Sub topic 14
Measuring Waste: Lead Time, Cycle Efficiency, and Little’s Law
Assume you can describe a process as ordered steps and record elapsed time, work in progress, and completed items. You do not need advanced statistics. The goal is to turn observations into evidence about waste.
Lead time and value-added time
Lead time is the total elapsed time from the start of a process to the customer receiving its output. It includes processing, queues, approvals, transport, rework, and all other delays.
Value-added time is the time spent changing the product or service in a way the customer needs and would recognize as useful. Preparing an accurate quote may be value-added. Waiting for an approval is not.
Lean also distinguishes necessary non-value-added work from pure waste. Compliance checks may be required even though the customer would not pay for them directly. Waiting caused by an avoidable queue is pure waste.
| Measure | Meaning | Typical waste signal |
|---|---|---|
| Lead time | Total elapsed time | Long queues or delays |
| Value-added time | Time that creates customer value | Small share of total time |
| Process cycle efficiency | Value-added time divided by lead time | Low percentage |
Process cycle efficiency (PCE) is:
PCE = value-added time / lead time
For example, suppose a quote process takes 400 minutes from request to delivery. Only 35 minutes are spent preparing and sending the quote. The PCE is 35 ÷ 400 = 8.75%, or about 8.8%. The remaining time deserves investigation.
steps = [
{"name": "Receive request", "minutes": 5, "value_added": False},
{"name": "Wait in queue", "minutes": 240, "value_added": False},
{"name": "Prepare quote", "minutes": 30, "value_added": True},
{"name": "Wait for approval", "minutes": 120, "value_added": False},
{"name": "Send quote", "minutes": 5, "value_added": True},
]
lead_time = sum(step["minutes"] for step in steps)
value_added_time = sum(
step["minutes"] for step in steps if step["value_added"]
)
pce = value_added_time / lead_time
print(f"Lead time: {lead_time} min")
print(f"Value-added time: {value_added_time} min")
print(f"Process cycle efficiency: {pce:.1%}")Little’s Law: connecting WIP and lead time
Work in progress (WIP) is work that has started but is not finished. Little’s Law relates average WIP, average throughput, and average lead time:
WIP = throughput × lead time
Rearranged:
Lead time = WIP / throughput
If a team has 60 open requests and completes 20 requests per day, its average lead time is about three days. If the team reduces WIP to 30 requests while maintaining the same throughput, average lead time falls to about 1.5 days.
def lead_time_days(wip_items, throughput_per_day):
"""Little's Law: average lead time = WIP / throughput."""
return wip_items / throughput_per_day
print(lead_time_days(60, 20)) # 3.0 days
print(lead_time_days(30, 20)) # 1.5 daysLittle’s Law describes averages. It does not promise that every item will finish in exactly the calculated time. Do not mix units: use items per day with days, or items per hour with hours. Also check that the process is reasonably stable. A sudden backlog, changing demand, or incomplete work counts can make the estimate misleading.
Exercise
A process has 48 items in progress and completes 16 items per day. What average lead time does Little’s Law predict? If 12 minutes of a 180-minute process are value-added, what is its PCE?
Show answer
The predicted lead time is 48 ÷ 16 = 3 days. The PCE is 12 ÷ 180 = 6.7%.