Deciding what to outsource
This chapter assumes you know basic project vocabulary (scope, schedule, budget, stakeholders), can read a work breakdown structure, and know what a contract is. It also assumes you have read the previous chapter on vendors, suppliers, and subcontractors. Here you will learn how to decide whether a piece of work is done by your own team or bought from an outside party. This is called a make-or-buy decision. You make it before you write a scope of work or look for vendors.
Why the decision comes first
Every outsourced item adds management work: a scope to write, a vendor to select, a contract to administer, invoices to check, and changes to control. Outsourcing the wrong item costs more than the vendor's price. Outsourcing nothing can leave the project short of skills or people.
The decision belongs in procurement planning. This is the early step where you decide what the project will buy, when, and in what form. Its outputs are a list of items to procure and a rough approach for each. The later chapters cover how to carry those items out.
What "make" and "buy" mean
- Make means your own organization does the work with its own staff, tools, and accountability.
- Buy means an outside party does it under a contract. The outside party might supply a finished product (a supplier), perform a service, or do a defined part of the project (a subcontractor).
- Hybrid options sit between them. Examples are renting equipment and operating it yourself, hiring a contractor who works inside your team, or buying a component and having your team integrate it.
Treat the hybrid options as real choices. Many projects settle on one because pure make and pure buy each fail on one criterion.
Factors to weigh
No single factor settles the decision. Work through these and record the answers.
Capability and capacity
Ask two separate questions. Can your team do this work well (capability)? Does your team have the free time to do it within the schedule (capacity)? A team can have the skill and still lack the hours. Buying fixes a capacity gap quickly. A capability gap is harder, because you must also judge the quality of work you cannot do yourself.
Cost
Compare the full cost of each option, not only the quoted price. The cost to make includes loaded labor (salary plus overhead), tools, training, and the opportunity cost of what those people would otherwise do. The cost to buy includes the vendor's price, your oversight time, and a reserve for the risk that the vendor performs poorly.
Control and quality
Work that needs frequent adjustment, or that shapes how the product feels to the client, is easier to steer in-house. A vendor works to the contract. Every change you make mid-stream goes through change control, which takes time and may cost money.
Core competence and intellectual property
Work that gives your organization its competitive edge is a poor candidate for outsourcing. So is work that produces sensitive know-how or data. If you buy it, you must protect that information through contract terms.
Risk transfer
Some contract types shift cost and schedule risk to the vendor. A later chapter covers them. Be careful with this idea. A fixed price transfers cost risk, but it does not transfer your responsibility for the project's outcome. If the vendor fails, the client still looks to you.
Supply, market, and timing
Check that qualified vendors exist and are available when you need them. A thin market means higher prices and less leverage. Also consider how long the need lasts. A one-time need for specialized equipment usually favors buying or renting. A continuing need may favor building the capability.
Dependencies on the schedule
Work on the critical path deserves extra thought. Outsourcing it puts your finish date in someone else's hands. That can be acceptable if you have a strong contract and a reliable vendor. It is risky if the vendor is new to you.
A decision flow
The flow below is a screening aid, not a formula. Use it to see which questions to ask in what order.
Comparing full costs
A common error is to compare the vendor's price with the internal labor cost alone. The comparison below includes the extras on both sides. The numbers are examples.
# Make-or-buy cost comparison for one work package.
# All figures are illustrative.
# Make: do the work with the project's own staff.
hours_needed = 900
loaded_rate = 55.00 # salary plus overhead, per hour
tooling = 12_000.00 # equipment or licenses bought for this work
make_cost = hours_needed * loaded_rate + tooling
# Buy: a vendor does the work for a fixed price.
vendor_price = 58_000.00
oversight_hours = 120 # your time to select, manage, review, and pay
oversight_rate = 70.00
risk_reserve_rate = 0.05 # extra held against vendor underperformance
buy_cost = (
vendor_price
+ oversight_hours * oversight_rate
+ vendor_price * risk_reserve_rate
)
print(f"Make: {make_cost:.2f}")
print(f"Buy: {buy_cost:.2f}")
print(f"Buy minus make: {buy_cost - make_cost:.2f}")Running it prints Make: 61500.00, Buy: 69300.00, and Buy minus make: 7800.00.
The vendor's price (58,000) looks lower than the make cost (61,500). Once oversight (8,400) and the risk reserve (2,900) are added, buying costs 7,800 more. The result flips because the extra costs were counted.
The numbers still do not decide the question. If the team has no free hours, the make cost is not available no matter how low it looks. Cost tells you the price of each path, and capacity tells you which paths are open.
Edge cases and common errors
Treating a vendor price as the whole cost
The example above shows this. Add oversight, integration, training, and the cost of changes. Include the cost of switching vendors if the first one fails.
Outsourcing to fix a management problem
If a work package is poorly defined, handing it to a vendor does not make it clearer. The vendor will price the ambiguity, and then dispute it. Define the work first, as the next chapter explains.
Ignoring lock-in
After a vendor builds something proprietary, switching is expensive. Ask what happens at the end of the contract. Who owns the output, the documentation, and the data? Can another party maintain it? Write the answers into the contract.
Deciding once and never revisiting
Conditions change. A key person may leave, a vendor may exit the market, or a quote may rise. Review make-or-buy decisions at stage gates or when a major assumption changes. Reversing late is costly, so the review should look at what is already committed.
Splitting work across too many parties
Each additional vendor adds an interface that you must coordinate. Several small contracts can give flexibility, but they also create gaps where no one is accountable. Group related work under one vendor when the work is tightly coupled.
Letting one stakeholder decide alone
A sponsor may favor a familiar vendor, or an engineer may want to keep interesting work. Record the criteria and the evidence, and have the decision reviewed. This protects the project and gives you a written rationale if the choice is questioned.
Recording the decision
Write down each decision briefly. A short record is enough:
| Field | What to record |
|---|---|
| Work item | The WBS element under consideration |
| Decision | Make, buy, or hybrid |
| Main reasons | The two or three factors that decided it |
| Cost comparison | Full cost of each option, with assumptions |
| Risks accepted | What could go wrong, and who owns the response |
| Review trigger | The event that would cause you to revisit |
This record feeds the next steps. Items marked "buy" or "hybrid" go forward to scope writing and vendor selection, and the stated risks go to your risk register.
Summary of the working model
- Start from the WBS and list the candidate work items.
- Screen each for core competence, capability, and capacity.
- Compare the full cost of each open option.
- Check that the market has qualified vendors and that the risk is manageable.
- Choose make, buy, or hybrid, and record the reasons and review triggers.
Exercise
Your team can build a reporting module in 600 hours at a loaded rate of 50 per hour, with no extra tooling, but the team has no free time for the next three months. A vendor offers a fixed price of 36,000. You estimate 80 oversight hours at 60 per hour and a 5% risk reserve on the vendor price. Calculate both full costs, then say which option you would choose and why.
Show answer
Make cost is 600 x 50 = 30,000. Buy cost is 36,000 + (80 x 60 = 4,800) + (5% of 36,000 = 1,800) = 42,600. Making is cheaper by 12,600 on cost. However, the team has no capacity for three months, so the make option cannot meet the schedule as stated. A sound answer chooses to buy, or to consider a hybrid such as a contractor working inside the team, because capacity rules out the cheaper path. The answer should also note that the decision be revisited if the schedule can absorb a delay of three months.
Exercise
A colleague proposes outsourcing a poorly defined work package so that "the vendor can figure it out." Give two problems with this and one step you would take first.
Show answer
The vendor will price the uncertainty into the quote or later claim extra payment through change requests, and you will have no clear basis for judging whether the work is complete. A first step is to define the work: clarify the deliverables and acceptance criteria in a scope of work before deciding to buy.