Sub topic 11
Monitoring performance and holding reviews
This chapter assumes you know basic project management vocabulary (scope, schedule, budget, stakeholders), can read a work breakdown structure, and have seen a contract. It also builds on the scope of work and the communication rhythm you set up earlier. Once the vendor is working, your job is to find out early whether the work is on track, and to act while the fix is still cheap.
Why monitoring a vendor is different
You manage your own team through daily contact. A vendor sits outside that contact. You see their output, not their effort, and their incentives differ from yours. A fixed-price vendor earns more by spending less. A time-and-materials vendor earns more by spending more. Neither is dishonest by default, but each has a reason to report news in a particular way.
For this reason, monitor against things you can verify. Do not rely on how confident the vendor sounds. Your monitoring rests on three items that already exist from earlier chapters:
- The scope of work, which names the deliverables.
- The acceptance criteria, which define when a deliverable counts as done.
- The schedule and payment milestones, which say when each deliverable is due.
If those three are vague, monitoring turns into an argument about opinions. If they are specific, monitoring is a comparison between what was promised and what exists.
What to measure
Pick a small set of measures and agree on them with the vendor at kickoff. Measures the vendor first sees in a bad review feel like a trap.
| Area | Example measure | Where the data comes from |
|---|---|---|
| Schedule | Milestones delivered on or before the due date | Project schedule, vendor status report |
| Cost | Spend to date against earned value | Invoices, accepted milestones |
| Quality | Defects found at inspection or test, rework rate | Inspection records, test results |
| Scope | Open change requests, work done that is not in scope | Change log |
| Responsiveness | Time to answer questions and fix defects | Issue log |
| Safety or compliance | Incidents, audit findings | Site reports, audit records |
Prefer outcome measures to activity measures. "Percent of acceptance criteria met" tells you more than "hours worked this week." Activity measures are easy to inflate and say little about whether the deliverable will pass.
Leading and lagging indicators
A lagging indicator reports something that already happened, such as a missed milestone. A leading indicator warns you before the miss. Examples of leading indicators include:
- Key vendor staff leaving or being moved to another job.
- Materials ordered late or delivered late.
- Questions to your team that go unanswered for days.
- Status reports that stay green while the list of open issues grows.
- Work that is "90% done" for several consecutive reports.
Watch the leading indicators closely. By the time a lagging indicator shows trouble, you have usually lost the cheapest options.
Measuring progress honestly
Percent-complete numbers from a vendor are the least reliable data you will receive. People report effort spent as progress made. Use rules that tie progress to evidence.
- Count only accepted deliverables as earned. This is the same rule used for payment. A milestone that has not passed its acceptance criteria is not complete, however much work went into it.
- Break long tasks into short ones. A task that lasts three weeks can hide problems for three weeks. Tasks of a few days each give you a check every few days.
- Verify by observation. Visit the site, watch a demo, or inspect a sample. A weekly walk-through catches problems that a written report does not.
- Compare two sources. Check the vendor's report against your own records, such as delivery receipts, test logs, or access logs for site attendance.
The payment calculation from the vendor register example shows the principle in practice. Only accepted milestones count, so with a 120,000 USD contract and two of three milestones accepted, earned value is 84,000.
CONTRACT_VALUE = 120_000
RETAINAGE_RATE = 0.10
milestones = [
{"name": "Design approved", "share": 0.20, "accepted": True},
{"name": "Build complete", "share": 0.50, "accepted": True},
{"name": "Acceptance test passed", "share": 0.30, "accepted": False},
]
earned = sum(CONTRACT_VALUE * m["share"] for m in milestones if m["accepted"])
retainage = earned * RETAINAGE_RATE
payable = earned - retainage
print(f"Earned: {earned:.2f}, retainage held: {retainage:.2f}, payable now: {payable:.2f}")This prints Earned: 84000.00, retainage held: 8400.00, payable now: 75600.00. Compare the earned figure with the cost the vendor has reported and with the schedule. If the vendor says it has spent 100,000 to reach 84,000 of earned value, the work is running over cost on a fixed-price contract, and you should find out why. It might be the vendor's problem to absorb, or it might signal pressure for a change request.
The monitoring cycle
Monitoring is a repeating loop, not a single event. Each cycle collects data, compares it with the plan, decides what to do, and records the result.
The cadence of this loop should match the risk. A routine supply contract may need a monthly check. A critical subcontractor on the schedule's longest path may need a weekly review, as in the vendor register example, where review_cadence: weekly.
Types of review
Different reviews serve different purposes. Using one meeting for everything produces a meeting that does none of it well.
Progress meetings
These are short and frequent. They cover work done since the last meeting, work planned next, open issues, and open change requests. Keep a standing agenda and publish minutes with named owners and due dates for every action. Minutes matter because they become evidence if a dispute arises later.
Formal performance reviews
These happen at milestones, at set intervals (quarterly, for example), or at the end of a phase. They compare results against the agreed measures across the whole period. A formal review covers trends, not only the latest week, and produces a written rating or summary that the vendor can read and respond to.
Inspections and audits
An inspection checks a specific deliverable against its acceptance criteria. An audit checks the vendor's process, such as quality procedures, safety records, or how they manage their own subcontractors. Your contract must give you the right to do both. If the contract does not, you can only ask, and the vendor may refuse.
Ad hoc reviews
Call one when a leading indicator trips, such as a missed milestone or a key person leaving. Do not wait for the next scheduled review.
Running a performance review
A review has more impact when it follows a predictable shape.
- Send data in advance. Share the measures and your assessment a few days before the meeting, so nobody sees surprises on the day.
- Start with facts. Walk through the numbers and the evidence. Agree on what happened before discussing why.
- Discuss causes. Ask what drove the result. Causes may sit on your side, such as late approvals or slow answers to questions. Acknowledge those honestly, since vendors notice when only their faults are discussed.
- Agree on actions. Each action needs an owner, a due date, and a way to check it was done.
- Document and distribute. Send the record within a day or two and ask the vendor to confirm or correct it in writing.
Treat the review as a joint problem-solving session first. Most vendor problems are fixed by clearer information, faster decisions, or a resourcing change, not by penalties.
Common errors
- Trusting percent complete. Use accepted deliverables instead.
- Measuring too many things. Ten measures nobody reads are worse than four that drive decisions.
- Reviewing only the vendor. If your own delays cause the slippage, a one-sided review damages the relationship and may weaken your position under the contract.
- Not recording notice. If you tell a vendor verbally that they are late and never write it down, you may lose rights that depend on timely written notice. Check your contract's notice terms.
- Letting small deviations slide. Accepting late or substandard work without comment can be read as agreement and may weaken your later claims. Note each deviation in writing, even when you choose not to press it.
- Waiting for the formal review. Serious problems should trigger action at once, not at the next scheduled meeting.
- Ignoring good news. Record strong performance too. It informs future sourcing decisions and the lessons-learned record at closeout.
From monitoring to action
Monitoring only has value if it leads to decisions. A useful pattern is graduated response:
| Signal | Typical response |
|---|---|
| Minor slip, cause understood | Note in minutes, confirm recovery date |
| Repeated slips or a leading indicator | Ad hoc review, written recovery plan |
| Missed milestone or failed inspection | Formal notice under the contract, corrective action plan |
| Recovery plan fails | Escalate under the contract's escalation steps |
The next chapters on change control and escalation pick up from here. Many performance problems come from scope being changed informally, so keep the change log and the performance data side by side.
Exercise
A fixed-price subcontractor reports that its Build complete milestone is "90% done" for the third week running, and the status report is still green. Name two leading indicators in this scenario, and say what you should do before the next scheduled review.
Show answer
The leading indicators are the "90% done" figure that does not move across three reports, and the green status that conflicts with that stalled progress. Before the next scheduled review, call an ad hoc review. Verify the work by inspection or a site visit instead of relying on the report. Ask for a written recovery plan with dated steps, and record the discussion and any notice in writing.
Exercise
Using the earned value example, a vendor on a 120,000 USD contract with 10% retainage has had only the Design approved milestone (20% share) accepted. The vendor has invoiced 40,000. How much is earned, how much is payable now after retainage, and what does the invoice tell you?
Show answer
Earned is 120,000 x 0.20 = 24,000. Retainage is 2,400, so 21,600 is payable now. The 40,000 invoice is well above earned value, so the vendor is billing for work that has not been accepted. Reject or reduce the invoice to the accepted amount and ask the vendor to explain the gap.