Sub topic 6
Delivery Terms: Place, Method, and Who Does What
This chapter assumes you understand basic contract formation and common commercial roles such as supplier, customer, buyer, and seller. It focuses on how a delivery clause turns a general duty to provide goods or services into a process that can be checked.
What a delivery clause controls
A delivery clause answers four practical questions:
- Where must delivery occur?
- When must it occur?
- How must the supplier deliver?
- Which party must arrange, pay for, and perform each step?
“Supplier shall deliver the Goods” is incomplete. It does not say whether delivery means handing the goods to a carrier, placing them at the customer’s loading dock, or unloading them inside the customer’s warehouse. Those events may occur at different times and may create different responsibilities.
A useful clause identifies the delivery location precisely. It can name an address, warehouse, site, port, or another defined destination. It should also state whether the supplier must unload, install, configure, or provide delivery documents.
Assigning responsibility
Delivery often involves several tasks:
- packaging and labeling the goods;
- obtaining export or import documents;
- selecting and paying the carrier;
- arranging insurance;
- unloading the shipment;
- inspecting for visible damage; and
- giving notice of dispatch or delay.
Do not assume that the party paying the carrier performs every task. The contract should assign each important task expressly. It should also identify who bears the cost if a party fails to provide information, access, permits, or equipment needed for delivery.
For international shipments, commercial delivery terms such as Incoterms can allocate transport, customs, cost, and risk responsibilities. The contract should name the rule, place, and version clearly. A reference such as “FOB” without a named location can create uncertainty.
Delivery date and delivery event
A delivery date should be measurable. “Promptly” and “as soon as possible” are difficult to apply objectively. A clause might require delivery “on or before 30 June 2027” or within a stated number of business days after an order.
The contract must also define the delivery event. For example, delivery might occur when:
- the supplier gives the goods to the carrier;
- the goods arrive at the destination;
- the goods are unloaded; or
- the customer signs a receipt.
That definition may affect acceptance, invoicing, risk of loss, and delay remedies. Keep those provisions consistent.
Delivery. Supplier shall deliver the Goods to the Customer's warehouse at the address in the Order on or before the Delivery Date. Risk of loss passes to Customer when the Goods are unloaded at that address. Title passes to Customer on payment in full.Avoiding hidden gaps
A strong clause addresses failed or attempted delivery. It can state what happens if the customer is not ready, refuses access, provides an incorrect address, or fails to obtain a required permit. The clause should distinguish a customer-caused delay from a supplier-caused delay.
It should also state whether delivery may be made in separate shipments. If partial delivery is allowed, explain whether the customer may reject one incomplete shipment, whether separate invoices are permitted, and what happens when one shipment is late.
Reviewing a delivery clause
Use this checklist:
- Is the destination specific?
- Is the delivery date measurable?
- Is the delivery event defined?
- Who chooses and pays the carrier?
- Who handles customs, insurance, unloading, and installation?
- What documents must accompany delivery?
- What happens after delay, failed delivery, or customer-caused obstruction?
- Are partial shipments and delivery notices addressed?
- Do the delivery, payment, acceptance, risk, and title provisions use compatible triggers?
Exercise
A clause says, “Supplier will ship the equipment to Customer promptly.” Identify two important gaps and propose a precise replacement for each.
Show answer
The clause does not identify the destination or the delivery date. It could say, “Supplier shall deliver the equipment to Customer’s warehouse at [address] on or before 30 June 2027.” It should also state who selects and pays the carrier and whether delivery includes unloading.