Sub topic 16
Solution Scope and Change Control
This chapter assumes you know the Explore phase of SAP Activate, the fit, configuration, and delta classification, and the clean core principle. It covers how the solution scope is set and protected while fit-to-standard workshops run. It also covers what to do when a finding or request would change that scope.
Why scope needs a control mechanism
Fit-to-standard workshops are open by design. Business users see standard processes, react to them, and raise new needs. Without a control mechanism, every reaction can turn into a scope increase. The result is a project that agrees to more than its budget, timeline, or clean core strategy can support.
Two terms matter here:
- Solution scope is the agreed set of scope items, processes, organizational units, and delta requirements that the project will deliver. It is the baseline against which the project is measured.
- Change control is the procedure for deciding whether a proposed change to that baseline is accepted, rejected, or deferred. Each decision is recorded.
The workshops produce proposed scope. Change control keeps the proposal and the committed baseline separate until someone with authority approves the difference.
What the baseline contains
The baseline starts from the scope items selected before the workshops. Each scope item is a packaged business process from SAP Best Practices. Workshop findings then add detail to it. A practical baseline holds these elements:
- The list of scope items in scope, with the business areas and organizational units that use them.
- The configuration decisions captured per scope item.
- The approved delta requirements, each with its justification and chosen extensibility approach.
- Items explicitly out of scope, with the reason. Recording exclusions prevents the same request from returning later as a "forgotten" requirement.
- Assumptions and constraints, such as the countries, languages, and deployment model the scope depends on.
Scope states for workshop findings
A finding is not in scope just because it was written down. Give each one a state, so the team can tell proposed work from committed work.
| State | Meaning | Who decides |
|---|---|---|
| Open | Raised in a workshop, not yet assessed | Workshop facilitator |
| Assessed | Classified and, for deltas, analyzed against extensibility options | Process lead and solution architect |
| Proposed | Recommended for the baseline, pending approval | Project manager |
| Approved | Added to the baseline, ready for the backlog | Steering authority |
| Rejected or deferred | Excluded now, or moved to a later release | Steering authority |
Fit and configuration findings usually move through these states quickly, because they stay inside standard scope items. Delta requirements need the most scrutiny because each one adds build effort, test effort, and long-term maintenance.
Triggers for change control
Not every edit needs a formal request. Define a clear rule so the team knows when to escalate. Typical triggers are:
- Adding a scope item that was not in the original list.
- Adding a country, company code group, or business unit to a scope item.
- Approving a new delta requirement, or enlarging an approved one.
- Choosing an extensibility approach that is further from the standard than the one first estimated, for example moving from key user extensibility to a side-by-side extension.
- Changing a configuration decision that has already been signed off.
Choosing a different value inside a configuration option that the scope item already supports is normally not a scope change. It is a configuration decision and is recorded as such.
A change request record
Record each change with enough information for the steering authority to decide without a meeting to reconstruct the context. The following record is illustrative and tool-neutral. It links back to the delta requirement from the workshop so the trace stays intact.
{
"changeId": "CR-021",
"relatedFinding": "F2S-SD-007",
"scopeItem": "Sales Order Processing",
"changeType": "add delta requirement",
"description": "Customer-specific document layout not provided by standard output management",
"businessJustification": "Contractual requirement from a key customer",
"extensibilityOptionsReviewed": [
"in-app and key user extensibility",
"developer extensibility",
"side-by-side extension"
],
"recommendedOption": "in-app and key user extensibility",
"impact": {
"effort": "to be estimated",
"timeline": "to be assessed",
"cleanCore": "no modification of standard code"
},
"decision": "pending",
"decidedBy": null
}The fields extensibilityOptionsReviewed and cleanCore are what separate a useful request from a bare wish. They show that the team applied adopt-before-adapt before asking for more scope.
The change control flow
The flow below shows how a request moves from a workshop finding to a baseline decision.
Note that fit and configuration findings bypass the formal request. They are handled in the scope item records. Only deltas and baseline-affecting changes reach the steering decision.
Handling pressure during workshops
Scope pressure often shows up in the room, not on paper. Common situations and sound responses:
- A stakeholder asks for a feature "just in case." Ask for the business scenario and the cost of not having it. If neither is clear, record it as open and do not promote it.
- A senior attendee demands a legacy behavior. Record the requirement, then ask what outcome the behavior protects. Often a standard process reaches the same outcome by a different path.
- A request arrives after sign-off. Treat it as a change request. Sign-off is meaningful only if later requests face the same test.
- A team lead adds work informally. Remind the team that approved scope lives in the baseline, not in conversation. Informal additions that never reach the backlog cause surprises in the Realize phase.
Keeping the baseline traceable
Each approved item should be traceable in both directions. From a workshop finding, you should be able to reach the backlog item that implements it. From a backlog item, you should be able to reach the finding and the approved change request. Use a consistent identifier scheme, such as the F2S-<area>-<number> pattern in the earlier examples, and carry it into every record. Version the baseline, and keep a log of what changed between versions.
Common mistakes
- No owner for the baseline. Nobody notices drift when nobody is responsible. Name one person.
- Treating every delta as approved by default. A delta needs a justification, an extensibility review, and a decision.
- Escalating everything. If routine configuration choices go through change control, approvers lose time and stop reading. Keep the triggers narrow.
- Not recording rejections. Rejected and deferred items return unless the reason is written down.
- Approving a delta without an estimate. The steering authority cannot weigh cost against benefit without one.
Exercise
During a workshop on Accounts Payable, a user asks to add a second company code group that was not in the agreed scope. Separately, another user asks to change a tolerance value that the existing scope item already supports. Which request goes through change control, and why?
Show answer
The second company code group goes through change control because it extends the approved scope to a new organizational unit, which affects effort, testing, and timeline. The tolerance value change is a configuration decision within an already supported option, so it is recorded in the configuration log and does not need a formal change request, unless that value was already signed off, in which case changing it is a trigger.
Exercise
A change request proposes a side-by-side extension, but the request does not show which other extensibility options were reviewed. What should the steering authority do, and why?
Show answer
Return the request for completion before deciding. Without evidence that in-app and key user extensibility and developer extensibility were considered first, the team cannot show that the proposal follows adopt-before-adapt, and the clean core impact cannot be judged.