Sub topic 6
The starter system and what it contains
This chapter assumes you know what scope items are (covered in the previous chapter) and have a working picture of an S/4HANA implementation: a business process runs on an ERP system, and the project team configures that system to match the business. You do not need hands-on configuration experience.
What a starter system is
A starter system is a preconfigured SAP S/4HANA system that the project team uses during the Explore phase. SAP Best Practices content is already active in it, so the team can show real standard processes on a running system instead of describing them on slides.
In a fit-to-standard workshop, the business users see their order-to-cash or procure-to-pay process executed in the software. They react to what they see. That reaction is the raw material for fit, configuration, and delta classification.
The starter system is a tool for the workshop. It is not the customer's future system, and it is not a first draft of the customer's configuration.
What it contains
The exact content depends on the SAP S/4HANA edition and deployment option, so check the current documentation for your edition. In general, a starter system holds four kinds of content.
| Content | What it gives the workshop | Typical limitation |
|---|---|---|
| Activated scope items | Standard processes ready to run, with the configuration SAP Best Practices defines | Only the scope items activated in that system can be demonstrated |
| Sample organizational structure | A fictitious company with company codes, plants, sales organizations, and similar units | It does not match the customer's real structure |
| Sample master and transactional data | Customers, vendors, materials, and open documents for running processes end to end | Sample data is not customer data and is not migrated |
| Standard roles and users | Business roles and test users that show what each user sees in the Fiori launchpad | Authorizations are not tailored to the customer's organization |
Fiori apps are the primary user interface. Users reach processes through role-based tiles in the launchpad, so the demonstration shows what the end user would actually see.
Starter system versus the project's own systems
A frequent misunderstanding is that the starter system becomes the development system. Treat these as separate systems with separate purposes.
- The starter system exists to show standard behavior and let users challenge it.
- The project's own systems, built later, hold the customer's organizational structure, configuration, and eventually migrated data.
- Decisions made in the workshop are recorded in project documentation, not by changing the starter system and hoping the change carries over.
Some starter system setups allow limited configuration changes for demonstration. Even then, the record of a decision belongs in the backlog or workshop log. The record must say what value was agreed and why. A change that exists only in the starter system will not reach the project's own systems.
Where it fits in the workshop flow
The scope items you select drive what must be active. The workshops then produce findings, and the findings, not the starter system itself, move forward into the backlog.
Preparing the starter system
Preparation is a checklist, and each item prevents a specific failure during the session.
- Confirm that the scope items for the agenda are active. If a scope item is not active, the facilitator cannot demonstrate it. Improvising in the session wastes the business users' time.
- Check that the sample data supports the process end to end. For example, a sales order demonstration needs a customer, a material with stock or availability, and pricing data. Run the whole process once before the workshop.
- Prepare users and roles. The facilitator needs access to every role used in the demonstration. A process often crosses roles, such as a sales clerk creating an order and a credit manager releasing it.
- Agree on access for the team. Some team members may want to try transactions themselves between sessions. Decide who gets access and under what rules.
- Take a baseline. Know the state of the system before the series starts, so you can reset or compare it if the data is changed during demonstrations.
A short record in the project tracker helps keep this visible. The following example is illustrative and tool-neutral.
{
"id": "F2S-PREP-003",
"scopeItem": "Sales Order Processing",
"starterSystemCheck": {
"scopeItemActive": true,
"dryRunCompleted": true,
"sampleDataSufficient": true,
"rolesAvailable": ["Sales clerk", "Credit manager"]
},
"openIssues": [],
"status": "ready for workshop"
}What the workshop can and cannot conclude from it
The starter system supports some conclusions well and others poorly.
It supports:
- Whether a standard process step exists and how it behaves.
- Whether the user interface and flow are acceptable to the people who will use it.
- Which options appear to be available, which you then verify in the configuration documentation.
It does not support:
- Performance conclusions for the customer's data volumes.
- Final organizational structure decisions.
- Conclusions about customer-specific master data, such as real pricing conditions.
- Integration conclusions for the customer's other systems, unless those connections have been set up.
When a user says "this works the same as our process" because the sample data happens to behave that way, record the assumption. A fit that depends on sample data can turn into a gap once real data arrives.
Common errors
- Presenting sample organizational data as a proposal. If the starter system shows company code 1010 and the team treats it as the design, the real structure gets skipped. State clearly in the session that the sample structure is for demonstration only.
- Demonstrating more than the scope. Scope items that happen to be active but were not selected can pull the workshop into topics outside the agreed solution scope.
- Skipping the dry run. Missing data or authorizations are the most common cause of a stalled demonstration.
- Recording decisions only in the system. The starter system is not the system of record for decisions.
- Treating sample data behavior as proof of fit. See above. Test the edge cases that matter to the customer.
Putting it together
Imagine a workshop on Accounts Payable. The facilitator opens the starter system as a finance user and posts a vendor invoice using sample vendor data. The business users ask whether a second approval is possible above a threshold. The facilitator shows the standard options in the system, and the team records the finding as a configuration candidate in the backlog, not as a change in the starter system. The agreed threshold is captured as a decision with an owner. Later, the Realize phase applies it in the project's own system.
Exercise
A key user says, "We saw in the starter system that the sales organization is 1010, so let's keep it." What is wrong with this reasoning, and what should the facilitator do?
Show answer
The starter system uses a sample organizational structure for demonstration. It is not the customer's design. The facilitator should explain that the structure shown is fictitious, record the real organizational structure as a separate decision to be made with the right people, and not treat the sample values as agreed configuration.
Exercise
Name three things to check before the first workshop session so that a demonstration in the starter system does not stall.
Show answer
Any three of the following: the selected scope items are active; the sample data supports the process end to end (confirmed by a dry run); the facilitator has access to every role used in the process; the baseline state of the system is known so it can be restored after the demonstrations.