Sub topic 4
Principle 2: Identify the value stream
This chapter assumes you have read Principle 1 and can state what a customer values in a product or service. It also assumes you know how a business process turns inputs into outputs, and that you are comfortable with simple ratios. Agile, manufacturing, or service-operations experience helps but is optional.
What a value stream is
A value stream is the full set of actions needed to take one product or service from the customer's request to the customer's hands. It includes the actions that add value and the ones that do not. It also includes the waiting between actions.
Three parts of that definition cause most of the later mistakes.
- It is end to end. The stream starts when the customer asks for something, or when the need arises. It ends when the customer has the result. It does not start or stop at your team's inbox or outbox.
- It is specific to one product or service. You trace one product family at a time. A company has many value streams, not one.
- It includes everything that happens. Idle time, rework, approvals, handoffs, and queues are part of the stream even though nobody "does" them.
Principle 1 gives you the target: what the customer values. Principle 2 gives you the path: every action currently standing between the request and that value. You cannot improve flow or pull until you can see this path.
Three kinds of activity
Womack and Jones sort every activity in the stream into one of three groups. The sorting is relative to the value you specified in Principle 1.
| Kind of activity | Meaning | Example in an order process | What to do |
|---|---|---|---|
| Value-creating | The customer would pay for it, and it changes the product toward what they want | Assembly, packing the right item | Protect and improve it |
| Necessary but non-value-adding (type one muda) | The customer does not value it, but the process cannot currently work without it | Inspection with today's quality level, legally required checks | Reduce or design out over time |
| Avoidable waste (type two muda) | Neither valued nor necessary | Waiting in queues, re-keying data, rework, searching for information | Remove now |
The middle group is the one people argue about. "Required" always means required under the current design. An inspection step exists because the upstream process produces defects. Fix the upstream process and the inspection can shrink or disappear. Treat type one muda as a target for redesign, not as untouchable.
Regulation is a different case. An audit or a safety check mandated by law stays in the stream. You can still ask whether it is done in the cheapest way, and whether it waits in a queue.
Material flow and information flow
Every value stream carries two flows.
- Material flow is the physical item, document, or digital artifact moving from step to step.
- Information flow is the signal that tells each step what to do, how much, and when. Examples are orders, schedules, forecasts, tickets, and approvals.
Beginners tend to map only the first. Much of the waste sits in the second. If a planning department sends a weekly forecast-based schedule to every step, each step builds to the schedule instead of to actual demand. That creates queues and overproduction, and you cannot see it by following the item alone. When you walk a stream, follow the thing being made and also ask at each step, "How does this step know what to do next?"
In the diagram, solid arrows are material flow and dashed arrows are information flow. The weekly schedule into assembly is the kind of information path that later chapters on pull will replace.
Walking the stream: a worked example
Suppose you have mapped an order process and recorded the time each step takes and the time the order waits before the next step. You then label each entry as value-creating, required, or waste. Waiting is always waste, because the customer gets nothing from it and the process does not need it.
The following script tallies hours by category.
# Each entry: (activity, category, hours)
# Categories: "value" (value-creating), "required" (necessary non-value-adding),
# "waste" (avoidable waste, including all waiting)
activities = [
("Order entry", "value", 0.5),
("Wait for assembly slot", "waste", 8),
("Assembly", "value", 2),
("Wait for inspector", "waste", 24),
("Inspection", "required", 0.5),
("Wait for carrier pickup", "waste", 16),
("Shipping", "value", 1),
("Wait for delivery slot", "waste", 7.5),
]
totals = {"value": 0.0, "required": 0.0, "waste": 0.0}
for _, category, hours in activities:
totals[category] += hours
lead_time = sum(totals.values())
for category in ("value", "required", "waste"):
hours = totals[category]
print(f"{category:<9} {hours:5.1f} h {hours / lead_time:6.1%}")
print(f"Lead time: {lead_time} h")Expected output:
value 3.5 h 5.9%
required 0.5 h 0.8%
waste 55.5 h 93.3%
Lead time: 59.5 hTwo observations follow from the numbers.
- More than nine-tenths of the elapsed time is waiting. Speeding up assembly by 20 percent would save 24 minutes out of 59.5 hours.
- The biggest single item is the 24-hour wait for the inspector. That is a queue, so it points to a flow problem. Later chapters deal with that. For Principle 2 the job is only to see it and name it.
Here the "required" category contains inspection, which is the common case. The earlier measure of flow efficiency counts all four process steps as value-added time, giving 4.0 hours and 6.7 percent. This chapter splits that 4.0 hours more strictly, which gives 3.5 hours. Both are valid. State your definition when you report the number, because comparisons between teams fall apart when each team counts differently.
Deciding the boundaries
The hardest practical question is where the stream starts and stops. Use these rules.
- Start at the customer's trigger. For an order process, that is when the customer commits to the request, not when your system creates a record.
- End at the customer's receipt. Delivery is not done when the parcel leaves your dock. It is done when the customer can use it.
- Cross departments freely. A stream that matches one department's boundaries usually shows only that department's slice. Delay often hides in the handoffs.
- Include suppliers and distributors when they matter. Womack and Jones argue that real value streams stretch across companies. In practice you map what you can influence first, then note the upstream and downstream segments you cannot change yet.
Pick one product family or request type for each map. Items belong to the same family if they pass through similar steps and equipment. If you mix families with different routes, the map becomes an average that describes no real order.
Common errors
- Mapping the org chart. Drawing boxes for departments and arrows for reporting lines shows who is involved, not what happens to the work. Follow the work item itself.
- Mapping the designed process. The documented procedure and the real behavior differ. Walk the actual path, ask the people doing the work, and trace real items from start to end.
- Counting only touch time. Recording just the activities and leaving out queue times hides the waste. Waiting is usually where most of the lead time sits.
- Calling everything value-adding. People tend to defend their own steps. Anchor each classification to the customer value from Principle 1, not to how hard the step is or how long it has existed.
- Optimizing a local step. Making one step faster does not shorten lead time if the work then waits at the next step. Judge changes by their effect on the whole stream.
- Treating the map as the goal. The map is a tool for choosing a first improvement. A beautiful map with no change after it is itself waste.
Edge cases
Knowledge work and services. There is no physical item, so the work item is an information artifact such as a ticket, claim, or loan application. The same categories apply. Waiting is often invisible because the item sits in a queue as a record. Count the time between status changes to reveal it.
Shared resources. One inspector or one machine may serve several streams. A queue before that resource affects all of them. Map each stream separately, then note the shared resource as a point where streams interact.
Rework loops. If a failed inspection sends the item back to assembly, the stream is not a straight line. Record the loop and how often it occurs. A 10 percent rework rate adds that share of assembly and inspection time to the average lead time.
Variable demand. Lead times differ between busy and quiet periods. Record the typical case and the range, and note when the measurement was taken.
What this principle gives the next ones
Once you can see the whole stream and sort its parts, you have what you need for Principle 3. Flow needs you to know which steps create value and where work stops. Pull needs you to know where information is missing or distorted. The next chapter turns your sorted list into a visual map and a measured flow efficiency.
Exercise
A support team reports that each ticket takes 10 minutes of agent work, but customers wait on average 3 days for a resolution. The team proposes training agents to work 20 percent faster. Using the idea of a value stream, explain what they should do first and why the proposal may fail to help.
Show answer
They should map the full stream from the customer's request to the resolution, recording both agent work time and the waiting time between steps, and classify each entry as value-creating, required, or waste. Agent work takes 10 minutes, while the elapsed time is about 3 days (4,320 minutes), so the work is a tiny fraction of lead time. A 20 percent speedup saves 2 minutes, which is far below 0.1 percent of the lead time. Most of the delay is in queues and handoffs, so the map should locate the longest waits and target those first.
Exercise
In the order example, inspection takes 0.5 hours and the order waits 24 hours for the inspector. Which kind of activity is the inspection, which kind is the wait, and which one would you attack first?
Show answer
Inspection is necessary but non-value-adding (type one muda), because it exists due to current quality levels. The 24-hour wait is avoidable waste (type two muda). Attack the wait first, since it is far larger and can be removed without redesigning quality. Reducing the need for inspection is a longer-term goal.