Sub topic 9
Partial Delivery and Installment Contracts
Assume you understand basic contract terms such as buyer, seller, price, delivery, and breach. This chapter focuses on contracts where performance happens in parts rather than in one complete delivery.
Two ways performance can be divided
A partial delivery occurs when a supplier delivers less than the full quantity or scope promised. For example, a seller may promise 1,000 units but deliver only 600. The contract may allow this, or the short delivery may be a breach.
An installment contract requires or permits delivery in separate installments. Each installment may have its own quantity, date, inspection process, and payment. A missed or defective installment does not always allow the other party to cancel the entire contract.
The contract should answer these questions:
- Is partial delivery allowed?
- Who decides the quantity and timing of each installment?
- May the customer accept part and reject part?
- When is payment due for an accepted installment?
- Does a problem with one installment affect later installments?
- When may either party cancel the whole contract?
Partial delivery
A clause should distinguish an authorized partial delivery from an unauthorized short delivery. It should also state what happens to the missing portion.
Partial Deliveries. Supplier may make deliveries in installments only with Customer's written approval. Customer may accept conforming items and reject nonconforming items in each delivery. Supplier shall deliver any authorized shortfall by the later date stated in the Order. Customer shall pay for accepted items within thirty (30) days after receiving the applicable invoice. An unauthorized short delivery is a breach, subject to Supplier's cure rights under Section 9.This clause separates four events:
- The supplier delivers some items.
- The customer checks those items.
- The customer pays for items accepted under the agreed payment rule.
- The supplier completes the remaining delivery or faces a remedy.
Without this structure, a customer might argue that no payment is due until the entire order arrives. A supplier might argue that delivery of any quantity triggers payment for the whole order.
Installment contracts
An installment contract should identify each installment or provide a method for setting it. Useful details include:
- Quantity or scope for each installment.
- Required delivery date or delivery window.
- Delivery location and shipping method.
- Acceptance and testing rules.
- Price allocation and invoice timing.
- Notice requirements for delay or defects.
- Cure periods.
- Rules for terminating one installment or the entire contract.
A defect in one installment can have different effects. A minor defect may require correction but not justify cancellation. A serious defect may substantially defeat the purpose of the contract, especially if the installments are dependent on one another.
For example, defective machine components may make later components useless. By contrast, a late shipment of ordinary replacement parts may affect only that shipment.
Payment and acceptance
Payment terms should connect payment to an identifiable installment. Avoid saying simply that payment is due “on delivery” when the contract has several deliveries. State whether delivery means arrival, unloading, or acceptance.
| Contract wording | Main uncertainty |
|---|---|
| Payment due on delivery | Whether delivery means shipment, arrival, or acceptance |
| Payment due on acceptance of each installment | Whether the acceptance test and deadline are clear |
| Payment due for each conforming installment | How partial conformity and disputes affect payment |
A customer should normally be required to identify disputed amounts in writing. The contract can require payment of undisputed amounts while the parties resolve the disputed installment.
How remedies work
A party reviewing an installment dispute should ask:
- Was the installment authorized and delivered on time?
- Did the goods or services meet the stated criteria?
- Did the customer give timely notice of rejection?
- Did the supplier have a right to cure?
- Is the problem limited to one installment or does it affect the whole bargain?
- Does the governing law provide default rules for installment contracts?
Exercise
A supplier delivers 70 of 100 units in the first installment. The contract does not address partial delivery. What should you check before deciding whether the customer must pay?
Show answer
Check the quantity and delivery terms, any applicable default law, whether the customer accepted the 70 units, whether the shortfall can be cured, and whether the missing units materially affect the contract's purpose.