverable indefinitely unreviewed.
Deemed acceptance should not eliminate an agreed remedy for hidden defects. A customer might accept a deliverable after ordinary testing and later discover a defect that could not reasonably have been found during that testing. The contract should state whether acceptance preserves warranty, latent-defect, or other rights.
A clause should also address customer use. Using a deliverable in production, reselling it, or making substantial changes may count as acceptance, but that result should be stated rather than assumed.
Rejection and cure
A rejection notice should identify the failed requirement and preserve evidence of the test. The supplier's cure period should state what happens if the cure succeeds or fails. Repeated failed cures may give the customer rights to a refund, replacement, price reduction, or termination, depending on the contract.
Partial or installment delivery requires separate treatment. The testing period may apply to each installment, the complete system, or both. If separate components cannot function independently, accepting one installment should not necessarily waive the customer's right to reject the integrated deliverable.
Clause interaction and review
If payment depends on acceptance, the contract should state whether the customer may withhold only the disputed amount or all payment. The payment clause should also identify the invoice date and the effect of deemed acceptance.
Use this review checklist:
- Are the acceptance criteria measurable?
- Is the testing period's start and end clear?
- Must rejection be written and specific?
- Does the supplier have a defined cure period?
- Are hidden defects and warranties preserved?
- Are partial deliveries handled?
- Does acceptance trigger invoicing or payment?
Exercise
A customer receives a deliverable but sends no notice during the ten-business-day testing period. Two weeks later, the customer identifies a defect that the agreed tests would not have revealed. What should you check before concluding that the customer lost all remedies?
Show answer
Check whether the contract preserves warranty or latent-defect rights after deemed acceptance, and then check the governing law for limits on waivers or deemed-acceptance provisions.