Sub topic 7
Waiting: idle people, machines, and work
Working model
Assume you understand that a process turns inputs into outputs and that elapsed time can include both work and delay.
Waiting is waste when a person, machine, material, decision, or work item sits idle instead of moving the process toward the customer’s desired result. In Lean, the customer usually does not pay for the delay. Waiting is therefore usually non-value-added activity.
Some delays are necessary under current conditions. A safety check, legal approval, or batch curing time may be required. These delays still deserve measurement and improvement. Pure waste occurs when the delay has no useful purpose, such as an order sitting in an unattended queue.
Waiting can appear in several forms:
| Setting | Example of waiting |
|---|---|
| Manufacturing | A machine waits for material or a previous operation to finish |
| Office | An invoice waits for approval in an email inbox |
| Software | A developer waits for a test environment or code review |
A useful test is to ask, “What is this item waiting for, and why can the next step not start?” Record the item, the start time, the end time, and the reason. Avoid labeling every pause as a people problem. The cause may be scheduling, unclear ownership, batch processing, equipment downtime, or uneven workloads.
How waiting spreads
Waiting often connects to other wastes. Large batches create queues. Queues increase inventory and hide defects. Unplanned machine downtime creates waiting for operators and may cause overproduction elsewhere as teams build extra stock. A missing decision can cause motion as people repeatedly ask for updates.
The visible delay may not be the root cause. For example, “waiting for approval” describes the condition, but the cause may be an unclear approval rule or one person receiving every request.
Finding and measuring waiting
Observe the work where it happens, often called a gemba walk. Follow one item from request to completion. Mark every queue, handoff, interruption, and idle period on a simple process map.
Two basic measures are useful:
- Lead time is the total elapsed time from request to delivery.
- Process cycle efficiency is value-added time divided by total lead time.
For example, a request may require 35 minutes of useful work but take 400 minutes from start to finish. Its process cycle efficiency is 8.75%, so most elapsed time is delay or other non-value-added time.
steps = [
("Receive request", 5, False),
("Wait in queue", 240, False),
("Prepare quote", 30, True),
("Wait for approval", 120, False),
("Send quote", 5, True),
]
lead_time = sum(minutes for _, minutes, _ in steps)
value_added_time = sum(minutes for _, minutes, value_added in steps if value_added)
waiting_time = sum(minutes for _, minutes, value_added in steps if not value_added)
print(f"Lead time: {lead_time} minutes")
print(f"Waiting and other non-value-added time: {waiting_time} minutes")
print(f"Process cycle efficiency: {value_added_time / lead_time:.1%}")Little’s Law links waiting to work in progress: average lead time equals average work in progress divided by throughput. If a team completes 20 items per day and has 60 items in progress, the average lead time is about 3 days. Reducing work in progress to 30 items can reduce average lead time to 1.5 days if throughput stays stable.
Choosing countermeasures
Match the response to the cause:
- Use a pull system or kanban limit when too much work enters a constrained step.
- Use standard work when handoffs or decisions vary.
- Use clear service-level rules when requests have no priority or owner.
- Use preventive maintenance when equipment failures cause idle time.
- Cross-train people when one specialist becomes a bottleneck.
- Automate status updates when people spend time asking where work is.
Measure the delay again after the change. A shorter queue with more defects is not an improvement.
Exercise
A team has 40 items in progress and completes 10 items per day. What is the average lead time under Little’s Law, and what could happen if work in progress is cut to 20 items while throughput remains 10 items per day?
Show answer
The average lead time is 40 / 10 = 4 days. At 20 items in progress, it would be 20 / 10 = 2 days, assuming the averages remain stable.