01Chapter 1: Who you are managing: vendors, suppliers, and subcontractorsThis chapter assumes you know basic project management vocabulary: scope, schedule, budget, and stakeholders. You should also know how a project plan and a work breakdown structure (WBS) are organized, and have a general idea of what a contract is. You do not need legal training. The chapter introdu6 min read
02Chapter 2: Deciding what to outsourceThis chapter assumes you know basic project vocabulary (scope, schedule, budget, stakeholders), can read a work breakdown structure, and know what a contract is. It also assumes you have read the previous chapter on vendors, suppliers, and subcontractors. Here you will learn how to decide whether a 6 min read
03Chapter 3: Writing a scope of work that can be checkedA scope of work (SOW) is the part of a contract that says what the vendor will deliver, to what standard, and by when. This chapter assumes you know basic project vocabulary (scope, schedule, budget, stakeholders), how a work breakdown structure (WBS) is organized, and what a contract is. It follows7 min read
04Chapter 4: Finding and selecting vendorsThis chapter assumes you can write a scope of work with deliverables and acceptance criteria, and that you know the vendor, supplier and subcontractor distinction and the make-or-buy decision from earlier chapters. Here you take an approved scope and turn it into a chosen vendor, with a selection re6 min read
05Chapter 5: Choosing a contract typeThis chapter assumes you know basic project vocabulary (scope, schedule, budget, stakeholders), have seen a work breakdown structure, and understand that a contract is a legally binding agreement. It builds on the scope of work and vendor selection chapters. Here you pick the pricing arrangement tha6 min read
06Chapter 6: Contract terms that matter to the project managerThis chapter assumes you know basic project vocabulary (scope, schedule, budget, stakeholders), how a work breakdown structure is organized, and what a contract is in general terms. It does not make you a lawyer. Your organization's legal counsel drafts and approves the contract. Your job is to read6 min read
07Chapter 7: Managing vendor risk, insurance, and liabilityThis chapter assumes you know basic risk vocabulary (probability, impact, response) and have read the earlier chapters on contract types and key contract terms. Here you will find where vendor risk comes from, how contracts and insurance move it between parties, and how to check that the protection 6 min read
08Chapter 8: Onboarding and kickoffThis chapter assumes you know the basic vocabulary of scope, schedule, budget, and stakeholders. It also assumes you have read the earlier chapters on scope of work and contract terms. Onboarding is the step where the signed contract becomes working practice. A vendor that starts without it often wo6 min read
09Chapter 9: Setting a communication and reporting rhythmThis chapter assumes you know basic project management vocabulary (scope, schedule, budget, stakeholders). It also assumes you have read how a contract is structured and how onboarding sets up a vendor. Here you will build the working rhythm of meetings, reports, and escalation paths that keeps an e7 min read
10Chapter 10: Fitting vendor work into the project scheduleThis chapter assumes you can read a network diagram, know the terms predecessor, float and critical path, and have a signed scope of work from an earlier chapter. It covers how to place vendor activities in your schedule, how to model the dependencies they create, and how to keep the schedule 6 min read
11Chapter 11: Monitoring performance and holding reviewsThis chapter assumes you know basic project management vocabulary (scope, schedule, budget, stakeholders), can read a work breakdown structure, and have seen a contract. It also builds on the scope of work and the communication rhythm you set up earlier. Once the vendor is working, your job is to fi7 min read
12Chapter 12: Controlling changes to vendor workThis chapter assumes you know basic project management vocabulary (scope, schedule, budget, stakeholders), how a work breakdown structure is organized, and what a contract is. It also assumes you have read the earlier chapters on scope of work, contract types, and contract terms, because change cont7 min read
13Chapter 13: Verifying invoices and paying against milestonesThis chapter assumes you know the contract types from earlier in the tutorial (fixed price, time and materials, cost-plus). It also assumes you have a scope of work with accepted deliverables, and a change control process for vendor work. Here you will learn how to turn those documents into a paymen6 min read
14Chapter 14: Resolving issues and disputesThis chapter assumes you know the basic project vocabulary of scope, schedule, budget, and stakeholders. It also assumes you have read the earlier chapters on scope of work, contract terms, change control, and performance monitoring. Here you will learn how to move a vendor problem from a first comp6 min read
15Chapter 15: Acceptance, closeout, and lessons learnedThis chapter assumes you know basic project vocabulary (scope, schedule, budget, stakeholders), how a work breakdown structure is organized, and what a contract is. It also builds on earlier chapters: the scope of work and acceptance criteria, contract terms, change control, and milestone payments. 6 min read