Sub topic 2
What a project charter is and what it contains
This chapter assumes you know the five DMAIC phases (Define, Measure, Analyze, Improve, Control). It also assumes you know what a process, a defect, and a metric are. Later chapters cover the problem statement, the goal, and the scope in depth. Here you learn what the charter is, why it exists, and which parts it holds.
What a charter is
A project charter is a short document, usually one or two pages, that defines a Lean Six Sigma project before the team starts the detailed work. You write it in the Define phase. The project lead drafts it, and the sponsor approves it.
The charter does three jobs:
- It is an agreement. The sponsor, who controls resources, and the project lead agree on what the project will do and what it will not do.
- It is a reference. When the team is tempted to chase a new idea or a new data set, the charter shows whether that work belongs in the project.
- It is a record. After the project, the charter shows what the team set out to do, so you can compare it with what happened.
A charter is not a project plan. It does not list every task, and it does not describe the solution. In DMAIC, the team finds causes in Analyze and chooses solutions in Improve. If the charter already names a solution, the project becomes a delivery exercise and skips the analysis that DMAIC exists to provide.
Where the charter sits in the flow of work
The charter is the main output of the first half of Define. It uses the business case and the customer's requirements as inputs, and it feeds the Measure phase, where the team confirms the baseline and checks the measurement system.
The loop between the draft and the sponsor review is normal. Most charters go through at least one revision. The later chapters on charter review and common mistakes return to this loop.
The elements of a charter
Charter templates differ between organizations, but they hold the same core elements. The table lists them, what each one answers, and where this tutorial covers it.
| Element | Question it answers | Covered in |
|---|---|---|
| Business case | Why is this project worth doing now? | Making the business case |
| Problem statement | What is wrong, how big is it, where, and since when? | Writing the problem statement |
| Primary metric and baseline | How do we measure the problem, and what is the current value? | Choosing the primary metric |
| Goal statement | What value do we want, and by when? | Writing a SMART goal statement |
| Scope | Where does the process start and stop, and what is excluded? | Setting scope |
| Team and roles | Who sponsors, leads, and does the work? | Naming the sponsor, project lead, and team |
| Milestones | When does each DMAIC phase finish? | Planning the timeline |
| Risks, assumptions, constraints | What could derail the project, and what are we taking for granted? | Recording risks, assumptions, and constraints |
Some templates add the customer requirement (the critical-to-quality requirement, or CTQ) as its own line. Others fold it into the business case or the problem statement. Either way, the charter should show a visible link from customer need to measured problem.
How the elements depend on each other
The elements are not independent boxes to fill in any order. Each one constrains the next, and writing them in a sensible order saves rework.
- The business case and the customer need justify the project.
- The problem statement describes the gap using data.
- The primary metric gives the problem a number. The baseline is the current value of that metric.
- The goal statement sets a target for that same metric.
- The scope limits the project to a process you can actually change within the timeline.
- The team, milestones, and risks follow from the size of the scope and the goal.
A common consistency check is to read the charter and confirm that the metric named in the problem statement is the same metric, with the same definition, in the goal statement. If the problem statement says "orders with errors" and the goal says "errors per order line," the project has two different measures, and the team will argue about success at the end.
One example, shown in full
This tutorial uses one fictional example throughout: reducing order entry errors at the Dayton service center. The YAML below shows how the elements sit together in one document. You do not need to run it. It is a sketch of a charter's structure, and later chapters explain each part.
project_charter:
title: Reduce order entry errors at the Dayton service center
business_case: >
Rework from order entry errors costs about $18 per order and delays
delivery, which is the top driver of customer complaints.
problem_statement: >
From January to June 2026, 6.2% of orders (770 of 12,400) had at least
one data entry error that required rework before shipment.
primary_metric:
name: order entry error rate
definition: orders with at least one data entry error / total orders entered
baseline: 6.2%
data_source: order management system rework log
goal_statement: >
Reduce the order entry error rate from 6.2% to 3.0% or lower by
2026-12-18 and sustain it for 8 consecutive weeks.
scope:
process_start: customer order received by a service representative
process_end: order released to the warehouse
in_scope:
- phone and email orders entered at the Dayton service center
out_of_scope:
- web orders
- warehouse picking errors
- changes to the order management software vendor contract
team:
sponsor: Director of Customer Operations
project_lead: Green Belt, Customer Operations
members: [service representative, order management analyst, finance partner]
milestones:
define: 2026-07-17
measure: 2026-08-14
analyze: 2026-09-11
improve: 2026-10-30
control: 2026-12-18
risks_assumptions_constraints:
- assumption: rework log is complete and accurate
- risk: seasonal order peak in November may strain the pilot
- constraint: no budget for new software licensesNotice four things about this sketch:
- The metric has a definition (a numerator and a denominator), a baseline, and a data source. Without all three, two people can compute different numbers from the same process.
- The goal uses the same metric name and the same baseline as the problem statement.
- The scope names a start point and an end point, and it lists exclusions explicitly.
- Nothing in the charter names a cause or a fix. It does not say "automate order entry" or "retrain staff."
What the charter should not contain
Knowing what to leave out matters as much as knowing what to include.
- A solution. "Implement barcode scanning" belongs in Improve, after the data supports it.
- A cause. "Errors happen because staff are careless" is a belief to test in Analyze, not a fact to state in Define.
- Blame. The problem statement describes a process result, not a person or team.
- Unmeasured claims. "Customers are unhappy" needs a number, such as a complaint count or a survey score, before it belongs in the charter.
- A full task list. Detailed tasks go in a project plan. The charter holds phase-level milestones only.
A living document, with controlled changes
The charter is signed early, but the team learns a lot during Measure. For example, the baseline may turn out to be wrong, or the rework log may be incomplete. The charter can change, but only through agreement with the sponsor. A quiet change to the goal or scope, made by the team alone, is called scope creep when the work grows, and it is a common reason projects miss their dates. When you change something, record what changed, why, and who approved it.
Quality checks for a draft charter
Before you take a draft to the sponsor, run through this list:
- Does the business case say why the project matters in terms the sponsor cares about, such as cost, time, or customer retention?
- Does the problem statement include size, location, time period, and impact?
- Is the primary metric defined well enough that a stranger could calculate it from the data source?
- Does the goal use the same metric, the baseline, a target, and a deadline?
- Does the scope name start and stop points and list items that are out of scope?
- Are the sponsor and project lead named as people or roles, not as "management"?
- Do the milestones cover all five phases, and do they end on the goal deadline?
- Is any solution or cause hidden in a sentence anywhere in the document?
If the answer to the last question is yes, rewrite that sentence as a description of the gap or the process.
Exercise
A draft charter has this problem statement: "Our order entry process is inefficient and needs to be automated." Name two things wrong with it as a charter element, and state what the problem statement should contain instead.
Show answer
First, it embeds a solution ("needs to be automated"), which pre-empts the Analyze and Improve phases. Second, it has no measure: "inefficient" gives no size, location, time period, or impact. A better problem statement gives the data, for example: "From January to June 2026, 6.2% of customer orders entered in the Dayton service center (770 of 12,400) contained at least one data entry error that required rework before shipment. Each reworked order adds an average of 1.5 days to delivery and about $18 in labor cost." It describes the gap without naming a cause or a fix.
Exercise
The problem statement in a charter uses "orders with at least one data entry error / total orders," but the goal statement says "reduce errors per order line by 50%." What is the risk, and how do you fix it?
Show answer
The two statements use different metrics, so the team has no single baseline and could claim success or failure depending on which number it computes. Fix it by choosing one primary metric with one operational definition (numerator, denominator, data source) and using that same metric, with its baseline, in both the problem statement and the goal statement.