Sub topic 13
Finding Waste: Gemba Walks and Value Stream Maps
Assume you understand the basic idea of customer value and the eight TIMWOODS wastes. You should also be comfortable reading simple process times and quantities. This chapter shows how to find waste in the actual workflow instead of relying on reports or assumptions.
Start at the gemba
A gemba walk is a structured observation of work at the place where it happens. The Japanese word gemba means “the actual place.” In manufacturing, this may be a production line. In an office, it may be a claims desk. In software, it may include the issue tracker, development tools, test environment, and deployment pipeline.
A gemba walk is not a performance inspection. The goal is to understand the process and expose problems that normal summaries hide.
Before walking, define:
- The process start and end, such as “customer request received” through “working answer sent.”
- The product or service being followed.
- The time period and sample size.
- The observations you will record.
- The people who perform or support the work.
Follow one item from start to finish when possible. Record facts rather than conclusions. For example, write “ticket waited 18 hours for review,” not “the team is slow.” Ask open questions such as “What happens next?” and “What prevents this from moving now?”
Useful observations include:
- Processing time and waiting time.
- Queues and work in progress.
- Handoffs between people or teams.
- Repeated data entry or searching.
- Rework, defects, and approvals.
- Interruptions and missing information.
- Movement of materials, documents, or digital work.
Build a current-state value stream map
A value stream map (VSM) is a visual model of how work and information flow through a process. A current-state map describes what happens now. A future-state map describes a proposed improvement, so create the current-state map first.
For each process step, capture:
- Cycle time: hands-on time to complete the step.
- Wait time: elapsed time before the next step begins.
- Work in progress (WIP): items started but not finished.
- First-pass yield: the percentage completed without rework.
- Information triggers: signals, requests, schedules, or approvals that start work.
A simple map can use boxes for process steps, arrows for flow, and queues between steps. Add a timeline beneath it to separate value-adding time from waiting time.
The map helps connect observations to wastes. A large queue may indicate inventory and waiting. Frequent movement between locations may indicate transportation. Repeated clarification may indicate defects or over-processing. A review loop shows rework.
Turn observations into action
Do not treat every delay as a separate problem. Group observations by pattern, then ask why the condition exists. For example, a queue before testing may result from batching, limited test capacity, unclear entry criteria, or unstable inputs.
A practical sequence is:
- Observe and timestamp several items.
- Draw the actual sequence and queues.
- Mark each waste with a short factual note.
- Check the pattern with the people doing the work.
- Select one constraint or repeated delay for root-cause analysis.
- Measure the process again after a countermeasure.
A map is useful only when it reflects reality and leads to a testable change.
Exercise
During a walk, five support requests each spend 20 minutes being handled but remain open for 2 days. What should the current-state map emphasize?
Show answer
It should show the 20 minutes of processing separately from the 2 days of elapsed time, identify the queues and handoffs causing the delay, and record the WIP and information needed at each handoff.