Worked Example: A Complete DMAIC Project Charter
Starting assumptions
This example assumes that you understand the five DMAIC phases: Define, Measure, Analyze, Improve, and Control. You should also know what a process, defect, and metric are. The charter below is for a fictional order-entry project at the Dayton service center.
A strong charter connects the business need to a measurable problem, a target, and clear boundaries. It does not claim to know the root cause before the Analyze phase.
How the charter fits together
The business case explains why the project deserves attention. The problem statement describes the current gap without suggesting a solution. The metric makes the gap observable, and the goal defines the intended result.
Complete charter example
The following sketch shows how the elements can appear in one document.
project_charter:
title: Reduce order entry errors at the Dayton service center
business_case: >
Rework from order entry errors costs about $18 per order and delays
delivery, which is the top driver of customer complaints.
problem_statement: >
From January to June 2026, 6.2% of orders (770 of 12,400) had at least
one data entry error that required rework before shipment.
primary_metric:
name: order entry error rate
definition: orders with at least one data entry error / total orders entered
baseline: 6.2%
data_source: order management system rework log
goal_statement: >
Reduce the order entry error rate from 6.2% to 3.0% or lower by
2026-12-18 and sustain it for 8 consecutive weeks.
scope:
process_start: customer order received by a service representative
process_end: order released to the warehouse
in_scope:
- phone and email orders entered at the Dayton service center
out_of_scope:
- web orders
- warehouse picking errors
- changes to the order management software vendor contract
team:
sponsor: Director of Customer Operations
project_lead: Green Belt, Customer Operations
members:
- service representative
- order management analyst
- finance partner
milestones:
define: 2026-07-17
measure: 2026-08-14
analyze: 2026-09-11
improve: 2026-10-30
control: 2026-12-18
risks_assumptions_constraints:
- assumption: rework log is complete and accurate
- risk: November order volume may strain the pilot
- constraint: no budget for new software licensesChecking the important fields
The problem statement gives the period, location, count, rate, defect definition, and impact. It does not say that employees need training or that automation is required. Those may become hypotheses later.
The primary metric has an operational definition. An operational definition states exactly how a measure is calculated. Here, an order counts as defective if it has at least one data entry error requiring rework before shipment. The baseline uses 770 defective orders divided by 12,400 total orders.
The goal includes the metric, starting value, target, deadline, and sustainment condition. The sustainment condition prevents the team from declaring success after one unusually good week.
The scope starts when a service representative receives a phone or email order and stops when the order is released to the warehouse. Web orders and warehouse picking remain outside the project. These boundaries prevent the team from expanding into related problems that it cannot study within the planned schedule.
Sponsor review
During review, the sponsor should confirm that the problem matters, the goal is feasible, the team has authority to act, and the data source is available. The sponsor should also challenge vague language such as “improve efficiency” and solution claims such as “install automation.”
After corrections, the sponsor signs off on the charter. That approval authorizes the team to begin Measure and gives later decisions a shared reference point.
Exercise
The team proposes this goal: “Automate order entry by September.” What should be corrected before sponsor sign-off?
Show answer
Replace it with a measurable outcome goal, such as reducing the defined order entry error rate from its baseline to a target by a stated date. Automation can remain a possible improvement, not an assumed solution.