Sub topic 5
Writing the Problem Statement
This chapter assumes you know the five DMAIC phases (Define, Measure, Analyze, Improve, Control). It also assumes you know what a process, a defect, and a metric are. You do not need to have written a charter before.
The problem statement is the part of the charter that says what is wrong. Every other section depends on it. The goal is measured against it, the scope is drawn around it, and the Measure phase starts by checking its numbers. A vague or biased problem statement carries its flaws into the whole project.
What a problem statement must do
A good problem statement describes the gap between what the process delivers and what it should deliver. It states four facts:
- Size: how big the gap is, as a number, a rate, or a cost.
- Location: where in the business or process the gap occurs.
- Time period: when the data was collected.
- Impact: what the gap costs the customer or the business.
It also leaves two things out: a cause and a solution. At the Define phase you do not yet know why the problem happens. Naming a cause now closes off the Analyze phase before it starts, and naming a solution turns the project into an implementation task.
Weak and better statements
The example below compares a weak statement with a better one, using the same fictional order entry process used throughout this tutorial.
Weak: Our order entry process is inefficient and needs to be automated.
Better: From January to June 2026, 6.2% of customer orders entered in the Dayton service center (770 of 12,400) contained at least one data entry error that required rework before shipment. Each reworked order adds an average of 1.5 days to delivery and about $18 in labor cost.The weak statement has three faults:
- "Inefficient" is an opinion with no measure. Nobody can check whether it is true or whether it improved.
- "Needs to be automated" is a solution hidden inside the problem. If the data later shows the errors come from unclear order forms, automation would not help, but the charter already commits to it.
- It gives no location, time period, or impact, so a reader cannot tell how large the problem is or whether it deserves a project.
The better statement gives all four facts. It names the defect precisely ("at least one data entry error that required rework before shipment"). It shows the count and the denominator (770 of 12,400). It states the impact in days and dollars. It never says why the errors happen or what to do about them.
A quick check on the numbers: 770 divided by 12,400 is 0.0621, which rounds to 6.2%. Always confirm that the percentage and the counts agree. A reviewer who spots an arithmetic mismatch will doubt the rest of the charter.
Where the problem statement comes from
The problem statement draws on two earlier parts of the charter.
The business case explains why the problem matters to the organization. Here, rework costs money and delays delivery, which is the top driver of customer complaints. The business case justifies spending effort on the problem.
The voice of the customer (VOC) is what customers say they need, in their own words, such as "my order arrived late." A critical-to-quality (CTQ) requirement turns that into something measurable, such as "orders ship within the promised delivery time." The problem statement should describe a gap against a requirement that customers or the business actually care about. A gap against an internal preference, such as "our team likes tidier forms," is not a strong basis for a project.
The following diagram shows how these inputs feed the statement and what the statement feeds in turn.
Building the statement step by step
Work through these steps in order. Each one produces a piece of the final sentence.
Step 1: Define the defect in operational terms
An operational definition says exactly how to decide whether one item is a defect. "Error" is not enough. In the example, a defect is an order with at least one data entry error that required rework before shipment. Two people applying this definition to the same order should reach the same answer.
Note the unit. The statement counts orders with errors, not errors. An order with three wrong fields counts once. Mixing these units is a common source of inconsistent numbers later.
Step 2: Collect data for a defined period
Pull real data from a named source. In the example the source is the order management system's rework log, covering January to June 2026. Use a period long enough to include normal variation. Six months is better than one week, because a single bad week can mislead.
Step 3: State the size with a count and a denominator
Give the number of defects and the number of opportunities, then the rate. "6.2%" alone hides the volume. "770 of 12,400" lets a reader judge how reliable the figure is.
Step 4: State the location
Say where the problem occurs: a site, a team, a product line, or a step. Narrower is usually better. "The Dayton service center" is more workable than "customer operations."
Step 5: Quantify the impact
Translate the gap into the cost the business feels: time, money, customer complaints, or risk. Use figures you can source, and say if a figure is an estimate. The example uses an average of 1.5 days of added delivery time and about $18 of labor per reworked order.
You can sanity-check the cost of the problem with the data you already have, as the short script below shows. It is a rough annualized view, not a claim for the charter.
errors = 770
orders = 12_400
cost_per_rework = 18 # dollars of labor per reworked order
rate = errors / orders
six_month_cost = errors * cost_per_rework
print(f"Error rate: {rate:.1%}")
print(f"Rework labor cost over six months: ${six_month_cost:,}")Running it prints an error rate of 6.2% and a six-month rework labor cost of $13,860. That cost alone is modest, so the business case probably rests on delivery delay and complaints as well. If the numbers do not support the business case, say so before the sponsor does.
Step 6: Check for hidden causes and solutions
Reread the draft and remove any word that explains why or prescribes how. Common offenders are "because," "due to," "lack of," "need to," "should implement," and the names of tools or systems.
Testing your statement
Use this table as a review checklist.
| Test | Question to ask | Fails when |
|---|---|---|
| Measurable | Does it contain a number with a unit? | It uses words like "slow," "poor," or "inefficient" |
| Bounded | Does it name a place and a time period? | It says "across the company" with no dates |
| Sourced | Can someone find the data? | The figure comes from memory or opinion |
| Cause-free | Does it avoid explaining why? | It says "because staff are untrained" |
| Solution-free | Does it avoid saying what to do? | It says "needs a new system" |
| Consequential | Does it state an impact? | The reader asks "so what?" |
Common errors
- Restating the solution as the problem. "We do not have a barcode scanner" describes a missing solution, not a gap in performance. Ask what result the missing scanner causes, and state that result.
- Blaming people. "Representatives are careless" is a cause, it is unproven, and it makes the team defensive. Describe the outcome instead.
- Using a baseline you have not verified. If the rework log is incomplete, the true rate may differ. Record this as an assumption in the charter and plan to validate it in the Measure phase.
- Choosing a scope too wide to act on. A statement about "all orders" hides where the problem concentrates. If the data shows web orders are clean, say the problem is in phone and email orders.
- Mixing units. Reporting errors in one sentence and orders with errors in another produces numbers that do not reconcile.
Revising a draft
Consider this draft: "Poorly trained representatives make too many mistakes entering orders, so we should add a second review step."
Rewrite it using the steps above. It contains a cause (poor training), a solution (a second review step), and no measures. Replacing those with the sourced facts yields the better statement shown earlier. The ideas about training and review are not lost. Record them as hypotheses to test in the Analyze phase, or in a separate list of ideas, but keep them out of the problem statement.
Exercises
Exercise
A draft problem statement reads: "Due to outdated forms, too many invoices are wrong, so we need to redesign the invoice template." Name three things wrong with it and list the facts you would collect to fix it.
Show answer
It names a cause ("outdated forms"), it names a solution ("redesign the invoice template"), and it has no measure ("too many"). To fix it, collect: the operational definition of a wrong invoice, the count of wrong invoices and total invoices over a stated period, the location (team or site), the data source, and the impact (cost of corrections, payment delays, or complaints). Then write the statement using only those facts, and move the form and template ideas to a hypothesis list for the Analyze phase.
Exercise
A statement says "In March 2026, 90 of 1,500 shipments (9.0%) arrived late at the Reno warehouse." Check the arithmetic and say which of the four required facts is missing.
Show answer
90 divided by 1,500 is 0.06, so the rate is 6.0%, not 9.0%. The counts and the percentage do not agree and must be reconciled with the source data. The size, location (Reno warehouse), and time period (March 2026) are present, but the impact is missing. The statement should add what late shipments cost in customer complaints, penalties, or labor. Also define "late" operationally, and consider using a longer period than one month.