Applying the Five Principles Together
This chapter assumes you know the five Lean principles individually. You should be able to read a simple value stream map, compute flow efficiency, use Little's Law, and describe a kanban board and the Plan-Do-Check-Act (PDCA) cycle. Here you will use them as one sequence on a single process and learn where that sequence goes wrong.
Why the order matters
The principles form a chain. Each one depends on the output of the one before it.
- Specify value. Decide what the customer actually pays for.
- Identify the value stream. List every step that produces that value, including the steps that add none.
- Make work flow. Remove waiting, handoffs, and large batches so work moves steadily.
- Establish pull. Start work only when downstream demand or capacity signals it.
- Pursue perfection. Repeat the cycle, because each improvement exposes the next problem.
Skipping ahead causes common failures. A team that sets WIP limits (principle 4) before it knows what the customer values (principle 1) may run a smooth, well-controlled process that makes the wrong thing. A team that maps a stream (principle 2) without a definition of value has no basis for calling any step waste.
The arrow from perfection back to value is part of the method. Customer needs change, and the process changes with them, so the first principle gets revisited.
A worked case: an order-fulfilment process
Take the order process from the earlier flow-efficiency example. Customers place orders, and the team assembles, inspects, and ships them.
Step 1: Specify value
Suppose interviews show that customers care about two things: receiving a correct product and receiving it quickly and predictably. They do not care how the team is organised or how many internal approvals take place. So value is defined as "a correct order, delivered when promised."
This definition decides what counts as waste. An internal approval that no customer would pay for is a candidate for removal. An inspection step is more subtle. The customer does not pay for inspection as such, but they do pay for a correct product. Lean calls this kind of step necessary non-value-adding work: keep it for now, and try to design it out later by preventing the defects it catches.
Step 2: Identify the value stream
Next you map the process. The data from the earlier example looks like this:
| Step | Value-added (h) | Waiting before next step (h) |
|---|---|---|
| Order entry | 0.5 | 8 |
| Assembly | 2 | 24 |
| Inspection | 0.5 | 16 |
| Shipping | 1 | 7.5 |
The map shows 4 hours of work inside 59.5 hours of lead time. The code below computes the same figures and also reports where the waiting is concentrated, which tells you where to look first.
steps = [
("Order entry", 0.5, 8),
("Assembly", 2, 24),
("Inspection", 0.5, 16),
("Shipping", 1, 7.5),
]
value_added = sum(v for _, v, _ in steps)
waiting = sum(w for _, _, w in steps)
lead_time = value_added + waiting
print(f"Lead time: {lead_time} h")
print(f"Flow efficiency: {value_added / lead_time:.1%}")
worst = max(steps, key=lambda s: s[2])
share = worst[2] / waiting
print(f"Longest wait: after {worst[0]} ({worst[2]} h, {share:.0%} of all waiting)")Running it prints a lead time of 59.5 h, flow efficiency of 6.7%, and a longest wait of 24 h after Assembly, which is 43% of all waiting. Waiting after assembly is the first thing to investigate.
Step 3: Make work flow
Waiting usually has a structural cause. In this process, assembled orders are collected and sent to inspection once a day in one batch. Each order waits for the batch to fill, and the inspector then faces a spike of work. Reducing the batch to one order at a time, or to small batches several times a day, removes most of that queue. Cross-training one more person to inspect also helps, because it removes a handoff bottleneck.
Flow work targets the largest wait first. Reducing a 2-hour wait to 1 hour barely moves lead time. Reducing a 24-hour wait to 4 hours changes it by a third.
Step 4: Establish pull
Once work flows in small units, you need to stop the system from refilling its queues. Without a limit, order entry will keep releasing orders faster than assembly can finish them, and WIP grows again. A WIP limit makes the rule explicit.
WIP_LIMIT = 3
def can_pull_new_work(in_progress):
return in_progress < WIP_LIMIT
def avg_cycle_time(wip, throughput_per_day):
return wip / throughput_per_day
for wip in (30, 10, 3):
print(wip, "items in progress ->", avg_cycle_time(wip, 5), "days")
print(can_pull_new_work(2))
print(can_pull_new_work(3))At a throughput of 5 orders per day, 30 orders in progress means an average cycle time of 6 days. Cutting WIP to 10 gives 2 days, and 3 gives 0.6 days. The last two lines print True and False: with 2 items in progress the team may pull, and with 3 it must finish something first.
Little's Law (average cycle time = WIP / throughput) assumes a stable system. It describes averages over a long enough period. It does not promise that any one order will take exactly that long.
Step 5: Pursue perfection
Each change is an experiment, run as a PDCA cycle:
- Plan: "If we inspect each order as soon as assembly finishes, the 24 h wait after assembly will drop below 6 h."
- Do: Try it for two weeks on one product line.
- Check: Compare measured wait and defect rates with the baseline.
- Act: If it worked, make it standard. If not, record what you learned and form a new hypothesis.
After the change, the bottleneck moves. Perhaps inspection now idles and shipping becomes the longest wait. That is expected, and it is why perfection is a loop and not a final state.
How the principles check each other
The principles are more useful together because each one tests the others.
| If you see this symptom | It suggests a gap in | Question to ask |
|---|---|---|
| Efficient steps but unhappy customers | Value | Did we ask the customer what matters? |
| Improvement projects that never change lead time | Value stream | Did we measure waiting, or only work time? |
| Long queues despite fast workers | Flow | Where do batches form? |
| WIP creeps back up after each cleanup | Pull | Is there a limit, and does anyone enforce it? |
| Gains fade after a few months | Perfection | Who owns the next experiment? |
Choosing a first improvement
Teams often want to fix everything. A better first move is the smallest change with the largest measured effect. Use these criteria:
- Size of the wait. Pick the largest wait on the map.
- Cost and reversibility. Prefer changes you can undo in a week.
- Measurability. You need a baseline before the change, or the Check step has nothing to compare against.
- Local control. Choose something your team can change without waiting for another department.
In the order example, the 24 h wait after assembly passes all four tests. Moving to small-batch inspection is cheap, reversible, measurable with data you already have, and within the team's control.
Common errors
- Optimising a step instead of the stream. Making assembly 20% faster does nothing if work then waits 16 hours for inspection.
- Treating flow efficiency as a target to maximise. Low figures such as 6.7% are common in process work. It is a diagnostic, and the useful signal is the trend and where the waiting sits.
- Applying WIP limits without changing batches. A limit on large batches simply blocks the system for long periods.
- Labelling everything waste. Inspection, compliance checks, and safety steps may be necessary even if the customer never sees them. Remove the need for them gradually and do not just delete them.
- Declaring victory. Without a standing review cadence, the process drifts back within months.
Summary of the cycle on one page
- Define value in the customer's words.
- Map the stream and measure both work time and waiting time.
- Attack the largest wait by shrinking batches and removing handoffs.
- Set WIP limits so the gains are held, and use Little's Law to predict the effect.
- Run each change as a PDCA experiment, then return to step 1 with what you learned.
Exercise
A support team has 24 tickets in progress and closes 6 tickets per day on average. Tickets spend 2 hours being worked on and about 46 hours in total from arrival to resolution. (a) What is the average cycle time by Little's Law? (b) What is the flow efficiency? (c) The team sets a WIP limit of 12 without changing throughput. What is the new average cycle time, and what should the team check before trusting that number?
Show answer
(a) 24 / 6 = 4 days of average cycle time. (b) Flow efficiency = 2 / 46 ≈ 4.3%, so almost all of the time is waiting. (c) 12 / 6 = 2 days. The team should check that throughput really stays at 6 per day, because a very low WIP limit can starve the team or create idle time and lower throughput. It should also check that the system is stable, since Little's Law describes long-run averages and not individual tickets.
Exercise
A team maps its process and finds the longest wait is 30 hours before a manager approval step. Two engineers want to speed up the approval form to save 15 minutes of work time. Using the five principles, what would you ask first, and what first experiment would you propose?
Show answer
Start with value: does the customer care about this approval, or does it prevent a failure the customer would notice? Then look at the stream: the 30 h wait dwarfs the 15 minutes of work, so the form is the wrong target. Look at flow: approvals probably wait in a batch or on one person's availability. A first PDCA experiment could be to approve requests twice a day, or to delegate approval for low-risk requests. Measure the wait before and after, and keep the change only if the wait falls and defect rates stay flat.