Sub topic 12
Controlling changes to vendor work
This chapter assumes you know basic project management vocabulary (scope, schedule, budget, stakeholders), how a work breakdown structure is organized, and what a contract is. It also assumes you have read the earlier chapters on scope of work, contract types, and contract terms, because change control depends on all three.
Why vendor changes need their own process
A change to internal work costs you effort. A change to vendor work costs you money, because the vendor will bill for it. The contract fixes a price for a defined scope, so any work outside that scope is either a change you agreed to pay for or a dispute waiting to happen.
Vendor changes also carry a legal edge. If a vendor starts extra work on a verbal instruction and later invoices for it, you may owe the money even though nobody budgeted for it. Change control protects the budget, the schedule, and the relationship at the same time.
Changes usually come from one of these sources:
- The client or sponsor asks for something new.
- The scope of work was ambiguous, and each side read it differently.
- Site conditions or technical facts differ from what the plan assumed.
- A regulation, standard, or dependency changes.
- The vendor proposes a better method or a substitute material.
The change control path
Your contract should name a single route that every change follows. The route is the same whether the change is large or small. Only the approval level differs.
The order matters. The vendor starts the changed work only after the signed change order exists. Updating the baselines comes last, so that later performance reports compare against the current agreed plan.
What a change request contains
A change request is a short written record. It needs enough information for an approver to decide without a meeting. The example below is from the Northside Electrical contract used throughout this tutorial.
change_request:
id: CR-014
vendor: Northside Electrical Ltd
description: Add two circuits to the server room
cost_impact: 4200
schedule_impact_days: 3
status: submitted
approvals_required:
- project_manager
- sponsor
approved_before_work_starts: trueEach field does a job:
| Field | Purpose |
|---|---|
| `id` | Gives the change a unique reference, so invoices and emails can cite it. |
| `description` | States exactly what is added, removed, or altered. |
| `cost_impact` | Shows the price change, which the vendor normally quotes and you verify. |
| `schedule_impact_days` | Shows the effect on the vendor's finish date, which you check against the critical path. |
| `status` | Tracks where the request is in the process. |
| `approvals_required` | Names the people who must sign, set by the size of the change. |
| `approved_before_work_starts` | Records the rule that no work begins without approval. |
A fuller request would also record the reason for the change, the effect on risk and quality, and a link to the contract clause that allows it. Keep those in your own template.
Assess impact before you decide
Do not approve a change on the vendor's price alone. Check four things.
- Cost. Compare the vendor's quote with the contract rates or a reasonable estimate. On a fixed price contract the vendor prices the change. On time and materials, check hours and rates against the rate card.
- Schedule. A three day delay for the vendor may be a longer delay for the project if the vendor's task is on the critical path. If it has float, the project end date may not move at all.
- Dependencies. Ask which other vendors or internal tasks need the changed output. A change to one vendor's deliverable can force changes to another vendor's work.
- Risk and quality. New work may need new testing, new insurance cover, or a new permit.
Also ask whether the change really is a change. If the original scope of work already covered the item, the vendor must do it at the contract price. This is why a checkable scope of work and clear acceptance criteria matter. A vague scope turns every disagreement into a change request.
Set approval levels
Not every change needs the sponsor. A tiered approval table keeps small changes quick and large ones visible. The thresholds below are an example. Set yours from the project's budget and risk tolerance.
| Change size | Example | Approvers |
|---|---|---|
| No cost, no schedule effect | Clarifying a drawing note | Project manager |
| Up to 1% of contract value | Minor material substitution | Project manager |
| 1% to 5% of contract value, or any critical path delay | Two extra circuits, 3 day delay | Project manager and sponsor |
| Over 5% of contract value, or any change to the end date or acceptance criteria | Redesign of a subsystem | Change control board and sponsor |
For CR-014, the cost is 4,200 on a 120,000 contract, which is 3.5%. Under the example table, it needs both the project manager and the sponsor, which matches the approvals_required list.
Include the cumulative effect in your rules. Ten changes that each fall under the 1% limit can add up to a large overrun. Track the running total of approved changes against the original contract value, and send the whole set to the sponsor when it passes a set limit.
Handle urgent and informal changes
Real projects produce pressure to start work now. Plan for this so people do not bypass the process.
- Emergency changes. Allow a fast path for safety or critical outage work. A named person may give written authority by email, with the formal change order following within a fixed number of days.
- Verbal instructions on site. Teach your team to say, "Send me a change request first." A site supervisor who agrees to extra work in passing can bind the project to a cost.
- Work started before approval. Treat it as a process breach. Record it, decide whether to accept or reject the work, and remind the vendor of the contract clause. Do not quietly pay it, because that teaches everyone the process is optional.
Contract type changes what a change means
The contract type you chose earlier affects how you price and control changes.
| Contract type | How changes are priced | What to watch |
|---|---|---|
| Fixed price | The vendor quotes a price for the added or removed work. | Inflated quotes, because the vendor knows the buyer needs the work. Ask for a cost breakdown. |
| Time and materials | Extra hours and materials are billed at agreed rates. | Scope growth hidden inside normal timesheets. Require a change request for work beyond the agreed estimate or cap. |
| Cost-plus | Extra costs are reimbursed with the fee or percentage. | Unnecessary cost growth. Approve changes in advance and audit the cost records. |
On fixed price work, changes also include reductions. If the buyer removes an item, ask for a credit. Vendors rarely offer one unprompted.
Keep records and update the baselines
Keep a change register for each vendor, or one register for the project with a vendor column. Record the id, date, description, cost, days, approvers, decision, and date of the signed order. When the change is approved, update:
- The contract value and payment schedule. If milestone shares change, the payment calculation changes too.
- The vendor's schedule and the integrated project schedule.
- The scope of work and acceptance criteria, if the deliverable itself changes.
- The project budget and the contingency or management reserve used.
For example, if CR-014 is approved, the Northside contract moves from 120,000 to 124,200. The retainage held on later payments is then calculated from the new total at the 10% rate in the contract. Tell your finance team, so the invoice they receive matches the order they have on file.
CONTRACT_VALUE = 120_000
RETAINAGE_RATE = 0.10
approved_changes = [
{"id": "CR-014", "cost_impact": 4200, "approved": True},
{"id": "CR-015", "cost_impact": 1800, "approved": False},
]
approved_total = sum(c["cost_impact"] for c in approved_changes if c["approved"])
current_value = CONTRACT_VALUE + approved_total
change_percent = approved_total / CONTRACT_VALUE * 100
print(f"Approved changes: {approved_total}")
print(f"Current contract value: {current_value}")
print(f"Change as share of original: {change_percent:.1f}%")
print(f"Retainage on full value: {current_value * RETAINAGE_RATE:.2f}")Only approved changes enter the total. CR-015 is pending or rejected, so it stays out of the contract value and the running percentage.
Common errors
- Letting the vendor define the change. The vendor may describe a change in a way that favors its price. Write the description yourself and check it against the original scope.
- Approving without a schedule check. A cheap change can still push the project end date.
- Splitting a large change into small ones to stay under an approval limit. Add a rule that related changes are assessed together.
- Forgetting downstream updates. Approving the order but not updating the baseline makes later performance reports misleading.
- Slow approvals. If requests wait for weeks, the vendor may stop work or proceed at risk. Set a response time, such as five working days, and track it.
- No rejection record. Tell the vendor in writing when a request is declined, so there is no later claim that you implied consent.
Connect change control to the rest of the project
Change control sits between several other processes. Performance monitoring uses the updated baseline to judge the vendor fairly. Payment management checks that every invoice line matches the contract or a signed change order. When a vendor and buyer cannot agree whether something is a change, the matter moves to issue escalation and, if needed, dispute resolution. Closeout confirms that all orders were signed, delivered, and paid.
Exercise
A vendor on a fixed price contract worth 80,000 submits a change request for 3,200 that adds a day of testing and delays its finish by 2 days. The task has 5 days of float. Using the example approval table in this chapter, who must approve it, and does the schedule impact move the project end date?
Show answer
The cost is 3,200 / 80,000 = 4%, which falls in the 1% to 5% band, so both the project manager and the sponsor must approve it. The 2 day delay is smaller than the 5 days of float, and the task is not on the critical path, so the project end date does not move. You should still update the vendor's schedule, remember the float is now reduced to 3 days, and issue the signed change order before the vendor starts the extra testing.
Exercise
A site supervisor tells you that the vendor's foreman has already started installing extra outlets because the client asked for them in a hallway conversation. No change request exists. What do you do?
Show answer
Ask the vendor to pause the extra work until it is authorized. Record the event as a process breach. Have the vendor submit a written change request with cost and schedule impact, then assess it like any other. If you approve it, issue a signed change order. If you reject it, tell the vendor in writing and decide whether the installed work must be removed. Remind the supervisor and client that only the named approvers can authorize changes.