Sub topic 12
Rejection, Cure Rights, and Remedies
Assume you know the basics of offer, acceptance, consideration, and commercial contract terms. This chapter focuses on contracts for goods or services where one party says the performance does not meet the agreement.
When can a customer reject performance?
Rejection is the customer's refusal to treat delivered goods or services as conforming to the contract. A contract should identify what counts as conformity. Useful criteria include specifications, quantities, delivery dates, required documents, service levels, and testing results.
A defect does not always permit rejection of the entire performance. The answer depends on the contract, the seriousness of the defect, and governing law. A minor defect may create a right to repair or a price adjustment rather than a right to cancel.
A rejection notice should be prompt and specific. It should identify:
- The item or service affected.
- The contractual requirement that was not met.
- The facts showing the failure.
- The remedy requested.
- The deadline for correction, if the contract provides one.
Silence can create risk. A contract may state that failure to give notice during a testing period results in deemed acceptance. That rule may be limited by mandatory law or by a party's conduct, so it should not replace a clear inspection process.
Cure rights
A cure right gives the supplier an opportunity to correct defective performance. A useful cure clause states who may cure, what counts as a cure, when notice must be given, and who pays the related costs.
| Clause element | Drafting question |
|---|---|
| Cure period | How many days does the supplier have to repair, replace, or reperform? |
| Cure method | Must the supplier repair, replace, redeliver, or provide a workaround? |
| Costs | Who pays shipping, removal, testing, and reinstallation costs? |
| Failed cure | What can the customer do if the cure is late or unsuccessful? |
For example, a clause might allow the customer ten business days to give written notice of a failure, then require the supplier to correct and redeliver within ten business days. The contract should say whether the customer may reject the replacement if it fails the same objective criteria.
Under some sales laws, a seller can cure a nonconforming tender within the contract period, or sometimes within a reasonable additional period when the seller had reasonable grounds to believe the tender would be acceptable. Service contracts may use different rules, including substantial-performance or material-breach principles. The contract should therefore state the intended process without assuming that one legal rule applies everywhere.
Remedies after an unsuccessful cure
The contract should connect rejection and cure to remedies. Possible remedies include:
- Repair, replacement, or reperformance.
- Refund of amounts paid for the nonconforming performance.
- Price reduction.
- Damages for losses allowed by the contract and governing law.
- Cover, meaning a reasonable substitute purchase.
- Suspension of payment for the disputed portion.
- Termination for a material or repeated breach.
A customer should avoid withholding every payment merely because one part is disputed unless the contract permits it. A better clause can require payment of undisputed amounts while the parties resolve the rejected portion.
How partial performance changes the analysis
For separate deliveries, acceptance and rejection may apply to each installment. For an installment contract, one defective installment may justify rejection of that installment, but rejection of the whole contract usually requires a substantial impairment of the entire agreement or a clear contractual right.
Review checklist
Ask these questions:
- Are acceptance criteria objective and measurable?
- Is the rejection notice deadline clear?
- Must the notice describe the defect?
- What cure is required, and who bears its costs?
- Is payment of undisputed amounts preserved?
- What happens after a failed or repeated cure?
- Do partial deliveries receive separate treatment?
- Does governing law change the available remedy?
Exercise
A customer discovers that a delivered machine fails one measurable specification and sends a detailed notice within the testing period. The supplier misses the contractual cure deadline. What should the reviewer identify before advising that the customer may terminate?
Show answer
The reviewer should check whether the contract permits termination after a failed cure, whether the failure materially affects the agreement, whether the customer must allow another cure, and what governing law and remedy limits apply.