Sub topic 14
Worked example: a complete charter
This chapter assembles every part of the charter into one document. It then reviews that document the way a sponsor would. It assumes you have read the earlier chapters on the problem statement, the primary metric, the SMART goal, and scope. You should know the five DMAIC phases and be able to define a defect and a metric.
The situation
The Dayton service center takes phone and email orders. Service representatives type each order into the order management system. Some orders contain data entry errors, such as a wrong part number, a wrong ship-to address, or a missing quantity. A warehouse clerk or the representative catches the error and the order goes back for rework before it can ship.
The Director of Customer Operations sees rework as the top driver of customer complaints. A Green Belt is asked to lead a project. The charter is the Green Belt's first deliverable.
Build the charter in dependency order
The parts of a charter depend on each other. Writing them in the order below keeps each part grounded in the one before it.
1. Business case and customer need
The business case says why the work matters now. Here it is short: rework costs about $18 per order and delays delivery, and late delivery is the top complaint driver. The customer need is on-time, correct orders. The critical-to-quality requirement (CTQ) is an order that ships without rework, so the CTQ points at the metric chosen later.
The cost figure is modest. At the same volume, the goal removes about 397 reworked orders per six months, which is about $7,100 of labor. That is roughly $14,000 per year. The business case therefore cannot rest on labor alone. It also rests on the 1.5 days of added delivery time and on the complaints that delay causes. A reviewer will ask about this, so the charter should say it.
2. Problem statement
The problem statement gives the gap, size, location, period, and impact. It names no cause and no fix.
From January to June 2026, 6.2% of customer orders entered in the Dayton service center (770 of 12,400) contained at least one data entry error that required rework before shipment. Each reworked order adds an average of 1.5 days to delivery and about $18 in labor cost.You can check the arithmetic: 770 / 12,400 = 6.2%. The statement does not say "because representatives are undertrained" or "so we need automation." Those are hypotheses for the Analyze phase.
3. Primary metric and baseline
The metric is the order entry error rate. Its operational definition is orders with at least one data entry error divided by total orders entered. "At least one" matters. An order with three errors counts once, so the metric is the share of defective orders, not errors per order. The baseline is 6.2%, and the data source is the order management system rework log.
4. Goal statement
Goal: Reduce the order entry error rate (orders with at least one data entry error / total orders entered) at the Dayton service center from 6.2% to 3.0% or lower by December 18, 2026, and sustain it for 8 consecutive weeks.The goal names the metric with its definition, the baseline, the target, the location, and the deadline. It is specific, measurable, and time-bound. Whether it is achievable is a judgment the sponsor makes. A cut of about half is ambitious but plausible for an entry-error process with no current controls.
5. Scope
Scope lists the process start and end and what is in and out.
- Start: a customer order is received by a service representative.
- End: the order is released to the warehouse.
- In scope: phone and email orders entered at Dayton.
- Out of scope: web orders, warehouse picking errors, and changes to the software vendor contract.
Each exclusion has a reason. Web orders use a different entry path with no human typing. Picking errors happen after the end point. The vendor contract is a decision above the project's authority. The last exclusion also guards against a premature solution.
6. Team, milestones, risks
The sponsor is the Director of Customer Operations, who owns the budget and removes barriers. The project lead is a Green Belt. Members are a service representative, an order management analyst, and a finance partner. The finance partner validates the $18 figure. The representative brings knowledge of how entry really happens.
Milestones follow DMAIC phases. Define ends July 17, Measure August 14, Analyze September 11, Improve October 30, and Control December 18. The November peak is a risk to the pilot. Rework log accuracy is an assumption. No budget for new licenses is a constraint.
The complete charter
project_charter:
title: Reduce order entry errors at the Dayton service center
business_case: >
Rework from order entry errors costs about $18 per order and delays
delivery, which is the top driver of customer complaints.
problem_statement: >
From January to June 2026, 6.2% of orders (770 of 12,400) had at least
one data entry error that required rework before shipment.
primary_metric:
name: order entry error rate
definition: orders with at least one data entry error / total orders entered
baseline: 6.2%
data_source: order management system rework log
goal_statement: >
Reduce the order entry error rate from 6.2% to 3.0% or lower by
2026-12-18 and sustain it for 8 consecutive weeks.
scope:
process_start: customer order received by a service representative
process_end: order released to the warehouse
in_scope:
- phone and email orders entered at the Dayton service center
out_of_scope:
- web orders
- warehouse picking errors
- changes to the order management software vendor contract
team:
sponsor: Director of Customer Operations
project_lead: Green Belt, Customer Operations
members: [service representative, order management analyst, finance partner]
milestones:
define: 2026-07-17
measure: 2026-08-14
analyze: 2026-09-11
improve: 2026-10-30
control: 2026-12-18
risks_assumptions_constraints:
- assumption: rework log is complete and accurate
- risk: seasonal order peak in November may strain the pilot
- constraint: no budget for new software licensesReview the draft like a sponsor
A sponsor reads the charter looking for contradictions. Four checks apply to this one.
- Does the problem statement hide a cause or fix? No. It contains only measurements.
- Does the metric match the problem? Yes. The same definition appears in the problem, the metric, and the goal.
- Do the scope boundaries match the data? The baseline counts phone and email orders at Dayton. The scope covers the same population, so the baseline and the future measurements are comparable. If the 12,400 included web orders, the baseline would have to be recalculated.
- Do the dates agree with the goal? Here the draft has a problem.
The goal asks for 8 consecutive weeks at or below 3.0%. Counting back 8 weeks from December 18 gives October 23. The Improve milestone is October 30, so the solution cannot be in place early enough for the sustain period to finish by December 18.
The charter needs one of two fixes. The first is to move the dates earlier, which is hard with a November peak. The second is to reword the goal so the deadline applies to reaching the target and the sustain period runs afterward. This chapter uses the second. The target must first be reached by December 18, and the Control phase monitors the weekly rate through February 12, 2027, which is 8 weeks later. The charter records that date as an extra field.
sustain_monitoring_end: 2027-02-12Common mistakes this charter avoids
| Draft habit | What this charter does instead |
|---|---|
| "Needs to be automated" in the problem | States only size, place, period, and impact |
| "Improve quality" as the goal | Gives a metric, baseline, target, and date |
| Scope of "the whole order process" | Names start, end, inclusions, and exclusions |
| Baseline without a source | Names the rework log and the period |
| Risks left blank | Lists an assumption, a risk, and a constraint |
Exercises
Exercise
The Dayton team discovers during Measure that 15% of the 770 rework cases were caused by the warehouse mislabeling shipments, not by entry errors. Which charter parts must be revisited, and why?
Show answer
The baseline and the metric definition. If those cases are not data entry errors, the 6.2% overstates the entry error rate, and the problem statement's 770 count is wrong. The goal's starting point changes too, so the target of 3.0% needs a sponsor conversation. The scope already excludes warehouse picking errors, so those cases should come out of the baseline rather than the scope being widened.
Exercise
A reviewer proposes changing the goal to "eliminate all order entry errors by December 18." Give two reasons to push back, using the charter's own numbers or structure.
Show answer
First, a target of zero is rarely achievable for a manual entry process and gives no basis for judging success short of perfection, so it fails the "achievable" test of SMART. Second, the goal needs a sustain period, and the timeline already conflicts with 8 weeks of sustained results by December 18, so a stricter target makes that conflict worse. A target such as 3.0% or lower, set with the sponsor, can be tested against the baseline of 6.2%.
Exercise
Write one sentence that adds a measurable constraint to the "risks, assumptions, and constraints" section for the November peak risk. It should be a risk statement with a trigger, not just a worry.
Show answer
Example: "Risk: if weekly order volume in November exceeds 20% above the June weekly average, the pilot team may be unable to apply the new entry checks; the project lead will pause the pilot and report to the sponsor within one business day." Any answer is correct if it names a measurable trigger, an owner, and an action.