Sub topic 5
Mapping a Value Stream and Measuring Flow Efficiency
This chapter assumes you know the first two Lean principles: value is defined by the customer, and a value stream is every step that turns a customer request into a delivered result. You should also be comfortable with ratios and basic arithmetic. Here you will learn how to draw a value stream map and how to calculate the number that summarizes it, flow efficiency.
What a value stream map is
A value stream map (VSM) is a diagram of every step a piece of work passes through, from the customer's request to delivery. For each step it records how much time the work is actively handled and how much time it waits.
The map is useful because it makes waiting visible. Teams usually describe their process as a list of tasks. A list does not show the hours or days that work spends sitting in a queue between tasks. A map does.
There are two versions of the map:
- The current-state map shows how work flows today. You draw it first, from observation.
- The future-state map shows the flow you want after improvements. You draw it second, from the gaps the current-state map exposes.
Three time measures
Every step on the map carries a few numbers. Three matter most.
- Value-added time (also called process time or touch time) is the time someone is actually working on the item in a way the customer would pay for.
- Waiting time (also called queue time) is the time the item sits idle before the next step starts.
- Lead time is the total elapsed time from the request arriving to the result being delivered. It equals value-added time plus waiting time.
Be careful with "value-added". Some work is necessary but adds nothing the customer values, such as re-entering data or filling in an internal approval form. That work is waste even though someone is busy doing it. When you measure value-added time, count only the activities that change the item in a way the customer would recognize and want.
How to draw a current-state map
Follow these steps.
- Define the start and end. Pick a trigger (for example, "customer order received") and a finish (for example, "order delivered"). A vague boundary produces a vague map.
- Pick one product or service family. Mixing different kinds of work in one map hides the real flow.
- Walk the process. Go where the work happens and follow a real item from start to finish. Do not rely on the documented procedure. The documented procedure is how the process is supposed to run, and the map must show how it does run.
- List the steps in order. Use verbs and keep each step small enough that it has one owner.
- Record times for each step. Measure value-added time and the waiting time before the next step. Use real timestamps from tickets, logs, or order records when you can. Estimates from memory are usually too optimistic.
- Note extras that explain delays, such as rework loops, handoffs between teams, and batch sizes.
- Total the columns and calculate flow efficiency.
The diagram below shows the shape of a simple map. Work moves left to right, and the gaps between steps are queues.
Calculating flow efficiency
Flow efficiency is the share of lead time during which the item is actually being worked on:
flow efficiency = value-added time / lead time
Here is the same order process as the diagram, in code.
# Each step: (name, value-added hours, waiting hours before the next step)
steps = [
("Order entry", 0.5, 8),
("Assembly", 2, 24),
("Inspection", 0.5, 16),
("Shipping", 1, 7.5),
]
value_added = sum(v for _, v, _ in steps) # 4.0 hours
waiting = sum(w for _, _, w in steps) # 55.5 hours
lead_time = value_added + waiting # 59.5 hours
flow_efficiency = value_added / lead_time
print(f"Lead time: {lead_time} h, flow efficiency: {flow_efficiency:.1%}")
# Lead time: 59.5 h, flow efficiency: 6.7%Of 59.5 hours of lead time, only 4 hours involve real work. The other 55.5 hours are waiting. This is typical. Many knowledge-work and service processes have flow efficiency in the single digits or low teens, and a figure around 40% or higher is rare. Do not treat any figure as a universal benchmark, because it depends on the type of work and on how strictly you define value-added.
What the number tells you
The most important consequence is where improvement effort pays off. Look at the order example:
- If you make assembly twice as fast (value-added time drops from 2 h to 1 h), lead time falls from 59.5 h to 58.5 h. Flow efficiency barely moves.
- If you halve the waiting time before assembly and inspection (24 h to 12 h and 16 h to 8 h), lead time falls by 20 h to 39.5 h, and flow efficiency rises to about 10.1%.
Speeding up the people who are already busy has a small effect. Removing the wait has a large one. This is why Lean teams look at queues first.
def flow_efficiency(steps):
va = sum(v for _, v, _ in steps)
lead = va + sum(w for _, _, w in steps)
return lead, va / lead
faster_work = [
("Order entry", 0.5, 8),
("Assembly", 1, 24),
("Inspection", 0.5, 16),
("Shipping", 1, 7.5),
]
less_waiting = [
("Order entry", 0.5, 8),
("Assembly", 2, 12),
("Inspection", 0.5, 8),
("Shipping", 1, 7.5),
]
for label, s in [("faster work", faster_work), ("less waiting", less_waiting)]:
lead, fe = flow_efficiency(s)
print(f"{label}: lead time {lead} h, flow efficiency {fe:.1%}")
# faster work: lead time 58.5 h, flow efficiency 6.8%
# less waiting: lead time 39.5 h, flow efficiency 10.1%Reading a map for waste
Once the map is drawn, look for these patterns.
| Pattern on the map | What it usually means | Typical Lean question |
|---|---|---|
| Long wait before a step | Batching, a bottleneck, or too much work in progress | Why is work arriving faster than this step can take it? |
| Loop back to an earlier step | Rework from defects or unclear requirements | What causes the defect, and can it be prevented upstream? |
| Many handoffs between teams | Lost information and extra queues | Can one team own more of the flow? |
| Approval steps with no change to the item | Control activity that adds no customer value | Is the approval needed, or can the check be built into the work? |
| Step with high work time but low customer value | Overprocessing | Would the customer notice if we skipped this? |
Each pattern ties back to the waste categories you saw earlier, such as waiting, defects, overprocessing, and unnecessary motion or transport.
Percent complete and accurate
Many maps also record a quality measure for each step called percent complete and accurate (%C&A). It is the share of items arriving at the step that the step can use without fixing or asking questions. If inspection receives incomplete assemblies 30% of the time, its %C&A is 70%, and the rework that follows lengthens lead time. A low %C&A points to a cause upstream of the step where the delay appears.
Common errors
- Mapping the documented process. The map must follow real items, or it will miss the informal workarounds and queues that cause delay.
- Averaging away the variation. A mean wait of 24 hours can hide a range from 2 hours to 5 days. Record the spread, or at least a typical and a worst case.
- Counting activity as value. A step that keeps people busy is not value-added unless the customer would want it.
- Mapping too broadly. An entire company on one page produces boxes with no useful numbers. Start with one product family.
- Confusing lead time with cycle time. In a strict sense, lead time is measured from the customer's request, while cycle time is measured from when work starts. Teams use the terms differently, so state your definition on the map.
- Optimizing one step. A local speed-up that leaves queues unchanged does not shorten lead time, as the example above shows.
- Treating the map as the goal. The map is a tool. The value comes from the future-state map and the changes that follow.
From current state to future state
With the current-state map and its flow efficiency in hand, draw the future-state map in three moves.
- Remove steps that add no value and cannot be justified, such as redundant approvals.
- Shrink the queues between the remaining steps by reducing batch sizes and the amount of work in progress. The next chapters cover how.
- Set a target for lead time and flow efficiency, and pick a first improvement that attacks the largest queue.
The map also gives you a baseline. After you make a change, measure again and compare. Without the baseline, you cannot tell whether the change helped.
Exercises
Exercise
A support request spends 1 hour being triaged, waits 20 hours, spends 3 hours being fixed, waits 10 hours for review, spends 1 hour in review, and waits 5 hours for release, after which the fix is delivered. Treat all the working time as value-added. What are the lead time and the flow efficiency?
Show answer
Value-added time is 1 + 3 + 1 = 5 hours. Waiting time is 20 + 10 + 5 = 35 hours. Lead time is 5 + 35 = 40 hours. Flow efficiency is 5 / 40 = 12.5%.
Exercise
In the support example above, the team can either cut the fixing time from 3 hours to 1.5 hours, or cut the 20-hour wait after triage to 10 hours. Which change gives the larger gain in flow efficiency, and why?
Show answer
Cutting the fixing time gives a lead time of 38.5 hours and a flow efficiency of 3.5 / 38.5, about 9.1%, which is lower than before because value-added time also shrinks. Cutting the wait gives a lead time of 30 hours and a flow efficiency of 5 / 30, about 16.7%. The wait reduction is better for both lead time and flow efficiency, because most of the lead time is waiting, not work.
Exercise
A team drew its map from the written procedure and found a flow efficiency of 30%. A later walk of real items shows 12%. Name two likely reasons for the gap.
Show answer
The written procedure leaves out informal queues and handoffs, and it leaves out rework loops. Real items also wait for people, approvals, or batches that the procedure does not mention. Estimating from memory instead of timestamps can add to the gap.