Sub topic 11
Recording risks, assumptions, and constraints
This chapter assumes you know the five DMAIC phases and can read a charter that already has a problem statement, a goal, a scope, a team, and milestones. It covers the last working section of the charter: the record of what could go wrong, what you are taking for granted, and what limits you cannot change.
The running example is the Dayton order entry project. The goal is to cut the order entry error rate from 6.2% to 3.0% or lower by 2026-12-18.
Why the charter needs this section
A charter is a plan made before the data is in. You will be wrong about some things. The risks, assumptions, and constraints section keeps those unknowns visible so the sponsor can react early and so you are not blamed later for conditions you flagged at the start.
The section does three jobs:
- It tells the sponsor which conditions the plan depends on.
- It gives the team a list to check at every phase gate.
- It separates things the project can influence from things it cannot.
The three terms are often mixed up, so keep them apart.
| Item | What it is | Certain? | Can the team change it? | Example from the Dayton project |
|---|---|---|---|---|
| Risk | An uncertain event that, if it happens, hurts the project | No, it has a likelihood | Partly. You can reduce likelihood or impact | The November order peak strains the pilot |
| Assumption | A condition treated as true without proof | Believed, not verified | Not directly. You verify it | The rework log is complete and accurate |
| Constraint | A fixed limit on the project | Yes | No | No budget for new software licenses |
Constraints
A constraint is a limit that was set before the project began. It is not up for negotiation inside the project. Common types:
- Budget: money, licenses, or purchased equipment.
- Time: a fixed end date tied to a business event.
- Resources: people available part time, or only on certain days.
- Technical: a system that cannot be changed.
- Policy or regulatory: rules the process must obey.
Write constraints as plain facts. "No budget for new software licenses" is a constraint. "We would like to avoid new software" is a preference and does not belong here.
Constraints interact with scope. The Dayton charter lists "changes to the order management software vendor contract" as out of scope, and the license constraint explains why. The two entries should never contradict each other. If a solution would need new software, the team knows early that it is not available.
Assumptions
An assumption is something you rely on without having proven it. Every project has them. The danger is not having assumptions. The danger is leaving them unstated, because an unstated assumption cannot be checked.
Write each assumption so it can be tested. Compare these:
- Weak: "The data is good."
- Better: "The rework log in the order management system records every order that was corrected before shipment."
The better version names the thing and states the claim. It also tells you how to check it. Someone can compare a sample of paper order forms against the log and count the misses.
Assign each assumption a verification step and an owner. In the Dayton project, the Measure phase is the natural place to test the rework log assumption. If the log misses 20% of corrected orders, the baseline of 6.2% is too low. The goal must then be revisited with the sponsor.
An assumption that is verified becomes a fact and can be removed. An assumption that proves false becomes either a risk that has happened (an issue) or a reason to change the charter.
Risks
A risk is an event that might happen. It has a likelihood and an impact. A useful risk entry states the event and its effect on the project, not just a topic.
- Weak: "Seasonality."
- Better: "The seasonal order peak in November raises order volume and may strain the pilot, which could delay the Improve phase results."
Scoring and responding
Keep scoring simple. Rate likelihood and impact as low, medium, or high, then decide what to do about the risks that rate high on either one. There are four standard responses:
- Avoid: change the plan so the risk cannot occur.
- Reduce: lower the likelihood or the impact.
- Transfer: move the consequence to someone better able to carry it.
- Accept: do nothing now and watch for it.
For the November peak, a reasonable response is to reduce. The team runs the pilot with one shift in October, before the peak, and schedules the full rollout review after the peak settles. The charter entry records the risk, the response, and an owner.
A fuller risk entry
A charter does not need a heavy risk register. A short table is enough, as long as every row has a response and an owner.
| Risk | Likelihood | Impact | Response | Owner |
|---|---|---|---|---|
| November peak strains the pilot | High | Medium | Reduce: pilot in October, review after the peak | Project lead |
| Service representatives are pulled to cover absences and miss team sessions | Medium | Medium | Reduce: schedule sessions in the low-volume morning window | Sponsor |
| Rework log proves incomplete | Medium | High | Reduce: audit a sample in Measure, adjust the baseline | Order management analyst |
Notice that the third row is a risk created by an assumption. This link is common. Each assumption you cannot verify now implies a risk that it is false.
How the three relate
Think of the three as a flow. Constraints set the boundary of what is possible. Assumptions describe what you are betting on inside that boundary. Risks describe what happens if a bet fails or if outside events intrude.
Recording the section in the charter
Here is the section as it appears in the Dayton charter, expanded slightly to carry verification and owners.
risks_assumptions_constraints:
constraints:
- statement: no budget for new software licenses
source: Customer Operations fiscal plan
assumptions:
- statement: rework log records every order corrected before shipment
verify_by: compare 100 sampled paper forms against the log
verify_in_phase: measure
owner: order management analyst
risks:
- event: seasonal order peak in November strains the pilot
likelihood: high
impact: medium
response: reduce
action: run pilot in October; review results after the peak
owner: project leadCommon mistakes
- Listing constraints as risks. A fixed budget limit is certain, so it is not a risk. Putting it in the risk table makes the team try to "mitigate" something they cannot change.
- Listing risks with no response. A risk with no action and no owner is only a worry written down.
- Writing generic risks. "Resistance to change" or "lack of resources" could appear in any charter. Tie each risk to a named event in your process.
- Hiding assumptions. If the goal depends on the rework log being accurate and the charter never says so, a bad log looks like a project failure.
- Never revisiting the list. The section is a living record. Review it at each phase gate and update it.
- Using the section to protect against the goal. Padding the list with excuses so the project cannot fail makes the sponsor distrust the charter.
Reviewing the section with the sponsor
During charter review, take the sponsor through this section last and ask three things:
- Are any listed constraints actually negotiable? If so, the sponsor can remove them and widen the options.
- Who owns each high-rated risk? Owners outside the team need the sponsor to assign them.
- Which assumption, if false, would make the sponsor want to change the goal or the date?
Record the answers, then carry the list forward to the first phase gate.
Exercise
A Green Belt writes these three charter lines: (a) "The warehouse will not change its release schedule." (b) "The rework log is accurate." (c) "Service representatives may be reassigned to cover a staffing shortage in October." Classify each as a risk, an assumption, or a constraint. Then say what you would add to each so it is useful.
Show answer
(a) is a constraint if the schedule is fixed by a decision outside the project. Add the source of the limit, such as the warehouse operations plan. If the schedule is only unlikely to change, it is an assumption. (b) is an assumption. Add a way to check it, such as comparing a sample of 100 paper forms to the log in the Measure phase, and an owner. (c) is a risk. Add likelihood, impact, a response such as scheduling sessions in the low-volume window or naming a backup team member, and an owner.
Exercise
In Measure, an audit shows the rework log misses about 25% of corrected orders. Which section entry has failed, what does this do to the baseline and goal, and what is the right next step?
Show answer
The assumption that the rework log is complete has failed, so the risk tied to it has occurred. The true error rate is higher than 6.2%, so the baseline is understated and a 3.0% goal may be easier or harder than intended depending on the corrected rate. The next step is to recalculate the baseline from the audited data, tell the sponsor, and agree on whether to adjust the goal or date. Update the charter and record the change.