Sub topic 15
From workshop findings to the backlog
This chapter assumes you know what a fit-to-standard workshop produces: a list of findings, each classified as fit, configuration, or delta. It also assumes you know the basics of SAP Activate and the Explore phase. Here you will learn how those findings move into a backlog, how to keep them traceable, and which errors break that traceability.
Why the backlog matters
A workshop finding is only a note until someone owns it. The backlog is the single ordered list of work that the project will carry into the Realize phase. Every configuration task and every approved delta requirement must appear there. If a finding never reaches the backlog, nobody builds it, and the gap surfaces later as a defect in testing or after go-live.
The backlog also gives the project a shared view of effort. Product owners, process leads, and the technical team all read from it, so its entries must be clear enough for people who were not in the workshop.
What goes into the backlog
Not every finding becomes a backlog item. The classification decides what happens next.
| Classification | Backlog action | Typical item |
|---|---|---|
| Fit | No build item. Record the confirmation against the scope item. | The standard process was accepted as demonstrated. |
| Configuration | Create a configuration item with the decided values or the open question. | Set a second approval threshold for vendor invoices. |
| Delta | Create a delta item only after the gap review. It needs a justification and an estimate. | Customer-specific document layout. |
Fit findings still matter. Keep them on record so the team can show later which parts of the standard process the business accepted. This protects the project when someone asks why a requirement was never built.
Carrying the record forward
Each finding keeps one identifier from the workshop to the backlog. Never renumber it. The identifier is the thread of traceability, because it lets you follow a requirement from the process step to the build item, the test case, and the sign-off.
Compare the two example records below. The first is a configuration finding.
{
"id": "F2S-FI-014",
"scopeItem": "Accounts Payable",
"processStep": "Post vendor invoice",
"finding": "Business requires a second approval for invoices above a company-specific threshold",
"classification": "configuration",
"decision": "Evaluate the standard approval workflow options before proposing any custom development",
"owner": "Finance process lead",
"status": "open"
}The status is open because the decision is not final. The team must still check the standard workflow options. The item enters the backlog as a configuration task, and the owner is accountable for closing it.
The second record is a delta requirement.
{
"id": "F2S-SD-007",
"scopeItem": "Sales Order Processing",
"processStep": "Create sales order",
"finding": "A customer-specific document layout is required that standard output management does not provide",
"classification": "delta",
"businessJustification": "Contractual requirement from a key customer",
"proposedApproach": "Review extensibility options in order of preference, starting with in-app and key user extensibility",
"priority": "must-have",
"status": "to be estimated"
}This record carries more fields. A delta needs a business justification and a proposed approach so reviewers can test it against the clean core principle before anyone estimates it.
The path from finding to backlog item
The flow has gates. A delta does not go straight from a workshop to the build team.
The gap review is where the clean core principle acts. The team asks whether the standard system, a configuration option, or a preferred extensibility approach can meet the need. Only a gap that survives this review is estimated.
Prioritizing the backlog
Order matters as much as content. Use a small, consistent set of priorities so that the whole team reads them the same way.
- Must-have: the business cannot operate or comply without it at go-live.
- Should-have: important, but a workaround exists for a limited time.
- Could-have: a convenience that can move to a later release.
Two rules help. First, set priorities with the business, not for it. Second, configuration items that other items depend on go first, since a delta often builds on a configuration decision such as an organizational structure or a number range.
Traceability in practice
Traceability means you can answer four questions for any item at any time.
- Which workshop and process step produced it?
- Who decided what, and when?
- Which build, test, and sign-off entries relate to it?
- What is its current status?
Keep these answers in one tool. Many teams use SAP Cloud ALM, while others use a general task tool. Either works if the identifier and the status fields stay consistent. Splitting the record across spreadsheets, e-mails, and slide decks is the most common way to lose it.
Common errors
- Findings without owners. An item with no owner does not move. Assign one before the workshop ends.
- Deltas entered without a justification. The reviewers cannot judge the gap, so it either stalls or passes unchecked.
- Duplicate items. Two workshops raise the same need in different words. Merge the items and keep both source identifiers.
- Open decisions hidden as closed. Marking an item done while the decision is still open pushes the risk into testing.
- Backlog items that restate the finding only. Add the acceptance criteria, so the build team knows what finished looks like.
Handling changes after the workshop
Findings are not frozen once they enter the backlog. A business user may reverse a decision, or an estimate may show that a delta costs too much. Treat each change as an update to the existing record. Note the reason, the date, and the person who approved it. Larger changes that affect the agreed solution scope follow the change control process covered in the next chapters.
Exercise
A workshop finding says that the business wants an extra approval step for vendor invoices above a set amount. It is classified as configuration. Which fields must the backlog item have before the workshop ends, and why does the identifier stay unchanged when the item moves from the workshop log to the backlog?
Show answer
The item needs an owner, a status, a link to the scope item and process step, and the decision or open question about the standard approval workflow options. The identifier stays unchanged because it is the thread of traceability. It lets the team follow the requirement from the process step to the build item, the test case, and the sign-off.
Exercise
A delta requirement for a customer-specific document layout has a business justification but no proposed approach. What should happen before it is estimated, and which outcome follows if the gap review rejects it?
Show answer
The team should add a proposed approach that reviews extensibility options in order of preference, starting with in-app and key user extensibility, and then run the gap review against the clean core principle. If the review rejects the delta, the item returns to the business to look for a standard alternative, and no estimate or build item is created.