Conditions versus Promises and Why It Matters
Assume you understand the basic idea of a contract and the roles of buyer, seller, supplier, and customer. This chapter uses those ideas to examine one question: what happens when a party does not do what the contract says?
A commercial contract usually contains both promises and conditions. A promise is a contractual commitment to do something. A condition is an event or fact that controls whether a contractual duty becomes due or whether a party receives a contractual right.
The working difference
Suppose a supplier promises to deliver equipment by June 1. That is a promise. If the supplier delivers on June 5, the supplier may have breached the promise.
Now suppose the contract says:
Customer's obligation to pay the final installment is conditioned on Customer's acceptance of the equipment under Section 5.Acceptance is a condition to final payment. Until acceptance occurs, the final payment duty may not be due. The parties have made the event part of the trigger for performance.
| Term | Meaning | Typical effect when it does not occur |
|---|---|---|
| Promise | A commitment to perform an act | The other party may claim breach and available remedies |
| Condition | An event that must occur before a duty or right takes effect | The affected duty may not arise, or a right may be lost |
| Condition precedent | An event that must occur before a duty becomes due | Payment or another duty may be delayed |
| Condition subsequent | An event that ends an existing duty or right | A party's future duty may be discharged |
The exact legal effect depends on the wording, governing law, and contract type. Courts often look at the parties' intent and the practical consequences of treating language as a condition.
Why classification affects remedies
If a promise is breached, the injured party may have a claim for damages. The contract may also provide a cure period, service credits, termination rights, or specific performance.
If a condition is not satisfied, the affected duty may never become payable. For example, if final payment is expressly conditioned on acceptance, the customer may have a stronger basis for withholding that payment before acceptance. The supplier may still argue that the customer wrongfully prevented acceptance or rejected conforming work.
The distinction can produce harsh results. A missed condition may defeat a right even when the failure was minor. For that reason, a drafter should not label every requirement a condition. The contract should identify which events truly control payment, termination, or another major right.
Drafting conditions clearly
A useful condition states four points:
- The event that must occur.
- The party responsible for causing or verifying it.
- The evidence required to show that it occurred.
- The consequence if it does not occur.
For example:
Customer shall pay the final installment only after Customer accepts the Deliverable in writing under Section 5. Supplier shall not invoice the final installment before that acceptance.This wording links acceptance, invoicing, and payment. It also reduces an argument about whether the supplier may invoice before the acceptance process ends.
Conditions can also be written to protect against deliberate obstruction. A contract might state that acceptance cannot be unreasonably withheld and that the customer must provide written reasons for rejection. Without such language, one party may claim that the other prevented the condition from occurring.
Review questions
When reviewing a clause, ask:
- Is this language creating a promise, a condition, or both?
- What duty is affected if the event does not occur?
- Who controls the event?
- Is there a notice, testing, or cure procedure?
- Could a party waive the condition through its conduct?
- Does the governing law impose special rules for this contract?
Exercise
The contract says, “Customer shall pay within 30 days after acceptance.” Is acceptance necessarily a condition to payment?
Show answer
Not necessarily. The wording links payment timing to acceptance, but it may be interpreted as a condition, a promise, or a timing rule depending on the full contract and governing law. Use clearer language if acceptance must be a strict prerequisite.