Reviewing the Charter and Getting Sign-Off
This chapter assumes you can already write a problem statement, a primary metric with a baseline, a SMART goal, and a scope. It also assumes you know the five DMAIC phases. Here you take a finished draft and get it approved. Approval is the point where the sponsor agrees to the work and commits resources. It is not a formality at the end of the Define phase.
Why the review matters
A charter is a working agreement between the project lead and the people who control the resources. If the sponsor never reads it closely, the first disagreement shows up in the Analyze or Improve phase, when changes are expensive. Examples are "I thought web orders were included" or "that target is too low." A good review moves those disagreements to the start of the project.
The review has three jobs:
- Check that the charter is internally consistent: the problem, metric, goal, and scope all describe the same thing.
- Check that the charter is feasible: the team, timeline, and constraints can support the goal.
- Record a decision: the sponsor approves, approves with changes, or declines.
Who reviews and in what order
Review in two passes. First, do a self-review and a peer review. Then hold the sponsor review.
- Self-review. Read the charter the next day, not right after writing it. Run the consistency checks below.
- Peer review. Ask a Black Belt, a Master Black Belt, or an experienced colleague to read it without any briefing. If they misunderstand something, the charter is unclear. Explaining it aloud does not fix a written document.
- Process owner and finance check. The owner of the process in scope should confirm the start and stop points and the in-scope list. A finance partner should confirm the cost figures in the business case.
- Sponsor review. The sponsor reads the revised draft, discusses it with you, and signs off.
Consistency checks
Most charter defects are mismatches between sections. Check each pair below.
| Check | Question to ask | Typical failure |
|---|---|---|
| Problem and metric | Does the metric measure the gap described in the problem statement? | The problem describes late deliveries, but the metric counts data entry errors. |
| Baseline and data source | Can someone find the baseline number in the named source? | The baseline comes from memory, or the source does not exist. |
| Metric and goal | Does the goal use the same definition as the metric, with the same units? | The metric is orders with an error, but the goal is stated as errors per field. |
| Goal and scope | Can the in-scope process actually move the metric to the target? | The goal covers the whole site, but the scope covers only phone orders. |
| Scope and team | Does the team include someone from each in-scope step? | The scope includes the warehouse, but no warehouse member is on the team. |
| Goal and timeline | Does the date leave room for the Control phase and the sustain period? | The goal requires 8 stable weeks, but the Control milestone is 3 weeks after Improve. |
| Business case and goal | Is the benefit at the target level worth the project's cost? | The goal saves $2,000 a year, and the project uses six people for five months. |
You can check the sustain-period timing with simple arithmetic. In the example charter, the goal date is 2026-12-18 and the goal must hold for 8 consecutive weeks. Counting back 8 weeks (56 days) from 2026-12-18 gives 2026-10-23. The Improve milestone is 2026-10-30, which is after that date. So the 8 weeks of sustained performance cannot finish by the goal date if the improvement only goes live on the Improve milestone. The review should catch this, and the team should either move the dates or change the wording of the goal.
The following script runs that check so you can reuse it on any charter dates.
from datetime import date, timedelta
def latest_start_for_sustain(goal_date: date, sustain_weeks: int) -> date:
"""Latest date the improvement must be live to hold for the full sustain period."""
return goal_date - timedelta(weeks=sustain_weeks)
goal_date = date(2026, 12, 18)
improve_milestone = date(2026, 10, 30)
latest = latest_start_for_sustain(goal_date, 8)
print("Improvement must be live by:", latest)
print("Improve milestone:", improve_milestone)
if improve_milestone > latest:
days_late = (improve_milestone - latest).days
print(f"Conflict: the plan is {days_late} days too late for the sustain period.")
else:
print("Timeline supports the sustain period.")Running it prints a conflict of 7 days. The fix is a decision for the sponsor, and the options are in the next section.
Running the sponsor meeting
The sponsor meeting is a decision meeting, not a presentation. Send the charter at least two days beforehand so the sponsor arrives having read it. Keep the meeting to 30 to 45 minutes.
A workable agenda:
- State the ask (2 minutes). "I need your approval to start, plus these named people for the team."
- Walk through the problem, metric, and goal (10 minutes). Show the baseline data, not only the summary.
- Confirm scope (10 minutes). Read the out-of-scope list aloud. Sponsors often notice a missing exclusion here.
- Review team, timeline, and risks (10 minutes). Ask for specific commitments, such as hours per week for each member.
- Decide (5 minutes). Get a clear answer and record who will do what.
Bring the options when you raise a problem. For the timeline conflict above, you could offer:
- Move the goal date to 2027-01-15, which allows 8 weeks after a go-live on 2026-11-20.
- Shorten the sustain period to 4 weeks and state that Control will continue monitoring afterward.
- Pull the Improve milestone forward to 2026-10-23, if the pilot can be run sooner.
Each option has a cost. The first delays the benefit, the second weakens the evidence of a lasting result, and the third raises schedule risk. Let the sponsor choose, and record the choice.
What to challenge, and what to leave open
Some items should be fixed at sign-off. Others should stay open until the Measure and Analyze phases give you data.
| Fix at sign-off | Leave open until later |
|---|---|
| Problem statement, metric definition, and baseline | Root causes |
| Goal statement, target, and deadline | The specific solution |
| In-scope and out-of-scope lists, process start and stop | Detailed process maps |
| Sponsor, project lead, team members | Exact data collection plan |
| Phase milestone dates | Final cost savings estimate |
If the sponsor asks you to add a solution to the charter, for example "include the new software in the goal," explain that naming a solution before analysis closes off other options. Offer to record the idea in a separate list of "ideas received" for the Improve phase.
Recording sign-off
Sign-off should leave evidence. A short block at the end of the charter is enough.
charter_approval:
version: 1.2
review_date: 2026-07-10
decision: approved_with_changes
changes_required:
- move goal date from 2026-12-18 to 2027-01-15 to allow 8 sustain weeks
- add the warehouse supervisor as an advisory team member
signatures:
sponsor: Director of Customer Operations
process_owner: Dayton Service Center Manager
project_lead: Green Belt, Customer Operations
finance_partner: Finance Business Partner
next_review: Define tollgate at 2026-07-17Note the version number and the list of changes. After approval, the charter is a controlled document. Changes to the goal, scope, or deadline need the sponsor's agreement and a new version, with the reason recorded. Minor changes, such as a team member swap, can be noted without a full re-review. This keeps the team from drifting without a record, which is called scope creep when it expands the work.
When the sponsor declines or delays
A decline is a valid outcome of the review. Common reasons and responses:
- The business case is too small. Check whether the project can be combined with a related one, or whether a quicker fix, without a full DMAIC project, would work.
- The scope is too large. Split it into phases and charter the first one.
- No team time is available. Do not start. A project without committed time usually stalls in Measure.
- The sponsor has a different priority. Ask who else could sponsor it, or when to return.
A project that starts without real sponsor support rarely recovers. Stopping early costs less than stalling later.
Exercise
A charter states the goal as "Reduce the order entry error rate from 6.2% to 3.0% by 2026-12-18 and sustain it for 8 consecutive weeks." The Improve milestone is 2026-10-30 and the Control milestone is 2026-12-18. The sponsor asks you to approve without changes. What do you point out, and what are two options you offer?
Show answer
Eight weeks before 2026-12-18 is 2026-10-23, and the improvement does not go live until 2026-10-30. The sustain period cannot be completed by the goal date, by 7 days. Two options: move the goal date later, for example to 2027-01-15, or shorten the sustain period or pull the Improve milestone forward. Record the sponsor's choice in a new charter version.
Exercise
Name three consistency checks you would run before the sponsor meeting, and say which section pair each one compares.
Show answer
Any three of these: problem statement against metric (does the metric measure the described gap); baseline against data source (can the number be found in the named source); metric against goal (same definition and units); goal against scope (can the in-scope process reach the target); scope against team (is each in-scope step represented); goal against timeline (is there room for the sustain period); business case against goal (is the benefit worth the cost).