Sub topic 5
Choosing a contract type
This chapter assumes you know basic project vocabulary (scope, schedule, budget, stakeholders), have seen a work breakdown structure, and understand that a contract is a legally binding agreement. It builds on the scope of work and vendor selection chapters. Here you pick the pricing arrangement that fits the work.
What a contract type decides
A contract type is the rule for how the buyer pays the seller. It does not change the work. It changes who absorbs the financial effect of surprises.
Two kinds of surprise matter:
- Cost overrun: the work takes more hours or materials than expected.
- Scope drift: the work turns out to be different from what was described.
The three common types split these risks differently:
| Contract type | Buyer pays | Cost risk sits mostly with | Typical fit |
|---|---|---|---|
| Fixed price (lump sum) | Agreed total price | Seller | Well-defined scope, stable requirements |
| Time and materials (T&M) | Hours worked times rates, plus materials | Buyer | Unclear scope, short or exploratory work |
| Cost-plus | Actual allowable costs plus a fee | Buyer | Large, uncertain work where costs can be audited |
The rule of thumb: the clearer the scope, the more risk you can push to the vendor. The vaguer the scope, the more risk you must keep.
Fixed price
The vendor commits to deliver the defined scope for one price. If the vendor's costs rise, the vendor's margin shrinks. If the vendor works efficiently, the vendor keeps the gain.
The sample vendor register entry from this project shows a typical fixed-price subcontract:
vendor: Northside Electrical Ltd
type: subcontractor
scope: Electrical rough-in, floors 1-3
contract_type: fixed_price
contract_value: 120000
currency: USD
retainage_rate: 0.10
owner: j.alvarez
review_cadence: weekly
deliverables:
- name: Design approved
acceptance: Signed off by the project engineer
- name: Build complete
acceptance: Inspection passed
- name: Acceptance test passed
acceptance: Client witness test signedNotice that every deliverable has an acceptance rule. A fixed-price contract is only as safe as the scope behind it. If "electrical rough-in" is vague, the vendor and buyer will each read it in their own favor.
Strengths
- Budget certainty for the buyer.
- Little effort spent checking hours.
- Clear payment points tied to deliverables.
Failure modes
- Corner cutting. A vendor losing money may reduce quality to protect margin. Acceptance criteria and inspections are your defense.
- Change-order mining. A vendor who bid low may look for any gap in scope to justify extra charges. Tight scope wording and a formal change process limit this.
- Padded bids. If the vendor is unsure of the work, the price includes a contingency you pay for whether or not it is needed.
- Vendor failure. A vendor that cannot finish at the price may stall or walk away. Check financial health during selection.
Variants
Fixed price with economic price adjustment lets the price move with a named index, such as copper or fuel prices, over a long contract. Fixed price with incentive fee adds a bonus for beating cost or schedule targets. Both reduce the vendor's exposure to things outside their control.
Time and materials
The buyer pays an hourly or daily rate for each person, plus materials at cost or with a markup. The contract sets the rates, not the total.
T&M suits work you cannot define yet, such as an early investigation, a support retainer, or urgent repair work. You start quickly and learn as you go.
The main risk is that the buyer pays for inefficiency. The vendor has little reason to finish sooner. You manage this with controls:
- Not-to-exceed cap. A ceiling on total spend that the vendor cannot pass without written approval.
- Named roles and rate card. A table of roles and hourly rates, so a junior task is not billed at a senior rate.
- Timesheet approval. Someone on your side reviews hours against actual progress each week.
- Short authorization periods. Release funds in small blocks, such as one month at a time.
A T&M contract with a cap and tight review behaves like a hybrid. It keeps flexibility but limits the downside.
Cost-plus
The buyer reimburses the vendor's actual allowable costs and adds a fee. Cost-plus is common in large construction, defense, and research, where the work is uncertain and the buyer wants the vendor to be willing to start.
The fee structure matters:
- Cost plus fixed fee (CPFF). The fee is a set amount. It does not grow if costs grow, so the vendor has no incentive to inflate costs.
- Cost plus percentage of cost. The fee is a percentage of costs. This rewards higher spending and is restricted or banned in many public-sector settings. Avoid it where you can.
- Cost plus incentive fee (CPIF). The fee changes depending on how actual cost compares to a target. Buyer and vendor share savings or overruns by a set ratio, for example 80/20.
- Cost plus award fee (CPAF). Part of the fee depends on the buyer's judgment of performance against stated criteria.
Cost-plus requires you to define "allowable cost" in the contract and keep the right to audit records. Without that, you cannot verify what you are reimbursed.
Comparing risk with a worked example
Suppose the vendor estimates a job at 1,000 hours at 100 per hour, so 100,000. The real effort turns out to be 1,300 hours.
| Contract | Estimate | Actual effort | Buyer pays | Who absorbs the extra 30,000 |
|---|---|---|---|---|
| Fixed price | 100,000 | 130,000 | 100,000 | Vendor |
| T&M, no cap | 100,000 | 130,000 | 130,000 | Buyer |
| T&M, cap 110,000 | 100,000 | 130,000 | 110,000 | Vendor beyond the cap, unless the buyer approves more |
| Cost-plus, 10% fixed fee on the estimate | 100,000 | 130,000 | 140,000 | Buyer |
A cap changes the result only if the vendor accepts the limit and you enforce it. Vendors often respond to a cap by asking for a higher rate, or by stopping at the cap and requesting a change.
Choosing: decision criteria
Ask these questions in order.
- How well defined is the scope? If you can write clear deliverables and acceptance criteria, fixed price is possible. If not, prefer T&M or cost-plus until the scope firms up.
- How stable are the requirements? Frequent changes turn a fixed-price contract into a stream of change orders. Each one is a negotiation.
- How much can the vendor control the cost? If major costs come from outside forces, such as materials markets, a fully fixed price will be padded or fail.
- How well can you oversee the work? T&M and cost-plus need people who can review hours, invoices, and records. If you cannot staff that, you lose the control that justifies the contract type.
- How much do you want the vendor to take on the work early? Less risky contracts for the vendor, such as cost-plus, make it easier to start.
- Do rules limit your options? Some organizations and public bodies require fixed price above a threshold, or prohibit percentage-of-cost fees.
Mixing types
Real contracts often combine types. A common pattern is T&M for a discovery phase, then fixed price for the build once the scope is clear. Another is fixed price for the base work with a unit-price schedule for quantities that are unknown, such as excavation volume. Mixing lets each part of the work use the type that suits its uncertainty.
Recording the choice and its consequences
Whatever you choose, record it in the vendor register and make sure the payment mechanics follow from it. In the Northside example, fixed price and milestone acceptance drive payment. Only accepted milestones count as earned, and retainage is withheld from that amount:
CONTRACT_VALUE = 120_000
RETAINAGE_RATE = 0.10
milestones = [
{"name": "Design approved", "share": 0.20, "accepted": True},
{"name": "Build complete", "share": 0.50, "accepted": True},
{"name": "Acceptance test passed", "share": 0.30, "accepted": False},
]
earned = sum(CONTRACT_VALUE * m["share"] for m in milestones if m["accepted"])
retainage = earned * RETAINAGE_RATE
payable = earned - retainage
print(f"Earned: {earned:.2f}, retainage held: {retainage:.2f}, payable now: {payable:.2f}")This prints earned 84000.00, retainage held 8400.00, and payable now 75600.00. Under T&M the same register would instead hold a rate card, a cap, and a timesheet approver.
Contract type also sets how you handle change. On fixed price, extra work needs a formal change request approved before the vendor starts. The same register tracks it:
change_request:
id: CR-014
vendor: Northside Electrical Ltd
description: Add two circuits to the server room
cost_impact: 4200
schedule_impact_days: 3
status: submitted
approvals_required:
- project_manager
- sponsor
approved_before_work_starts: trueCommon errors
- Choosing fixed price for undefined work. The result is disputes over what was included.
- Choosing T&M with no cap or review. Costs drift and nobody notices until the budget is gone.
- Using percentage-of-cost fees. They reward the vendor for spending more.
- Treating the lowest fixed bid as the best. An unrealistically low price predicts change requests or poor quality.
- Forgetting audit rights on cost-plus. Without them you cannot verify costs.
- Picking a type by habit. The same type on every project ignores how different the uncertainty is.
Exercise
A software team needs a vendor to investigate whether an old billing system can be connected to a new platform. Nobody knows how hard it is, and the budget owner wants a spending ceiling. Which contract type fits, and which control makes it safe?
Show answer
Time and materials fits, because the scope is unknown and a fixed price would be padded or disputed. Add a not-to-exceed cap, a rate card, and weekly timesheet approval, with funds released in short blocks. After the investigation, re-evaluate and consider a fixed-price contract for the build.
Exercise
A vendor quotes 200,000 fixed price for a job you estimated at 300,000. What should you check before accepting, and why?
Show answer
Check whether the vendor misread the scope, left out work, or cannot afford to deliver at that price. An unrealistically low fixed price often leads to change requests, corner cutting, or the vendor leaving. Compare the scope line by line with other bids, ask for a cost breakdown, and confirm the vendor's financial health.