Men, days and hours: the M1D1H1/W1 = M2D2H2/W2 relation
This chapter assumes you are comfortable with direct and inverse proportion, with fractions and ratios, and with the single relation work = rate × time from the earlier chapters. Here the "time" splits into two parts, days and hours per day, and the "rate" becomes the combined output of a crew of workers. One formula then covers a whole family of problems that CAT sets as "men, days, hours" questions.
Where the formula comes from
Suppose one worker, in one hour, does a fixed amount of work. Call that amount the worker's efficiency, e. A crew of M workers, each putting in H hours a day for D days, does this much work:
W = e × M × D × H
The product M × D × H is the total effort in man-hours (one man-hour is one worker working for one hour). If the workers in both situations have the same efficiency, then e is the same on both sides:
W1 / (M1 × D1 × H1) = W2 / (M2 × D2 × H2)
Inverting both sides gives the form used in exams:
M1 × D1 × H1 / W1 = M2 × D2 × H2 / W2
Each side is the number of man-hours needed to finish one unit of work. The two situations must be equal in that figure. This is the idea to remember. The formula is just a statement that the cost of one unit of work does not change.
How each quantity behaves
The formula is a chain of direct and inverse proportions, so you can also solve problems by reasoning one quantity at a time.
| Quantity | Relation to work done | Relation to the other effort quantities |
|---|---|---|
| Men (M) | Direct | Inverse with days and with hours per day |
| Days (D) | Direct | Inverse with men and with hours per day |
| Hours per day (H) | Direct | Inverse with men and with days |
| Work (W) | n/a | Direct with M, D and H together |
The rule is simple. Work goes in the denominator on the same side as the fixed effort, and everything that is "more effort" goes in the numerator. Doubling the men, with days and hours unchanged, doubles the work done in the same time. Doubling the work, with men and hours unchanged, doubles the days.
A procedure that works every time
Step 2 is the useful one. Once you have man-hours per unit of work, every later question is a single division or multiplication.
Worked example 1: the unknown is days
15 men working 8 hours a day finish a job in 12 days. How many days will 20 men working 6 hours a day need for the same job?
The work is the same on both sides (W1 = W2), so it cancels:
15 × 12 × 8 = 20 × D × 6
1440 = 120 × D, so D = 12 days.
A direction check agrees. There are more men (more effort) but fewer hours per day (less effort). The two changes happen to cancel exactly: 20 × 6 = 120 man-hours per day, against 15 × 8 = 120 before.
Worked example 2: different work amounts
10 men working 6 hours a day dig 360 m of trench in 12 days. How many men are needed to dig 540 m in 9 days, working 8 hours a day?
Man-hours per metre are 10 × 12 × 6 / 360 = 2. The new job needs 540 × 2 = 1080 man-hours. Each man supplies 9 × 8 = 72 man-hours, so you need 1080 / 72 = 15 men.
You can check both examples with exact fractions in Python.
from fractions import Fraction
def man_hours_per_unit(men, days, hours, work):
"""Man-hours needed for one unit of work in the known scenario."""
return Fraction(men * days * hours, work)
# Example 1: same job, unknown days
k = man_hours_per_unit(15, 12, 8, 1)
days = k / (20 * 6)
print(days) # 12
# Example 2: different work, unknown men
k = man_hours_per_unit(10, 12, 6, 360)
men = k * 540 / (9 * 8)
print(men) # 15Using Fraction keeps the arithmetic exact. If the result is not a whole number, the output shows it as a fraction such as 31/2, which you then have to interpret (see the edge cases below).
When workers have different efficiencies
The formula assumes every worker has the same efficiency. If the crew mixes types of worker, such as men and women, convert each type into a common unit first. This is the same idea as the efficiency ratios in the earlier chapter.
Example: 6 men and 3 women finish a job in 12 days. Two men do as much work as three women. How long will 8 men and 4 women take?
If 2 men equal 3 women, then one man is 3 units per day and one woman is 2 units per day (the efficiencies are in the ratio 3 : 2). The first crew produces 6 × 3 + 3 × 2 = 24 units a day, so the job is 24 × 12 = 288 units. The second crew produces 8 × 3 + 4 × 2 = 32 units a day, so it needs 288 / 32 = 9 days.
Note the direction of the conversion. "2 men = 3 women" means a man is the stronger worker, so a man gets the larger number. Writing it the wrong way round is the most frequent mistake in this problem type.
Crew changes and schedule slips
Many exam questions change the crew partway through. The clean method is to count the total work in man-days (or man-hours), subtract what is done, and divide what remains by the new effort per day.
Example: 30 men are hired to finish a job in 40 days. After 20 days only 40% of the work is done. How many extra men are needed to finish on the original date? Hours per day stay the same.
- Total work is 30 × 40 = 1200 man-days.
- Work done is 40% of 1200 = 480 man-days.
- Work left is 1200 − 480 = 720 man-days, to be done in the remaining 20 days.
- Men needed are 720 / 20 = 36, so 6 extra men are required.
Notice that the 30 men were doing only 480 / 20 = 24 men's worth of work in the first 20 days. They were behind the plan. Whether the cause was low efficiency or a delay, the method does not change. You can handle the case where workers leave in the same way: subtract the work done, then divide what is left by the smaller daily effort.
Edge cases and traps
- Whole numbers of people. The formula can return 6.2 men. You cannot hire 0.2 of a man, so round up if the deadline must be met. If the question asks for days, a fractional answer such as 7.5 days is acceptable unless the problem says work happens in whole days.
- Day versus hour mismatch. If the first scenario gives hours per day and the second gives total hours, convert so both are in the same unit before you substitute.
- Different working conditions. Questions that mention "men working 8 hours" in one case and "5 men working double time" in another rely on you to translate the phrase into a multiplier on hours or efficiency.
- Same work on both sides. When the job is the same, W1 = W2 and you should cancel it. Do not invent numbers for it.
- Equal efficiency is an assumption. The formula is wrong if one scenario involves tired, new, or different workers and the problem does not tell you to treat them the same. Use the problem's wording as the guide.
Speed tips for the exam
Reduce the relation to one line: (M × D × H) ÷ W is constant. Cancel common factors before multiplying. In example 1 you can see at once that 15 × 8 = 120 and 20 × 6 = 120, so the days cannot change. For a mixed crew, always convert to a base unit first, then treat the problem as plain man-days.
Exercise
18 men working 7 hours a day build 630 m of road in 15 days. How many days will 14 men working 9 hours a day need to build 840 m of the same road?
Show answer
Man-hours per metre = (18 × 15 × 7) / 630 = 1890 / 630 = 3. The new job needs 840 × 3 = 2520 man-hours. The crew supplies 14 × 9 = 126 man-hours per day, so it takes 2520 / 126 = 20 days.
Exercise
24 men are hired to finish a job in 30 days, working the same hours each day. After 12 days only one quarter of the job is done. How many extra men are needed to finish on the original date?
Show answer
Total work = 24 × 30 = 720 man-days. Work left is three quarters, which is 540 man-days. The remaining time is 30 − 12 = 18 days, so 540 / 18 = 30 men are needed. That is 30 − 24 = 6 extra men.