Recording Risks, Assumptions, and Constraints
This chapter assumes you know the five DMAIC phases and understand processes, defects, and metrics. In the Define phase, a project charter records three conditions that shape the work: risks, assumptions, and constraints. Recording them early prevents avoidable surprises and makes the charter a realistic agreement with the sponsor.
Distinguishing the three conditions
A risk is an uncertain event that could affect the project. The event may prevent the team from meeting its goal, delay the schedule, or weaken the data. For example, a November order peak may reduce the service center’s capacity for a pilot.
An assumption is something the team accepts as true for planning purposes, even though it has not been fully verified. For example, the team may assume that the order management system’s rework log includes every order sent back for correction.
A constraint is a fixed limit that restricts the available choices. A budget limit, a required deadline, a staffing rule, or a system that cannot be changed during the project can be a constraint.
| Condition | Key question | Example |
|---|---|---|
| Risk | What might happen? | November volume may delay the pilot. |
| Assumption | What are we treating as true? | The rework log is complete. |
| Constraint | What limit must we accept? | No budget is available for new software. |
Do not treat an existing problem as a risk. If incomplete data already exists, record it as a current issue and assign an action to verify or correct it.
Build a useful register
Add a short register to the charter. Each entry should state the condition, its possible effect, its owner, and the planned response. A response can reduce a risk, test an assumption, or work within a constraint.
For the Dayton order-entry project, the register might contain these entries:
- Risk: November order volume may strain the pilot. Effect: The team may miss observations or see unusual error rates. Owner: Project lead. Response: Complete the pilot before the seasonal peak or analyze peak-period data separately.
- Assumption: The rework log captures all data-entry corrections. Effect: The baseline may be understated if records are missing. Owner: Order management analyst. Response: Compare the log with a sample of shipment holds during Measure.
- Constraint: No new order-entry software may be purchased. Effect: Improvements must use existing tools. Owner: Sponsor. Response: Prioritize standard work, training, and configuration changes that do not require a new license.
A risk needs a probability and impact assessment when the project is large enough to justify one. A simple scale such as low, medium, and high is usually sufficient in a charter. Avoid false precision. The purpose is to focus attention, not to create a complicated risk model.
Connect the register to the DMAIC plan
Risks, assumptions, and constraints should affect later planning:
- Test data assumptions during Measure.
- Investigate risks that could distort the Analyze results.
- Design Improve actions that fit the constraints.
- Add controls for risks that could return after implementation.
- Review the register at each phase milestone.
Review with the sponsor
Before sign-off, ask the sponsor whether the listed conditions reflect operational reality. Confirm which limits are truly fixed and which may be negotiable. Confirm that each high-impact item has an owner. A charter is incomplete when it lists concerns but gives nobody responsibility for them.
Exercise
The team assumes that its customer complaint data is complete, but a sample finds many complaints recorded only in email. How should the charter change?
Show answer
Record data completeness as a current issue, assign an owner to reconcile the sources, and revisit the baseline and goal after measuring the missing records.