Sub topic 7
Sharing Wages by Work Done
This chapter assumes you can add fractions, use the LCM method to pick a total amount of work, and read efficiency ratios. If any of those feel shaky, revisit the earlier chapters on the work-rate relation, the LCM method and efficiency first.
The principle: pay follows work, not presence
When several people finish a job together and share one payment, the fair split is in proportion to the work each person did. It is not split by headcount, and it is not split by the days each person stayed on site.
Work done by a person is:
work done = rate × time worked
So the wage ratio is the ratio of (rate × time) for each person. Three cases come up again and again:
- Everyone works for the same time. The wages split in the ratio of their rates, which is the ratio of their efficiencies.
- Everyone has the same rate. The wages split in the ratio of the time each person worked.
- Rates and times both differ. Compute each person's units of work and split in that ratio.
The last case is the general one. The first two are shortcuts.
Case 1: Same time, different rates
A can finish a job in 10 days and B can finish it in 15 days. They work together to complete it and are paid a total of 6000. How much does each get?
Take the total work as LCM(10, 15) = 30 units.
- A's rate is 30 / 10 = 3 units per day.
- B's rate is 30 / 15 = 2 units per day.
They work together for the same number of days, so the wage ratio equals the rate ratio, 3 : 2.
- A gets 3/5 of 6000 = 3600.
- B gets 2/5 of 6000 = 2400.
A useful observation: the wage ratio is the inverse of the ratio of the times taken alone. Times are 10 : 15 = 2 : 3, so wages are 3 : 2. This is the efficiency-time inverse relation from the efficiency chapter, applied to money.
Case 2: Different times worked
Now suppose A leaves after 2 days and B finishes the job alone. The total payment is still 6000, with the same rates of 3 and 2 units per day and a total of 30 units.
- In 2 days, A does 3 × 2 = 6 units.
- The remaining work is 30 − 6 = 24 units.
- B does 24 units at 2 units per day, which takes 12 days.
- B's work is 24 units. A's work is 6 units.
The wage ratio is 6 : 24 = 1 : 4.
- A gets 1/5 of 6000 = 1200.
- B gets 4/5 of 6000 = 4800.
Notice that the wage shares are simply each person's units of work divided by the total units. Because every unit of work is worth the same amount, the total of 30 units is worth 6000, so one unit is worth 200.
The per-unit method
Pricing a single unit of work is often the cleanest approach, especially when the question asks for one person's pay or changes the total payment.
- Choose the total work with the LCM method.
- Divide the total payment by the total units to get the pay per unit.
- Multiply by the units each person completed.
Here is the idea in code, using exact fractions so no rounding creeps in.
from fractions import Fraction
from math import lcm
def split_wages(total_pay, days_alone, days_worked):
"""days_alone: days each person needs to do the whole job alone.
days_worked: days each person actually worked on the job."""
total_work = lcm(*days_alone)
rates = [total_work // d for d in days_alone]
work = [r * t for r, t in zip(rates, days_worked)]
done = sum(work)
if done != total_work:
raise ValueError(f"work done {done} does not equal total {total_work}")
return [Fraction(total_pay) * w / done for w in work]
# Case 1: both work 6 days
print(split_wages(6000, [10, 15], [6, 6])) # [Fraction(3600, 1), Fraction(2400, 1)]
# Case 2: A works 2 days, B works 12 days
print(split_wages(6000, [10, 15], [2, 12])) # [Fraction(1200, 1), Fraction(4800, 1)]The function checks that the work done equals the total. If it does not, the stated days are inconsistent with the job, and the split would be meaningless. This is a good habit in exams too: confirm that the units add up to the total before you divide the money.
Case 3: Three workers, each with a different history
A, B and C can finish a job alone in 12, 18 and 36 days. All three start. A leaves 4 days before the job is finished, and B leaves 6 days before it is finished. C stays to the end. The total payment is 9000. How much does each get?
Let the job last T days in total.
Take the total work as LCM(12, 18, 36) = 36 units.
- A's rate is 36 / 12 = 3 units per day.
- B's rate is 36 / 18 = 2 units per day.
- C's rate is 36 / 36 = 1 unit per day.
Working times:
- A works T − 4 days.
- B works T − 6 days.
- C works T days.
Total work equals 36:
3(T − 4) + 2(T − 6) + 1(T) = 36
3T − 12 + 2T − 12 + T = 36
6T = 60
T = 10 days.
Work done by each person:
- A: 3 × 6 = 18 units.
- B: 2 × 4 = 8 units.
- C: 1 × 10 = 10 units.
The total is 18 + 8 + 10 = 36, which matches. The ratio is 18 : 8 : 10 = 9 : 4 : 5, with a sum of 18 parts. One part is 9000 / 18 = 500.
- A gets 9 × 500 = 4500.
- B gets 4 × 500 = 2000.
- C gets 5 × 500 = 2500.
The key move is writing each person's days worked in terms of one unknown, then forcing the work total to equal the LCM.
Wages when the job is done in parts
Some problems pay by the part of the job, not for the whole. For example, a contractor is paid 8000 for a job. A does half of it alone and B does the other half alone. Because each did half of the work, the wages are equal, even if A is faster. Here the work is fixed, so time does not matter. Pay depends only on the amount of work.
This is the same principle as before. The only thing that decides the split is work done. Speed changes how long it takes, not how much work counts.
Wages with helpers who are paid differently
Occasionally a problem states a daily wage for each type of worker, such as men and women, and asks for the total cost of a job. In that case the wage is not shared out from a fixed pool. You compute cost directly:
cost = (number of workers × daily wage) × days
Suppose 5 men and 4 women can finish a job in 6 days. A man earns 300 a day and a woman earns 200 a day. The cost of the job is:
(5 × 300 + 4 × 200) × 6 = (1500 + 800) × 6 = 13,800
Do not confuse this with the shared-pool problems. Check whether the question gives a total payment to divide, or gives rates of pay to multiply.
Common errors
| Error | Why it is wrong | Fix |
|---|---|---|
| Splitting wages in the ratio of times taken alone (10 : 15) | A faster worker does more work in the same time, so should earn more. This gives the wrong direction. | Invert the times, or use rates |
| Splitting by days present alone when rates differ | Ignores efficiency | Use rate × days |
| Splitting equally because "they finished together" | Finishing together says nothing about contribution | Compute units of work |
| Forgetting a worker who left early still earns for the days worked | Their work was real work | Include their units |
| Not checking that units sum to the total | Hides arithmetic slips and impossible data | Add the units and compare with the LCM |
Sanity checks
- The shares must add up to the total payment.
- If everyone works the same time, the faster worker gets more.
- If rates are equal, the person who worked more days gets more.
- Any person who did none of the work gets nothing, even if they were hired for the whole job.
- If the ratio simplifies to small whole numbers, the setup is usually right. Awkward fractions often signal a mistake in days worked.
Exercises
Exercise
A, B and C can finish a job alone in 20, 30 and 60 days. They work together and are paid 12000 for the job. How should the payment be divided?
Show answer
Take the total work as LCM(20, 30, 60) = 60 units. The rates are 3, 2 and 1 units per day. They all work the same number of days, so the wage ratio equals the rate ratio, 3 : 2 : 1, with 6 parts. One part is 12000 / 6 = 2000. A gets 6000, B gets 4000 and C gets 2000.
Exercise
A can do a job in 12 days and B can do it in 24 days. They start together, but A leaves after 4 days and B finishes the rest alone. The total payment is 9000. How much does each person get?
Show answer
Take the total work as 24 units. A's rate is 2 units per day and B's rate is 1 unit per day. In 4 days, A does 8 units and B does 4 units, so 12 units are done. The remaining 12 units take B another 12 days, so B does 4 + 12 = 16 units in total. The work ratio is A : B = 8 : 16 = 1 : 2. A gets 3000 and B gets 6000.
Exercise
P and Q can do a job in 15 and 10 days. With R's help they finish in 4 days, and they are paid 3000 in total. What is R's share?
Show answer
Take the total work as 30 units. P does 2 units per day and Q does 3 units per day, so together they do 5 units per day. In 4 days the job is done, so the three together do 30/4 = 7.5 units per day, and R does 7.5 − 5 = 2.5 units per day. All three work 4 days, so the wage ratio equals the rate ratio, 2 : 3 : 2.5, which is 4 : 6 : 5 with 15 parts. One part is 3000 / 15 = 200. R gets 5 × 200 = 1000.