Sub topic 8
Setting Scope: In, Out, and Process Boundaries
This chapter assumes you know the five DMAIC phases, what a process is, and how a defect and metric are defined. You will use the project goal and problem statement as inputs when setting scope.
Why scope matters
Scope states which work the project will study and which work it will leave alone. A clear scope keeps the team focused, makes data collection manageable, and prevents the project from becoming a general attempt to improve everything.
Scope has three related parts:
- Process boundaries: The exact start and stop points of the process under study.
- In-scope work: Activities, locations, products, customers, or time periods the project includes.
- Out-of-scope work: Related areas the project deliberately excludes.
Scope should match the problem statement and goal. If the goal concerns order entry errors at one service center, the project should not quietly expand to warehouse picking, web orders, or all company locations.
Set the process boundaries
Choose a start point that the team can observe and measure. Choose a stop point that marks the end of the problem area or the point where the project hands work to another process.
For an order entry project, the boundaries might be:
- Start: A customer order is received by a service representative.
- Stop: The order is released to the warehouse.
The project then studies the activities between those points, such as reading the order, entering fields, checking information, and releasing the order. Warehouse picking begins after the stop point, so picking errors belong to another project.
Avoid vague boundaries such as “improve customer service” or “fix the order process.” These descriptions do not identify where the process begins or ends.
Define what is in and out
List inclusions and exclusions in concrete terms. Useful scope dimensions include:
- Location, such as the Dayton service center.
- Channel, such as phone and email orders.
- Product or customer type.
- Time period.
- Process steps.
- Defect or outcome being studied.
For example:
| Scope category | Decision for the order entry project |
|---|---|
| In scope | Phone and email orders entered at the Dayton service center |
| In scope | Data entry and verification before warehouse release |
| Out of scope | Web orders |
| Out of scope | Warehouse picking errors |
| Out of scope | Replacing the order management software |
The last exclusion matters because a proposed solution should not silently become part of the project boundary. The team may later discover that software changes are useful, but the Analyze and Improve phases should provide evidence before that decision is made.
Test the scope with stakeholders
Review the draft scope with the project sponsor, process owner, and people who perform the work. Ask:
- Can the team collect reliable data within these boundaries?
- Does the scope cover the problem described in the charter?
- Could another team reasonably own the excluded work?
- Is the project small enough to complete within its timeline?
- Does any exclusion remove an important part of the customer or business impact?
Record disagreements as decisions, assumptions, or risks. Do not resolve them by making the scope silently broader.
Common scope errors
- Scope creep: Adding locations, products, or process steps without changing the goal, resources, or timeline.
- A solution disguised as scope: Defining the project as “implementing automation” instead of studying the error.
- Unclear handoffs: Failing to state who owns work before the start or after the stop point.
- Overly narrow scope: Excluding a process step that is necessary to understand the defect.
- Overly broad scope: Including every channel or location when the team has data from only one.
A good scope is narrow enough to manage and broad enough to explain the measured problem.
Exercise
A team is studying late shipments caused by order entry errors. Should warehouse picking be in scope if the project stops when the order is released to the warehouse?
Show answer
No. Warehouse picking is outside the stated process boundary. The team should record picking as out of scope and refer any separate picking problem to the process owner or a future project.