Sub topic 6
Principle 3: Make Work Flow
This chapter assumes you have read the chapters on specifying value and identifying the value stream. You should be comfortable with the idea of a value stream map, with value-added time versus waiting time, and with simple ratios. No programming background beyond reading short Python scripts is needed.
What flow means
Once you know what the customer values and which steps produce it, the third Lean principle asks you to make those steps run as a continuous movement. Flow means that a work item moves from one value-adding step to the next with little or no waiting, stopping, or going backward.
Most organizations are built the opposite way. Work is grouped by department. Each department collects a pile of items, processes them in a batch, and passes the batch on. Each department looks busy and efficient. The item, however, spends most of its life sitting in a queue.
Flow shifts attention from keeping resources busy to keeping the work moving. These two goals often conflict. A person who is 100% busy has no slack to pick up an urgent item, so urgent items wait. The Lean view is that the item matters more than the worker's utilization, because the customer pays for the item.
Measuring how well work flows
The clearest measure of flow is flow efficiency. It is the value-added time divided by the total lead time, where lead time is the elapsed time from when the customer asks until they receive the result.
# Each step: (name, value-added hours, waiting hours before the next step)
steps = [
("Order entry", 0.5, 8),
("Assembly", 2, 24),
("Inspection", 0.5, 16),
("Shipping", 1, 7.5),
]
value_added = sum(v for _, v, _ in steps) # 4.0 hours
waiting = sum(w for _, _, w in steps) # 55.5 hours
lead_time = value_added + waiting # 59.5 hours
flow_efficiency = value_added / lead_time
print(f"Lead time: {lead_time} h, flow efficiency: {flow_efficiency:.1%}")
# Lead time: 59.5 h, flow efficiency: 6.7%The order spends 4 hours being worked on and 55.5 hours waiting. Flow efficiency is 6.7%. This is not unusual. In many knowledge-work and service processes, flow efficiency is below 15%. Many teams are surprised the first time they measure it.
Notice what this number tells you about where to look for improvement. If you made the assembly step twice as fast, you would save 1 hour out of 59.5. If you removed half of the waiting, you would save about 28 hours. Shortening the waits is almost always the better first target than speeding up the work.
Why work waits
Work waits for a small number of recurring reasons. Knowing them helps you read a value stream map and decide what to change.
- Queues in front of busy resources. A step with limited capacity accumulates items whenever work arrives faster than it leaves.
- Batching. Items wait for the rest of their batch to be finished before they move on.
- Handoffs between departments. Each handoff adds a queue, and often adds missing information that must be chased.
- Approvals and signatures. The item waits for a person who has many other items to review.
- Rework loops. A defect found late sends the item back to an earlier step, so it passes through the same queues twice.
- Unevenness in the work. Arrivals and processing times vary, so queues form even when average capacity looks sufficient.
Each of these can be seen on a value stream map as a long gap between boxes, or as a triangle showing inventory. Flow work is largely the work of removing or shrinking those gaps.
Practical ways to improve flow
There are several standard moves. They are listed here roughly in the order teams usually try them.
- Make the work visible. You cannot improve movement you cannot see. A board showing every item and its current step is enough to start.
- Reduce batch size. Move items one at a time, or in small groups, instead of waiting for a full batch.
- Limit work in progress. Fewer items in the system means shorter queues. The next two chapters cover this in detail.
- Rearrange the steps around the item. Put the people and tools needed for one kind of item close together, or in one cross-functional team, so the item does not cross departmental boundaries.
- Balance the work to the pace of demand. Lean calls this takt time: the available working time divided by the number of items the customer demands. If the customer wants 40 items in an 8-hour day, takt time is 12 minutes. Each step should be able to finish an item in about that time.
- Remove the causes of stoppage. Fix the defects, missing information, and equipment failures that make items stop.
The sixth move deserves emphasis. A flowing process is fragile. When items move one at a time with no buffer, any defect stops the whole line. This is intended. The stoppage makes the problem impossible to ignore, which is what drives the team to fix its cause. Teams that remove the buffers without fixing the underlying problems often get a bad first experience and abandon flow. Reduce the buffers gradually, and fix the problems that each reduction exposes.
Resource efficiency versus flow efficiency
The tension between keeping people busy and keeping work moving is easy to state and hard to feel. The following table compares the two views.
| Aspect | Resource efficiency view | Flow efficiency view |
|---|---|---|
| Goal | Keep every person and machine busy | Move each item to the customer quickly |
| Typical measure | Utilization per person | Lead time and flow efficiency per item |
| Handling of work | Large batches to avoid changeovers | Small batches or single items |
| Effect on queues | Queues grow, since there is no slack | Queues stay short, since there is slack |
| Response to a problem | Work around it and keep going | Stop, find the cause, and fix it |
Neither view is simply right. Changeovers, setups, and handoffs have real costs, and very small batches are only worth it if those costs are low. The Lean answer is usually to reduce the cost of a changeover so that small batches become affordable, instead of accepting large batches as a fact of life.
Why high utilization hurts
A common mistake is to treat 100% utilization as the target. Queueing theory shows why this fails. As a step's utilization approaches 100%, the average wait grows very fast. Going from 70% to 90% utilization does not add a little waiting. It roughly triples the queueing delay, and going from 90% to 95% almost doubles it again.
The following small script shows the shape of this effect using the simple single-server queue model, where average time waiting in the queue, as a multiple of the average service time, is utilization divided by one minus utilization.
def queue_wait_multiple(utilization):
"""Average wait in queue, in multiples of average service time (M/M/1 model)."""
if not 0 <= utilization < 1:
raise ValueError("utilization must be at least 0 and below 1")
return utilization / (1 - utilization)
for u in (0.5, 0.7, 0.8, 0.9, 0.95, 0.99):
print(f"{u:.0%} busy -> waits {queue_wait_multiple(u):.1f} x service time")Running it prints 1.0 at 50% utilization, 2.3 at 70%, 4.0 at 80%, 9.0 at 90%, 19.0 at 95%, and 99.0 at 99%. The model is a simplification, since real work rarely has exactly random arrivals and a single worker. The direction is reliable, though. Slack capacity is what lets a process absorb variation without building queues.
Edge cases and common errors
- Optimizing one step. Speeding up a step that is not the constraint changes nothing for the customer. Work piles up in front of the next slow step instead. Measure the whole stream before choosing a step to improve.
- Moving the queue instead of removing it. Splitting a department's backlog into several smaller queues, or hiding it in an email inbox, does not shorten lead time. Count total items waiting across the whole stream.
- Forcing flow on highly variable work. Some work, such as a custom engineering study, cannot be reduced to a steady rhythm. You can still make it visible, limit work in progress, and shorten the waits between steps, even if you cannot reach a takt time.
- Confusing speed with flow. Asking people to work faster raises utilization and often makes waiting worse. Flow comes from fewer interruptions and fewer queues, not from faster effort.
- Ignoring rework. An item that fails inspection and loops back can double its lead time. Count rework loops on the map and treat each as a defect in the process.
- Measuring only average lead time. Averages hide the slow items that annoy customers most. Look at the spread, such as the slowest 15% of items, as well as the mean.
How flow connects to the other principles
Flow depends on the first two principles. If you have not defined value and mapped the stream, you do not know which steps to connect and which to remove. Flow in turn creates the conditions for pull. Once items move with short queues, the downstream step can signal when it is ready for more, and the upstream step can wait for that signal instead of producing ahead. The chapters that follow cover the two tools that make this work: limiting batch size and work in progress, and Little's Law, which links work in progress to lead time.
Exercise
A repair process has 3 hours of hands-on work per ticket. The average ticket takes 5 days of 24 hours each to complete from request to return. (a) What is the flow efficiency? (b) A team proposes making the hands-on work 20% faster. What happens to flow efficiency and lead time, and what would you suggest instead?
Show answer
(a) Lead time is 5 x 24 = 120 hours. Flow efficiency is 3 / 120 = 2.5%. (b) A 20% reduction takes the hands-on work to 2.4 hours, so lead time falls by 0.6 hours to 119.4 hours. Flow efficiency becomes 2.4 / 119.4, which is about 2.0%, so it actually drops, and the customer sees almost no difference. Instead, study the 117 hours of waiting: find the queues, handoffs, and approvals, and reduce batching and work in progress so tickets spend less time waiting.
Exercise
A step has an average service time of 10 minutes. Using the single-server queue model, how long is the average wait in the queue when the step is 80% busy, and when it is 95% busy? What does this suggest about running a step at 95%?
Show answer
At 80% utilization the wait is 0.8 / 0.2 = 4 times the service time, or 40 minutes. At 95% it is 0.95 / 0.05 = 19 times the service time, or 190 minutes. Raising utilization by 15 percentage points makes the wait nearly five times longer. A step run at 95% will make items wait much longer, so it is better to keep some slack or reduce the work arriving at that step.
Exercise
A customer wants 60 items in an 8-hour working day. What is the takt time, and what does it tell a step that needs 9 minutes per item?
Show answer
Available time is 8 x 60 = 480 minutes, so takt time is 480 / 60 = 8 minutes per item. A step that needs 9 minutes per item cannot keep up with demand on its own. It will build a queue, so it needs more capacity, such as a second worker or a shorter task, or the work needs to be rebalanced across steps.