Sub topic 9
Principle 4: Let the Customer Pull
This chapter assumes you know the first three principles (specify value, identify the value stream, make work flow). It also assumes you are comfortable with Little's Law as covered earlier: average cycle time = WIP / throughput. You do not need any kanban knowledge. The next chapter covers kanban and WIP limits in detail, so this chapter stays on the principle itself.
What pull means
Pull means that nothing is made, started, or handed downstream until the next step or the customer asks for it. Womack and Jones put it this way: the customer pulls the product from you, instead of you pushing products onto the customer.
Pull is the fourth principle because it depends on the three before it:
- Value tells you what the customer actually wants, so you know what is worth pulling.
- The value stream shows which steps must respond to a request.
- Flow makes the work move fast enough that a request can be answered in days or hours, not months.
Without flow, pull fails. If your lead time is six weeks, customers cannot pull. They can only wait, so you end up guessing what they will want and building it ahead of time.
Push versus pull
In a push system, work is started according to a schedule or forecast. Each step finishes its work and sends it downstream, whether or not the next step is ready. In a pull system, a step starts work only when a downstream step signals that it has capacity or need.
| Aspect | Push | Pull |
|---|---|---|
| Trigger to start work | Schedule, forecast, or available capacity | Signal from the downstream step or customer |
| Direction of the signal | Downstream (with the work) | Upstream (against the work) |
| Typical result | Queues between steps, overproduction | Small, bounded queues |
| Response to a change in demand | Slow; plans must be revised | Fast; the signal changes immediately |
| Main risk | Building the wrong thing | Starving a step if the signal loop is too slow |
Why push builds up waste
Push has two basic problems.
First, forecasts are wrong. Any plan that starts work before an order exists is a bet. A lost bet produces finished goods nobody wants, which is overproduction. Lean counts overproduction as the worst of the classic wastes because it causes the others: inventory, waiting, extra transport, and extra handling.
Second, steps are never perfectly balanced. If step A can do 5 items a day and step B can do 3, push lets the queue between them grow by 2 items every day. Nobody decides this. It follows from the rule "A keeps working." Queues are where waiting time lives, so a growing queue is growing lead time. Chapter 3's flow-efficiency example showed 55.5 of 59.5 hours spent waiting. Push systems are where numbers like that come from.
Pull attacks the cause. It removes the permission to start work "because we can."
A worked simulation
The code below models two steps in a line. Step A can make 5 items a day and step B can process 3. In the push case A always works at full speed. In the pull case A may only add items while the queue in front of B is below a limit of 6. This is the same idea as the WIP-limit rule from earlier: pull new work only when there is free capacity.
def simulate(days, rate_a, rate_b, pull_limit=None):
"""Return (queue at end, items completed) for a two-step line."""
queue = 0
done = 0
for _ in range(days):
made = rate_a
if pull_limit is not None:
# Step A may only fill the free space in front of step B.
made = min(rate_a, max(0, pull_limit - queue))
queue += made
processed = min(queue, rate_b)
queue -= processed
done += processed
return queue, done
for label, limit in [("push", None), ("pull", 6)]:
queue, done = simulate(10, 5, 3, limit)
wait_days = queue / 3 # Little's Law: wait = WIP / throughput
print(f"{label}: queue={queue}, done={done}, wait={wait_days:.1f} days")
# push: queue=20, done=30, wait=6.7 days
# pull: queue=3, done=30, wait=1.0 daysBoth systems finish 30 items in 10 days, because step B is the bottleneck and sets the throughput. The difference is what happens to the rest of the work. Push puts the extra 20 items in a queue, where each new arrival waits about 6.7 days. Pull never starts them. Step A stays idle some of the time, but that idleness costs nothing, since its extra output could not have been finished sooner.
Many managers find this hard to accept. A busy-looking step A is not a sign of a healthy system. In Lean, utilization of a non-bottleneck step is not a goal.
Where pull signals come from
A pull system needs a clear signal that says "start now." Common forms:
- Customer orders. Work starts when a real order arrives (build to order). This is pure pull but needs short lead times.
- Replenishment. A small stock of finished items, often called a supermarket, is kept near the customer. When items are taken, the gap triggers a replacement. This suits products with steady demand and long or costly changeovers.
- Downstream capacity. A step asks for work when it has finished the last item. This is how WIP limits work, and the next chapter shows how kanban cards or board columns carry the signal.
Notice that the signal travels upstream. In a push system information and work move in the same direction, so the upstream step never hears whether the work was needed.
Pull in knowledge work
Pull is not only for factories. Examples:
- A support team takes the next ticket only when it has finished one, instead of having tickets assigned in bulk by a manager.
- A software team starts a new feature only when review capacity is free, instead of starting everything in the sprint plan on day one.
- A document approval chain stops accepting drafts when the reviewer has a backlog of five.
In each case the effect is the same as in the simulation: less work in progress, shorter waits, and earlier feedback. Faster feedback matters because a mistake found on the day it was made is cheaper than one found three weeks later.
What pull requires
Pull is not a switch you flip. It works only when some conditions hold.
- Reasonably short lead times. If a replenishment signal takes weeks to turn into goods, the buffer must cover weeks of demand, which is little better than a forecast.
- Small batches. A step that works in batches of 500 cannot respond to a signal for 5.
- Stable, repeatable steps. If a step fails unpredictably, downstream steps will starve. Pull exposes this quickly, which is a benefit but also a source of resistance.
- Visible signals. Everyone must see what triggers work. Hidden or informal signals turn back into push within a few weeks.
Common errors
- Calling a schedule a signal. A weekly plan that lists what each step must start is push, even if it is based on customer orders. Check whether a step can start work without any downstream step asking for it.
- Setting the limit too high. If the buffer limit is larger than the demand during the replenishment time, the limit never binds, and the system behaves as push.
- Setting the limit too low. A limit of 1 in front of a step with variable processing time starves the step whenever an item takes longer than usual. Adjust limits using measured data, not intuition.
- Pulling before flow. Introducing pull signals into a process with long changeovers and large batches produces stockouts. Fix batch size and waiting first, then add pull.
- Pushing around the system. Managers who "expedite" favourite items by bypassing the signal break the rules for everyone else, and the queue discipline collapses.
- Measuring the wrong thing. If step A is judged by its utilization, its manager has every reason to ignore the pull signal. Align the measures with flow and lead time.
Connecting back to Little's Law
Pull is the practical way to apply Little's Law. The law says average cycle time = WIP / throughput. If throughput is set by the bottleneck, the only variable you can change is WIP. A pull rule caps WIP directly, so it caps the average cycle time. In the simulation, capping the queue near 3 items against a throughput of 3 per day gave a wait of 1 day. Without the cap, the queue kept growing and so did the wait.
This also explains why pull does not reduce throughput when the bottleneck is correctly kept busy. The bottleneck always has work waiting, so it never idles, and throughput is unchanged. Everything upstream of the bottleneck can slow down without any loss.
Exercise
A two-step process has step A producing 8 items per day and step B processing 4 items per day. Under push, how many items are in the queue in front of B after 5 days, starting empty? If a pull limit of 4 items is introduced for the queue (A only adds items up to that limit), what is the approximate average wait time for an item entering the queue once the system is in steady state?
Show answer
Under push the queue grows by 8 - 4 = 4 items per day, so after 5 days it holds 20 items. Under pull the queue is capped at about 4 items. B's throughput is 4 items per day, so by Little's Law the wait is about 4 / 4 = 1 day. Throughput stays at 4 items per day in both cases because B is the bottleneck.
Exercise
A team lead says, "Our process is pull because each order is placed in the weekly plan and every step works through the plan in order." Is this a pull system? Give one test you could apply.
Show answer
Not necessarily. A plan that tells each step what to start is a push signal, even when the plan is built from real orders. A test is to ask what makes a given step start work. If steps start items because the plan lists them, regardless of whether the next step has capacity, it is push. A pull system would let a step start new work only when a downstream step signals free capacity or when stock is consumed.
Exercise
Why does the Lean sequence place pull after flow instead of before it?
Show answer
Pull relies on short response times. If work takes weeks to pass through the value stream because of large batches and long waits, a customer signal cannot be answered quickly, so builders fall back on forecasts and inventory. Making work flow first shortens lead time so that building to a real signal becomes practical.