This chapter assumes you know what SAP Activate is, what the Explore phase is for, and how findings are classified as fit, configuration, or delta. It also assumes you have seen how findings move into a backlog. Here we cover what the workshop series must produce, how those outputs are reviewed, and what sign-off means.
Why outputs matter
A fit-to-standard workshop is only useful if its results can be found, trusted, and used later. The Realize phase builds from these results. If a finding is vague, missing, or unowned, the team that configures or develops the system has to guess. Guesses become rework.
Treat the outputs as the contract between Explore and Realize. They record what the business agreed to adopt, what will be configured, and what will be built as a delta.
What the workshop series produces
The exact artifact names vary by project and tool. The content below is what most teams need to keep.
| Output | What it holds | Main consumer |
|---|---|---|
| Finding log | Every observation, with scope item, process step, and classification | Whole project team |
| Configuration decisions | Values and choices agreed for each setting | Configuration consultants |
| Delta requirements | Gaps with business justification, priority, and proposed approach | Solution architect, developers |
| Solution scope statement | The confirmed list of scope items and any added or removed items | Project manager, sponsor |
| Open issues and actions | Questions with an owner and a due date | Project manager |
| Attendance and agenda records | Who took part in which session | Project manager, auditors |
The finding log
The finding log is the base record. Every other output derives from it. Each entry should have a stable ID, the scope item, the process step, a plain statement of the finding, the classification, the decision, an owner, and a status.
The following record shows a configuration finding.
{
"id": "F2S-FI-014",
"scopeItem": "Accounts Payable",
"processStep": "Post vendor invoice",
"finding": "Business requires a second approval for invoices above a company-specific threshold",
"classification": "configuration",
"decision": "Evaluate the standard approval workflow options before proposing any custom development",
"owner": "Finance process lead",
"status": "open"
}Note that the decision does not say "build an approval". It says to evaluate standard options first. That follows the adopt-before-adapt mindset.
Delta requirement records
A delta record carries more detail than a configuration finding, because it must be estimated and justified. It needs a business justification, a proposed approach, and a priority.
{
"id": "F2S-SD-007",
"scopeItem": "Sales Order Processing",
"processStep": "Create sales order",
"finding": "A customer-specific document layout is required that standard output management does not provide",
"classification": "delta",
"businessJustification": "Contractual requirement from a key customer",
"proposedApproach": "Review extensibility options in order of preference, starting with in-app and key user extensibility",
"priority": "must-have",
"status": "to be estimated"
}The status "to be estimated" shows the record is not yet approved work. It enters the review described below.
The output lifecycle
Findings move through a small set of states. Keep the states few, and define each one so that two people read a status the same way.
The loop from Rejected back to Open matters. A declined delta is often reclassified as configuration once someone finds a standard option. Do not delete rejected items. Keep them so that the reasoning is visible later.
Review
Review happens at two levels.
- Per-session review. At the end of each workshop, the facilitator reads back the findings and decisions. Attendees correct wording on the spot. This is cheap and catches most errors.
- Series-level review. After all workshops, the core team checks the whole log for consistency. Typical checks are listed below.
Series-level checks:
- Every finding has a classification, an owner, and a status.
- No two findings contradict each other across scope items. For example, one workshop must not assume a single approval step while another assumes two.
- Every delta has a justification and has been tested against the available extensibility options.
- Cross-area dependencies are visible. A change to a finance setting may affect sales or procurement.
- Each scope item that was planned has been covered, or its omission is explained.
Challenging deltas
The review is where the clean core principle is enforced. For each delta, ask in order:
- Can a standard process, configuration option, or standard variant meet the need?
- Can the business adjust its process without losing value?
- If not, which extensibility option is the least invasive: in-app, key user, or side-by-side?
Record the answers in the delta record. A reviewer who sees "no alternative considered" should return the item.
Sign-off
Sign-off is the formal agreement that the outputs are an accurate and sufficient basis for the Realize phase. It is not agreement that the project will never change.
What is being signed
- The classification of findings, especially the list of deltas.
- The configuration decisions.
- The solution scope, including any scope items added or removed.
- The remaining open items, each with an owner and a date.
Who signs
Sign-off usually involves the business process owners for the areas covered, the project manager, and the solution architect. The sponsor or steering committee often approves the overall scope. Name the signers in the project plan before the workshops start, not at the end.
Partial and conditional sign-off
Large projects rarely sign everything at once. You can sign off by process area, as each series completes. You can also sign with conditions, for example "approved except items F2S-SD-007 and F2S-SD-011, pending estimates". State the conditions in the sign-off record.
After sign-off: change control
Signed-off outputs form a baseline. Later changes go through change control rather than informal edits. A new request is logged, assessed for impact on scope, cost, and schedule, and approved or declined by the agreed body. Keep the link between the change and the original finding ID so the history is traceable.
Common mistakes
| Mistake | Effect | Remedy |
|---|---|---|
| Writing findings after the workshop from memory | Wrong or missing details | Capture live, read back at session end |
| Treating sign-off as a formality | Business disputes outputs in Realize | Give signers time and a review checklist |
| Deleting rejected deltas | Same request returns without context | Keep them with the reason for rejection |
| Mixing decisions and discussion in one field | Developers cannot tell what was agreed | Separate "finding" from "decision" |
| No traceability from finding to backlog item | Gaps are built twice or not at all | Keep the finding ID on every backlog item |
Exercises
Exercise
A delta record has the status "to be estimated" and the proposed approach "build a custom report". The review notes contain no mention of standard reports or key user tools. What should the reviewer do, and why?
Show answer
Return the item to the owner. The review must confirm that standard options and the least invasive extensibility options were checked first, in line with clean core. The owner should document what was evaluated and why it is insufficient, or reclassify the finding as configuration or fit if a standard option works.
Exercise
Your project signs off the Finance area while two Sales deltas still await estimates. How can you record this without delaying Finance?
Show answer
Use partial and conditional sign-off. Sign the Finance area as a complete unit. Record Sales as signed with conditions, naming the two delta IDs and the pending estimates, each with an owner and a due date.