Where the Charter Fits in DMAIC
Prerequisites
This chapter assumes that you know the basic meaning of process, defect, metric, and Lean Six Sigma. You should also recognize the five DMAIC phases: Define, Measure, Analyze, Improve, and Control.
The charter's place in DMAIC
DMAIC is a structured method for improving an existing process:
- Define establishes what problem the project will address and why it matters.
- Measure describes current process performance with reliable data.
- Analyze identifies likely causes of the performance gap.
- Improve tests and implements changes that address verified causes.
- Control preserves the improvement and detects a return to poor performance.
A project charter belongs primarily to the Define phase. It is the agreement that gives the improvement project a clear purpose, boundary, owner, and expected result. The charter does not prove root causes or select a solution. Those decisions belong to later phases.
The charter should be specific enough to guide decisions but flexible enough to change when evidence improves understanding. For example, the team might discover during Measure that its original data source is incomplete. The team can update the charter, record the change, and obtain sponsor agreement. Revising an assumption is different from quietly expanding the project.
What the charter does
A useful charter connects the business need to a measurable improvement effort. It normally records:
| Charter element | Question it answers |
|---|---|
| Business case | Why should the organization spend time and resources on this problem? |
| Problem statement | What performance gap exists, where, and when? |
| Primary metric and baseline | How will current performance and progress be measured? |
| Goal statement | What result must the project achieve, and by when? |
| Scope | Which process steps, products, locations, and customers are included? |
| Team and governance | Who sponsors, leads, supports, and approves the work? |
| Milestones and risks | When will major work occur, and what could limit progress? |
The charter also prevents a common failure: beginning with a preferred solution. “Install automated order entry” describes an intervention, not a problem. A Define-phase charter should state the observed gap first. The team can evaluate automation in Improve after Measure and Analyze establish whether it addresses a verified cause.
How the charter connects the phases
The Define phase creates the initial project logic:
- A business need identifies why the issue matters.
- A problem statement describes the gap without claiming its cause.
- A metric and baseline make the gap observable.
- A goal defines the intended level and deadline.
- Scope limits the work to a manageable process and population.
- Roles, milestones, risks, and assumptions make the work governable.
Measure then tests whether the metric definition and baseline are trustworthy. Analyze uses the defined problem and scope to investigate causes. Improve uses the goal as a decision criterion for proposed changes. Control uses the same primary metric to confirm that the gain remains.
A sponsor should review the charter before substantial analysis begins. Sign-off means that the organization agrees on the problem, expected result, boundaries, resources, and decision authority. It does not mean that every detail is known.
Exercise
Why should a project charter avoid naming a solution in the problem statement?
Show answer
Naming a solution narrows the investigation before the team measures performance and verifies causes. The charter should describe the gap so later phases can compare possible improvements against evidence.