Sub topic 8
Preparing the Workshop Series
This chapter assumes you know the basics of SAP S/4HANA, the phases of an ERP implementation, and process terms such as order-to-cash and procure-to-pay. It also assumes you have met the idea of scope items and the starter system from earlier chapters. Here the focus is on the work that happens before the first workshop starts.
Why preparation decides the outcome
A fit-to-standard workshop is short and dense. Business users see a standard process demonstrated, react to it, and the team records decisions. If the room lacks the right people, the right data, or a system that runs the process, the time goes to explaining and searching instead of deciding. Most workshop failures can be traced back to missing preparation.
Preparation has four parts:
- Settle the scope and break it into workshops.
- Prepare the starter system and the demonstration data.
- Build the agenda and the materials.
- Confirm attendees and their roles.
Step 1: Settle the scope and group the scope items
The project's solution scope comes from the sales phase and the Discover and Prepare work. In SAP Activate terms, that scope is expressed as a list of scope items from SAP Best Practices content. Each scope item describes one business process or a group of related processes, together with its test scripts and configuration.
Turn that list into a workshop plan:
- Group scope items by business area, such as finance, sourcing and procurement, sales, manufacturing, and supply chain.
- Keep related scope items in the same workshop when they share master data or hand over documents. Order-to-cash steps, for example, should not be split across unrelated sessions.
- Put cross-area topics, such as organizational structure, master data, and integration, in their own sessions, because they affect every area.
- Estimate duration from the number of scope items and the number of process steps, not from a fixed number of hours per area.
A sequence that works well is to start with the enterprise structure and master data, then run the end-to-end process areas, and finish with cross-cutting topics such as reporting, authorizations, and data migration. Early sessions set decisions that later sessions rely on, such as company codes and chart of accounts.
Step 2: Prepare the starter system and data
The starter system is a system with SAP Best Practices already activated. It lets the team demonstrate real processes instead of slides. Preparation here has three tasks.
First, confirm that the scope items in your plan are active in the system. If a scope item is missing, activate it or plan a way to show it before the session. Do not discover this during the workshop.
Second, load demonstration data that business users recognize. Standard sample data proves that a process works, but users judge fit more reliably when the data looks like theirs. Use a small set of customer-like materials, business partners, and organizational units. Keep it small. The aim is recognition, not migration.
Third, prepare the user accounts and authorizations that the presenter needs to run each role's steps. A presenter who cannot post an invoice because of a missing authorization loses minutes in front of the whole group.
A dry run of each workshop closes this step. The presenter runs the full demonstration end to end, notes any step that fails, and fixes it. Treat the dry run as required for each workshop, not as an extra.
Step 3: Build the agenda and materials
Each workshop needs an agenda that follows the process, not the organization chart. A typical agenda for one process area contains:
- A short introduction: goals, the scope items covered, and how findings will be classified.
- An end-to-end overview of the process, so participants see where their step sits.
- A step-by-step demonstration in the system, one scope item at a time.
- Time after each step for questions, challenges, and recording.
- A closing review of open items, decisions made, and owners.
Allow more time than the demonstration alone needs. A common rule of thumb is that discussion and recording take as long as the demonstration. If an agenda has no slack, the team will skip recording, and the findings will be lost.
Prepare these materials before the session:
| Material | Purpose |
|---|---|
| Process flow diagrams for each scope item | Give the end-to-end view and show hand-overs |
| Test scripts or demo scripts from the Best Practices content | Guide the demonstration step by step |
| Findings template or tracker | Record classification, decision, owner, and status in one format |
| Glossary of the customer's terms mapped to SAP terms | Avoids arguments caused by different words for the same thing |
| Pre-reading for attendees | Lets users arrive with questions instead of first impressions |
The findings template matters most. Agree on its fields before the first workshop, so every session produces records that look the same. The following record shows a typical shape for a configuration finding.
{
"id": "F2S-FI-014",
"scopeItem": "Accounts Payable",
"processStep": "Post vendor invoice",
"finding": "Business requires a second approval for invoices above a company-specific threshold",
"classification": "configuration",
"decision": "Evaluate the standard approval workflow options before proposing any custom development",
"owner": "Finance process lead",
"status": "open"
}Use a consistent ID scheme, such as the workshop series prefix, the area, and a running number. IDs make later traceability into the backlog possible.
Step 4: Identify attendees and roles
Attendance affects decision quality more than any other factor. Plan the following roles for each session:
- Facilitator. Leads the session, keeps time, and enforces the adopt-before-adapt stance.
- Presenter. Runs the demonstration in the system. This is often a solution consultant for the area. The facilitator and presenter can be different people so that one can listen while the other operates the system.
- Scribe. Records findings live in the template. Do not leave this to the facilitator.
- Business process owner. Has authority to accept or reject a standard process for the area.
- Key users. Run the process day to day and know the exceptions.
- Technical and architecture representatives. Judge extensibility and integration impact when a gap appears.
Invite people by role and then by name. A business process owner who cannot attend leaves the team unable to decide, and decisions deferred to a later meeting add delay. If an owner is unavailable, name a delegate with the same decision authority.
Keep the group small enough that everyone speaks. Key users from different areas can join only the sessions that touch their handover steps.
Common preparation errors
- Scope too broad per workshop. Participants tire, and later scope items get rushed. Split the series further.
- No dry run. Demonstration failures consume the time meant for decisions.
- No agreed template. Records differ per workshop and cannot be merged into one backlog.
- Decision makers absent. Findings stay open, and the same topics return in later meetings.
- Pre-tailored system. The gap between standard and need becomes invisible.
Exercise
A project plans one workshop for "Order-to-cash" with eight scope items. The dry run shows that two scope items fail in the starter system. The business process owner for sales can only join for the first hour. What preparation actions would you take before the workshop, and why?
Show answer
Fix or reactivate the two failing scope items and repeat the dry run, or move them to a later session once they work, so the group is never shown a broken process. Split the workshop into smaller sessions so the eight scope items do not run in one sitting. Schedule the sessions that need the business process owner's decisions within the hour they are available, or name a delegate with the same decision authority for the rest. Confirm that the findings template and the scribe are in place so every decision is recorded in the same format.
Exercise
Why should the starter system not be configured to match the customer's wishes before the workshops?
Show answer
The workshops exist to show the business the standard process and record how far it fits. Pre-tailoring the system hides the real gap between standard and need, weakens the adopt-before-adapt approach, and removes the evidence that justifies later configuration or delta decisions.