Sub topic 13
Common Charter Mistakes and How to Fix Them
Assume you understand the five DMAIC phases, process defects, and basic metrics. This chapter focuses on reviewing a project charter before the team begins detailed measurement and analysis. A good charter creates agreement about the problem, the goal, and the work boundary. A weak charter sends the team toward a preferred solution or an unclear target.
Mistake: Embedding a Solution in the Problem Statement
A problem statement should describe the gap between current performance and expected performance. It should not claim why the gap exists or prescribe a fix. The Analyze phase tests possible causes. The Improve phase evaluates solutions.
A statement such as “The order entry process needs automation” contains both an untested cause and a proposed solution. Automation may help, but the defect could instead come from unclear instructions, missing data, training gaps, or system settings.
Use this structure:
- What is happening?
- How large is the gap?
- Where and when does it occur?
- What impact does it have?
| Weak statement | Improved statement |
|---|---|
| Order entry is inefficient and needs automation. | From January through June 2026, 6.2% of orders entered at the Dayton service center required rework because of at least one data entry error. Rework adds 1.5 days to delivery and about $18 in labor per order. |
Mistake: Using Vague or Unsupported Numbers
Words such as “many,” “often,” and “slow” do not define a measurable gap. Replace them with a count, rate, time, cost, or other operational measure. An operational definition states exactly how the team will classify and count the result.
For example, “order entry error rate” could mean the percentage of order lines with errors or the percentage of orders with at least one error. Those measures are different. Record the numerator, denominator, data source, time period, and location.
Avoid false precision. If the data source is incomplete or the measurement method is still being checked, label the value as provisional and state the limitation.
Mistake: Writing a Goal Without a Baseline or Deadline
A goal should connect the primary metric to a current baseline, target, deadline, and sustainability requirement. “Improve order accuracy” does not tell the team how much improvement is required or when success will be judged.
A stronger goal is:
Reduce the order entry error rate, defined as orders with at least one data entry error divided by total orders entered, from 6.2% to 3.0% or lower by December 18, 2026, and sustain the result for 8 consecutive weeks.The target should be challenging but credible. Check historical performance, customer requirements, process capability, and available time before accepting it.
Mistake: Making Scope Too Broad or Too Narrow
Scope defines where the project starts and stops. Without boundaries, the team may investigate related problems that the sponsor never approved.
State the process start and stop points, then list what is in scope and out of scope. For example, the project may start when a service representative receives a phone or email order and stop when the order is released to the warehouse. Web orders, warehouse picking, and vendor-contract changes may be excluded.
Mistake: Treating the Charter as a One-Time Form
A charter is an agreement that can be refined as the team learns more. The sponsor should review the problem, metric, goal, scope, roles, milestones, risks, assumptions, and constraints. Record open questions instead of silently making decisions.
Before sign-off, ask:
- Does the problem describe evidence rather than a suspected cause?
- Can two people calculate the primary metric the same way?
- Does the goal include a baseline, target, and deadline?
- Are the process boundaries and exclusions explicit?
- Does the sponsor agree to provide time, data, and authority?
Quick Review
Exercise
A draft says, “Install barcode scanners to eliminate shipping errors by the end of the quarter.” What should be corrected first?
Show answer
Replace the solution-based statement with a measured problem statement. Define the error metric, baseline, location, impact, and time period. Then set a goal and evaluate barcode scanners alongside other possible improvements.