Sub topic 10
Fitting vendor work into the project schedule
This chapter assumes you can read a network diagram, know the terms predecessor, float and critical path, and have a signed scope of work from an earlier chapter. It covers how to place vendor activities in your schedule, how to model the dependencies they create, and how to keep the schedule honest when the vendor's dates move.
Why vendor work needs special treatment in the schedule
Your own team's tasks sit under your control. You can reassign people, add overtime, or resequence work. A vendor's tasks sit under the vendor's control, and the vendor serves other customers. Three consequences follow:
- Dates are commitments, not estimates you own. The vendor's dates come from the contract, so a slip is also a contract event.
- Information is delayed. You see progress through reports and reviews, not by walking the floor.
- Dependencies cross organizational boundaries. A handoff between your team and a vendor involves two managers, two priorities and often two calendars.
A schedule that treats a vendor task as one more bar with a duration hides all three problems.
Model vendor work as more than one activity
A common mistake is a single task such as "Switchgear delivered, 30 days." That bar mixes your work, the vendor's work and waiting time. Break it into pieces you can control and track separately:
- Your inputs to the vendor. Approved drawings, site access, client decisions, free-issue materials. These are the vendor's dependencies on you.
- The vendor's lead time. Fabrication, procurement, or mobilization. This is a duration you do not control.
- The vendor's work on site. Installation, configuration, or delivery.
- Your acceptance activity. Inspection, testing, and sign-off. Acceptance takes time and people on your side, so it needs its own bar.
Each piece gets an owner. The vendor owns piece 2 and most of piece 3. You own pieces 1 and 4. Most "vendor delays" are actually late inputs from the buyer, and the contract usually lets the vendor claim time for them.
Dependency types you will use
| Dependency | Meaning | Vendor example |
|---|---|---|
| Finish-to-start (FS) | B cannot start until A finishes | Install switchgear after it is delivered |
| Start-to-start (SS) | B cannot start until A starts | Your inspector starts when the vendor starts site work |
| Finish-to-finish (FF) | B cannot finish until A finishes | Documentation finishes when installation finishes |
| Lag | A fixed wait between linked tasks | 10 days of concrete curing before equipment mounting |
Dependencies also differ by origin:
- Mandatory dependencies come from the nature of the work. You cannot test what is not built.
- Discretionary dependencies come from preference or best practice. You can sometimes compress them, at a cost.
- External dependencies come from outside the project, such as a permit or a vendor's delivery slot. Vendor milestones are external dependencies from your project's point of view. Mark them visibly so everyone knows you do not control them.
A worked example: finding float with a vendor on the path
The following script runs a forward and backward pass over a small network. It shows which tasks have float and which are critical. The network is a simplified version of the electrical example used earlier in this tutorial. Durations are in working days.
tasks = {
"Design approved": (5, []),
"Order switchgear": (1, ["Design approved"]),
"Switchgear lead time": (30, ["Order switchgear"]),
"Rough-in floors 1-3": (20, ["Design approved"]),
"Install switchgear": (3, ["Switchgear lead time", "Rough-in floors 1-3"]),
}
def schedule(tasks):
"""Return {name: (early_start, early_finish, total_float)}.
Tasks must be listed so that predecessors come first.
"""
es, ef = {}, {}
for name, (duration, preds) in tasks.items():
es[name] = max((ef[p] for p in preds), default=0)
ef[name] = es[name] + duration
end = max(ef.values())
ls, lf = {}, {}
for name in reversed(list(tasks)):
duration = tasks[name][0]
succs = [s for s, (_, preds) in tasks.items() if name in preds]
lf[name] = min((ls[s] for s in succs), default=end)
ls[name] = lf[name] - duration
return {n: (es[n], ef[n], ls[n] - es[n]) for n in tasks}
for name, (start, finish, slack) in schedule(tasks).items():
flag = "critical" if slack == 0 else f"float {slack}"
print(f"{name:<22} day {start:>2} to {finish:>2} {flag}")It prints:
Design approved day 0 to 5 critical
Order switchgear day 5 to 6 critical
Switchgear lead time day 6 to 36 critical
Rough-in floors 1-3 day 5 to 25 float 11
Install switchgear day 36 to 39 criticalThe vendor's lead time sits on the critical path. Your own rough-in has 11 days of float. Two lessons follow:
- Any slip in design approval or in placing the order moves the whole project, because both sit ahead of a 30-day vendor wait.
- The float on rough-in is not free. If the vendor's lead time grows from 30 to 35 days, the rough-in float grows to 16 days. If your rough-in crew is the one that slips by 12 days, the vendor's work becomes non-critical but the project end date moves.
Getting dates from the vendor
You need more than a delivery date from each vendor. Ask for:
- A resource-loaded or at least milestone-level schedule that matches the scope of work's deliverables.
- Lead times for long-lead items, with the date each must be ordered by.
- The inputs the vendor needs from you, with the date each is needed.
- Their assumptions, such as working hours, crew size, and site access windows.
Then reconcile their schedule with yours. A vendor's plan that starts the day your design is approved assumes zero review time on your side. If the two plans disagree, resolve it at kickoff, not in week six.
Put the agreed milestone dates in the contract or an attached schedule. A date that lives only in an email thread cannot support a delay claim or a termination notice.
Buffers and reserves
There are two places to hold protection, and they should not be mixed up:
- Schedule contingency belongs to the project manager. It is a reserve for known risks, set aside at the project level. Do not tell the vendor about it.
- Vendor padding is the margin vendors build into their own durations. You cannot see it, but you can estimate it by comparing quotes and past performance.
Place a buffer before a critical vendor milestone rather than hiding it in every task. A buffer in front of the switchgear order date, for example, protects the long lead item from late design approval.
Keeping the schedule current
- Status the vendor's tasks on a fixed day. Use the reporting cadence from the previous chapter. Collect percent complete, forecast finish, and blockers.
- Forecast, don't just record. A vendor that reports "80 percent done" on day 20 of a 25-day task has not told you the finish date. Ask for remaining effort and a forecast finish.
- Re-run the critical path after every update. Vendor tasks that had float last month may be critical now.
- Track your obligations with the same rigor. Keep a list of every input you owe a vendor, with due dates and owners, and review it in each status meeting.
A leading indicator worth watching is the vendor's input-to-start gap: the days between receiving what they need from you and their stated start. If the gap keeps shrinking, expect a delay.
Common failure modes
- Hidden dependencies. Two vendors share a work area or an access window, but nobody modeled the conflict. Add resource or location constraints to the schedule.
- Optimism in milestones. A vendor reports a milestone as met when only a demo was done. Tie the milestone to the acceptance criteria in the scope of work.
- Late buyer inputs. The project is late because your approvals were late. This weakens your position in any dispute and may entitle the vendor to extra time or cost under the contract.
- Accepting a recovery plan with no new information. "We'll make up the time" is not a plan. Ask what changes: more crew, longer shifts, resequenced tasks, or parallel work.
When a vendor slips
Follow a defined order:
- Confirm the slip and its cause, with the evidence from reports and records.
- Check whether you owe an input that is late.
- Re-run the schedule to see the effect on the critical path and the end date.
- Ask for a recovery plan, and evaluate it against the contract terms.
- If the delay needs a contract change, route it through change control. If it cannot be resolved, move to the escalation path covered in a later chapter.
Exercise
A vendor's 30-day fabrication task is on your critical path. Your design approval, a task that feeds the vendor's order, slips by 4 days. The design task has no float. What happens to the project end date, and what should you check before telling the vendor they are late?
Show answer
The project end date moves by 4 days, because design approval, the order, and the 30-day vendor lead time are all on the critical path. Before blaming the vendor, check whether the late design approval is your own input to them. If it is, the delay is yours, and the vendor may be entitled to a time extension. Re-run the schedule, document the cause, and decide whether to raise a change request or to recover time elsewhere.
Exercise
In the worked example, the rough-in task has 11 days of float. The vendor's lead time grows from 30 to 40 days. How much float does rough-in have now, and which tasks are critical?
Show answer
Rough-in float rises to 21 days, because the vendor path now finishes 10 days later while rough-in stays unchanged. Design approved, order switchgear, switchgear lead time, and install switchgear stay critical, and the project end moves from day 39 to day 49.